Topic 3 - Project Planning and Scheduling Flashcards

1
Q

WBS (work breakdown structure) is?

A

the process of subdividing project deliverables and project work into smaller, more manageable components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a work package? where is it located in the WBS?

A

Work package is planned work (can be scheduled, cost estimated, monitored, controlled)

-lowest level WBS components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Benefits or bar/grantt charts

Primary use?

A
  • simple
  • represent progress
  • commonly used for scheduling crews and equipment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Linear schedules?

advantages?

A
  • used to schedule repetitive activities
  • good for managing resources (e.g location)
  • capable of identifying space and resource conflicts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Purpose of project scheduling?

A

(1) define activities, durations, and relationship logic to implement the project plan
(2) monitor, update, and communicate the schedule to reflect current status and impact of project changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Defenition of TF / FF

A

TF (amount of time you can delay an activity without delaying the project)
=LF - EF

FF - amount of time you can delay an activity without delaying any following activities

FF = minimum(ESj) - EFi -LAG
j is any following activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When do u take minimum values/maximum values in critical path method?

A

max values for ES, EF

min values for LS, LF (backwards)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Time scaled logic diagram

  • blend of what?
  • advantage over bar chart?
A
  • blend of precedence network and gantt chart

- advantage is their inclusion of activity relations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Milestone?

A

points in time that have been identified as being important intermediate reference points during project delivery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly