Time Flashcards

1
Q

An extension of time regime is required because otherwise an ommission by the Principal that delays the Contractor will set time “at large”.

A

Peak Constructions (Liverpool) Ltd v McKinney Foundation Ltd (1970) EWCA

Bifold delay - redesign of defective pillars - delay in instructions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A discretionary power to grant an EOT, even if contractor is time barred, MUST be granted for the Principal’s delay.

A

Peninsula Balmain Pty Limited v Abigroup. Contractors Pty Limited [2002] NSWCA

Contractor time barred - AS2124 now often amended - Principal’s benefit only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

It is permissable to bring a global claim where it is impractical to disentangle the part of the loss attributable to each claim, and where difficulty has not bee caused by the contractor’s delay.

A

John Holland Construction and Engineering Pty Ltd v Kvaerner R J Brown Pty Ltd (1996) VSC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Where the Contractor has programmed to complete early and has assumed a contractual obligation to so complete, the Owner has an obligation to co-operate with the accelerated program.

A

Ailleraji Ply Lid (illfiq) v Groeoll Lid (1994) VSC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Generally, there is no obligation to co-operate with the Contractor’s accelerated program.

A

Glenlion Constructions Ltd v The Guiness Trust (1987) (UK)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between float and contingency?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Without CPM at commencement, there is no yardstick to analyse individual delay . A judge must make a ‘fair and reasonable’ apportionment of the gross delay.

A

City Inn v Shepherd Constructions [2007] (Scotland)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Will the wrongful failure to grant a DEOT re-enliven the prevention principal?

A

No.

Judge or arbitrator can simply award the appropriate extension.

(Dado’s Article)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the two contractual mechanism for protecting the principal from the prevention principal?

A

They are:

  1. Time bar - Contractor fails to submit on time - Turner.
  2. DEOT - Presence in contract means court can open up decision, grant EOT and “cure” prevention.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly