Topic 11 - Aggregate Production Planning and Master Scheduling Flashcards
Long-Term plans
Multiyear
*Facility location
*Product mix
*Product design
*Supply chain design
Intermediate plans
6-18 months with monthly or quarterly time increments
*Aggregate planning,
*Inventory Management
*Workforce
Short-term plans
6 months or less with weekly or daily increments
*Master production scheduling (Disaggregation)
*Dependent demand
*Detailed production planning
What are some techniques to adjust capacity?
*Hire Temp workers
*Overtime/ idle time
*Part-Time workers
*Stockpile inventories
*Sub-contracting
What are some ways to manage demand?
*Pricing
*Promotion
*Early Orders
*Back orders
*Exporting
*Complementary products
What are the Basic Aggregate Planning strategies?
1) Chase demand strategy
2) Level output/work force strategy
3) A combination of both
Chase demand strategy
Matching capacity to demand
Planning output set at forecasted demand
Meeting variations in demand with overtime, subcontracting & Part-time/temporary workers
*Conditions: Expensive or short-life inventory, capacity is expensive
Level output/workforce strategy
Maintain steady rate of output
Smooth production, but lots of inventory each month- Inventory cost
Meeting variations in demand with inventories
Conditions: High hiring/firing cost, skilled workforce requirement, intensive training needs