Tohoku and Haiti Case study Flashcards
Haiti : magnitude
7.0
Haiti : P Deaths
230,000
Haiti : P vulnerability
V.poor healthcare, sanitation, literacy rates, substandard housing.
Haiti : P Homeless
1.3 million
Haiti : P Infrastructure destruction
50+ hospitals, 1300+ schools, transport + communication links and main prison destroyed
Haiti : S unemployment
1/5 lost job due to building collapse
Haiti : S disease
Too many bodies to bury => bodies left in street => cholera spread
Haiti : IR EU aid
$330 million given by EU
Haiti : IR Homelessness
810,000 placed in aid camps. 1 million tarpaulin shelters provided.
Haiti : IR Community rescue
Due to transport links (airport + port destroyed) help to long time to arrive. Communities had to save each other.
Haiti : IR Government
US re-established a working government as presidential palace destroyed
Haiti : LTR Homelessness
1 million still homeless year after
Haiti : LTR Schooling
Temporary schools created with new teacher trainees
Haiti : LTR Port-au-Prince reconstruction
Reduced in size and stricter building codes
Tohoku : P deaths
15,000 deaths (majority tsunami)
Tohoku : Magnitude
9.0
Tohoku : Focus
V.shallow (19km)
Tohoku : P Electricity and water
4.4 million without power, 1.5 million without water
Tohoku : P Trains
1100 sections of train track damaged, but only 4 trains derailed due to early warning system
Tohoku : P Costal areas (earthquake)
All costal areas 130km from epicentre destroyed
Tohoku : S Tsunami size & speed
40m height, 10 mins to reach shore
Tohoku : S Tsunami infrastructure damage
$300 billion lost + factories had to shut production
Tohoku : S Fukushima Daichi power plant
Nuclear meltdown, massive amounts of radiation emitted, exclusion zone still in place
Tohoku : IR JSDF Planes
Within 30 minutes Japanese Self Defence Force aircraft in air and doing reconissence
Tohoku : IR JSDF Land
Teams on ground had cleared debris within 2 days
Tohoku : IR bullet trains
Automatically stopped due to early warning system
Tohoku : IR Dead
Buried dead in mass graves => no spread of disease
Tohoku : LTR Nuclear Power
All 55 nuclear power plants shut down
Tohoku : LTR Factory production
Many companies (I.E. Toyota) did not rebuild and instead relocated abroad
Tohoku : LTR Ports
Reopened by end of march (took place on 11th of march, 2011)
Tohoku : LTR Railway
Fully reopened by September (took place on 11th of march, 2011)