Topic 1 - Introduction to Project Management Flashcards
What are the 5 process groups of project management?
- Initiating
- Planning
- Executing
- Monitoring and Controlling
- Closing
Why is construction project management needed?
- profits are determined by the project managers ability to save money by good planning and decision making
- the more uncertainty in the project, the greater the need for more project management
- conditions such as technical complexity, timely completion, resource limitations, and substantial costs puts a lot of emphasis on having good project management
Construction Project Stages
Planning:
- concepts/needs/ideas
- design
- planning
Execution:
- construction
- delivery/close-up
- operation
Key project participants?
Owner
- public
- private
Designer
-architects/engineers
Construction
- general contractor
- specialty contractor
- trades
- material suppliers
- equipment suppliers
Others
- financial institutions
- insurance companies
- government agencies
Who is a Principal-in-Charge? What does he do?
who is an officer in charge?
Architect
-individual who makes the desicion regarding signing a contract and may be involved in obtaining it
Contractor
Role of Superindenent?
same as PM, but on a physical construction level
- 1 super per project, while 1 pm might do many projects
- on smaller projects, may be the only member of the contractors management
Project engineer role?
Field Engineer role?
Contractor Foreman role?
Reports to PM
-submits agreements, material submittals, liek a project coordinator
Reports to pm
- same as project engineering, but on-site and more hands on
- QA QC
- part of labor force (not management)
- directs labor creq
Project delivery methods?
DB - design builds
DBB - design-bid-build
DBB - Design bid build
Design
-complete design
Bid
-find fixed price bids
Build
- select contractor
- design team ensures construction is to specification and authorizes payments
DB - Design Build
Select contractor before design is complete
Design
Build
- single entity (joint venture, subcontract, or single firm) delivers design and construction
- single point of contract/responsibility
Difference between DB and DBB?
DB has fast delivery and saves cost
Relationships in DBB
Owner - Architect/Engineer and Owner-General contractor have a contractual relationship
Architect/Engineer – General contractor
observation only
Relationship in DB
Owner — design/builder contractual relationship
-1 entity takes care of design+build (joint venture, subcontract, or single firm)
Design-builder has a design team (architect/engineer) and construction team (general contractor)
Design/Construction Manager (D/CM)
Owner + prime contractor contractual relationship
Owner + Design/construction manager contractual relationship
Design/construction manager has an architect and construction team
Design/construction manager’s construction team works (non contractual) with prime contractor(s)
Professional Construction manager (PCM)
Owner + prime contractor contractual relationship
Owner + professional construction manager contractual relationship
Owner + Architect/engineer contractual agreement
Professional construction management works (not contractual) with architect/engineer
Professional Construction manager works (not contractual) with prime contractor(s)