time management Flashcards

1
Q

processes of time management (7)

A
  1. planning schedule management
  2. defining activities
  3. sequencing activities
  4. estimating activity resources
  5. estimating activity durations
  6. developing the schedule
  7. controlling the schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is used to develop a schedule management plan (3)

A
  • expert judgement
  • meetings
  • analytical techniques
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what does a schedule management plan include (2)

A
  • development of project schedule model

- the scheduling methodology and tool to use when developing the project schedule model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what does an activity list include (3)

A
  • the activity name
  • an activity identifier or number
  • a brief description of the activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what does activity attributers provide (5)

A
  • successors
  • predecessors
  • leads and lags
  • logical relationships
  • constrains
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is a milestone

A

a significant event that normally has no duration (a marker)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what does it take to complete a milestone

A

having done several activities prior

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what are the things sequencing activities include (2)

A
  • reviewing activities and determining dependencies

- determining activities leads to developing critical path analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

3 types of dependancies

A
  • mandatory
  • discretionary
  • external
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is a network diagram (PERT charts)

A

a schematic display of the logical relationships among project activities and their sequencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what does arrow diagraming method show (2)

A
  • finish-to-start dependancies

- activities in the form of arrows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what does estimating activity resources include (2)

A
  • determining the quantity and type of resources that will be assigned to each activity
  • resources are people, equipment, and materials.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what does estimating activity duration include (3)

A
  • the actual amount of time worked on an activity plus elapsed time
  • effort is the number of workdays or work hours required to complete a task
  • people doing the work should help create estimates, and an expert should review them
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what is a three point estimate (3)

A

an estimate that includes an

1) optimistic estimate (best case scenario
2) most likely estimate (expected scenario)
3) pessimistic estimate (worst-case scenario)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

tools and techniques used to develop the schedule (3)

A

1) gantt charts
2) critical path analysis
3) PERT analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what symbols does a gantt chart include and explain their meaning (4)

A
  • a black diamond: a milestones
  • thick black bars: summary tasks
  • lighter horizontal bars: durations of tasks
  • arrows: dependencies between tasks
17
Q

milestones should be SMART:

A
Specific
Measurable
Assignable
Realistic
Time framed
18
Q

what is a critical path

A

the longest path through the network diagram and has the least amount of slack or float

19
Q

what happens if one or more of the activities on the critical path takes longer than planned

A

the whole project schedule will slip unless the project manager takes corrective action

20
Q

using CPA to shorten schedule

A
  • shortening durations of critical activities/tasks by adding more resources or changing their scope
  • fast tracking activities by doing them in parallel or overlapping them
21
Q

what is PERT

A

a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates

22
Q

what estimate does PERT used

A

three point estimate

23
Q

PERT formula *

A

( optimistic time + 4(most likely time) + pessimistic time ) / 6

24
Q

what are the goals of controlling the schedule (4)

A

to know

  • the status of the schedule
  • influence factors that cause schedule changes
  • determine that the schedule has changed and manage changes when they occur
25
Q

tools and techniques used when controlling the schedule

A
  • progress reports
  • a schedule change control system
  • project management software, including schedule comparison charts