General Construction Law Flashcards
A Principal can demand the contractor perform all work “indispensably necessary” to the completion of the work, even if not specifically referred to in the contract.
Walker v Council of the Municipality of Randwick (1929) NSWSC
Retaining wall - ‘whole of the works’ - sand bank actually 12ft, not 6ft.
The scope of the contract can be a itterative process.
Multiplex Constructions v Epworth Hospital (unreported) (1996) VSCA.
Hospital construction - no design fixed at the date of tender - design evolving, though right to develop not open ended.
Absent a specific contractual term the Principal is powerless to order variations.
Ettridge v The Vermin Board of the District of Murat Bay [1928] SASR 124.
Construction of vermin fence - during construction Principal instructed contractor to deviate from the original line - Contractor refused.
A variation or omission power cannot be used to cancel “substantially all the works” under the contract.
Chadmax Plastics Pty Limited v Hansen and Yuncken (SA) Pty Ltd (1984) SASC.
Principal ordered variation which resulted in Head Contractor deleting 98% of Subcontractor’s work - “virtual cancellation” and repudiation.
Variation or omission power cannot be used to delete work and award it to another unless very clear words allow.
Carr v JA Berriman Pty Ltd (1953) HCA
Principal deleted steelworks from Head Contractor’s scope and made arrangements with a third party to fabricate and supply steel - repudiatory conduct.
How is the risk of Inconsistencies between the different parts of the relevant contract providing details of the work to be performed can provide the basis for a variation claim reduced?.
Most standard and non standard forms of contract contain provisions for resolving inconsistences and ambiguities in a contract, usually by giving the Superintendent notice who will issue a direction as to how to proceed.
Should a Principal’s power of variation be limited in a Design and Construct contract?
Yes.
As the Contractor is responsible for the design (and therefore liable if the design is not in accordance with the Contractor’s contractual obligations), the Contractor should have the ability to unilaterally vary the design. However, the Principal’s power to vary the design should be limited.
Variations must be reasonable, that is, on the objective assessment by an independent by-stander.
Wegan Constructions Pty Ltd v Wodonga Sewerage Authority [1978] VR 67
Increasing the excavation required by 60%, sewer length from 840 to 1181 metres (40%), increasing the manholes from 19 to 27 requiring 90% more concrete.
Amounted to a repudiation.
Generally, when does the right of the Principal to order a variation cease?
Once the after the certificate of practical completion had been issued: Jamieson Constructions Ltd v Christchurch City (1984) NZ per Cook J:
“When that point is reached (certificate of practical completion has been issued), with all the consequences that result and with the acknowledgment that is to be inferred from the certificate, I am unable to see that it can remain open for the Architect to direct something which would require a change in the work by way of addition, reduction or substitution.”
Modern case that contractual bars are prima facie enforcable.
Wormald Engineering Pty Ltd v Resources Conservation Co International (1988) 8 BCL 158 per Rogers J
Subject to the ACL, an owner makes no implied warranty as to “buildability” and need not issue a variation to overcome an impossible design.
Alexander Thorn v London Corporation [1870]
Blackfriars Bridge - ‘caissons’ kept drifting away - impossible design.
If a Superintendant mistakenly orders a variation, which is actually within the scope of work, can the contractor sue to recover the price?
Unlikely.
Existing legal duty - no consideration - Superintendent is not authorised to amend the contract on behalf of the Principal.
What is the old case that makes a contractual bar prima facie enforcable?
Tharsis Sulphur and Copper Company v McElroy & Sons [1878] 3 A.C. 1040 Lord Blackburn said:
“It is common enough to have provisions, as are here, more or less stringent, saying that no extra work shall be paid for unless it is ordered in writing by the Engineer; and if such conditions are properly made, and there is nothing fraudulent or iniquitous in the way they are carried out, those conditions would be quite sufficient and effectual.”
What are the three main issues with variations?
- Scope (was it a variation or was the contractor bound to do it anyway?);
- Non-compliance with procedural requirements; and
- Valuing the variations.
Complete this diagram:
Answer:
What is the measured mile method of quantiying loss?
Comparing the cost of “impacted” work withthe same or similar “unimpacted” work.
What is critical path method? (CPM)
A common method of analysisng delay by identifying activities on the critical path.
Requires expert evidence and complex computer programs.
A binding expert determination is only reviewable if the determination was not made in accordance with the contract.
Australian Vintage Limited v Belvino Investments No 2 P/L [2015] NSWCA
Vineyard lease - FM if production down 50% - severe frost - ED decided.
What are the two purposes of a bank guarantee identified in Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA?
They were:
- Security for damages - i.e. in liquidation;
- Who is out of pocket pending a dispute?
Clear words are needed to establish a party has abandoned common law remedies.
Concut Pty Ltd v Worrell [2000] HCA
Concrete salesman - misconduct - 3 month notice augments CL rights.
What is the most common form of security on large projects?
An unconditional undertaking issued as either a bank guarantee or insurance bond.
What is the most common form of security on smaller projects?
Retention monies.
‘The description “guarantee” commercially applied to the bank documents in this case is, in my opinion, a complete misnomer.’
Wood Hall Ltd v Pipeline Authority [1979] HCA per Barwick CJ
To introduce a qualification on the entitlement of the owner to call upon guarantees would be to deprive them of the quality which gives them commercial currency.
The commercial effectiveness of unconditional undertakings would be destroyed “if all the legal and factual complexities of a building dispute were injected” into what should otherwise be a relatively straightforward analysis.
Wood Hall v The Pipeline Authority [1979] HCA
Construction of pipeline - call on security - “as good as cash” necessary.
A clause may allow a Principal to draw on the security for a ‘claim’ with the contractor out of pocket pending final resolution of the dispute.
FMT v Sydney Ports Corporation [2010] NSWSC
OPT, Circular Quay - gangway - alleged defective workmanship.
Principal can call security after an adjudication determination in favour of the builder before a final determination of the parties’ contractual entitlements, if there is a “genuine dispute as to the merits of the adjudicator’s determination”.
Patterson Building Group v Holroyd Council [2013] NSWSC
Certificate to repay adjudiction - not in reality payable - ‘antidote’ to adjudication.
What are the three exceptions to the general unconditionality of bank guarantees, discussed in Clough Engineering Ltdv Oil & Natural Gas Corporation Ltd [2008] FCAFC (Clough)?
They are:
- Fraud or bad faith
- Unconsciousable
- Contractual pre-conditions unfulfilled.
In absence of an express clause, how is decided whether contractual rights (i.e. right to call on security) survive termination?
It will depend on whether the right has ‘accrued’ - termination discharges parties from future obligations, but ‘accrued’ rights are preserved.
What are five practical issues must be borne in mind when accepting a bank guarantee?
You should consider:
- Do you have the correct legal parties? Is the correct contract referenced?
- Is the guarantee properly executed? Enforcable in the jurisdiction?
- Is there a local branch to enforce?
- Is there an expiry date?
- Do you have the original? The orginal is cash - unreplacable.
How far back may a liquidator go to recover voidable transactions?
Depends:
- six months for unrelated parties
- four years for related parties and
- ten years when purpose to defeat creditors.
A liquidator may recover “unfair preferences”.
s 588FA Corporations Act 2001 (Cth)
A deed of company arrangement, normally extinguishing debts, does not extinguish rights under a guarantee.
s 444J Corporations Act 2001 (Cth)
‘Section 444H does not affect a creditor’s rights under a guarantee or indemnity.’
Who is the number one subject of liquidator unfair preference claims?
The ATO.
Well resourced, insured and subject to model litigant guidelines.
What is the “autonomy principle” in relation to performance security?
The bank must pay. Any dispute between the parties is irrelevant.
While an unconditional bank guarantee should be paid on its face, what often occurs?
The bank, keen to protect its relationship with its account client, advises client and delays paying.
This allows an injunction to be issued.
What are the criterion for seeking an injunction (often overlapping)?
They are:
- Serious question to be tried
-
Balance of convenience
- i) whether damages will be an adequate remedy;
- ii) delay;
- iii) risk of reputational harm.
- Whichever course carries the lower risk of injustice;
To call on security in Queensland, notice must be given within 28 days of the right to call security arising.
s 67J Queensland Building and Construction Commission Act 1991
‘The notice must be given within 28 days after the contracting party becomes aware, or ought reasonably to have become aware…’
What are preliiminaries?
The costs of setting up on site for the specific project.
What are prolongation costs?
Costs resulting from delayed demobilization
i.e. fixed staff costs, finance.
What are disruption costs?
Disturbance, hindrance or interruption to a Contractor’s normal working methods, resulting in lower efficiency.
What is a GMP contract?
Why might selecting an arbitrator from a foreign jurisdiction be advantageous?
When Australian law is against you.
What is the Notice of Dispute’s ultimately use?
Sets the jurisdiction for the arbitration. Draft broadly for flexibility.
What is this contract?
Design and Construct.
What is this contract?
Construct Only.
What is this contract?
Project Construction Management.