Security of Payment Flashcards

1
Q

“…stamp out the un-Australian practice of not paying contractors for work they undertake on construction.”

A

NSW Hansard Second Reading Speech 22 September 1999.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

“Cash flow is the lifeblood of the construction industry.”

A

Dawnays v FG Minter [1971] EWCA per Denning LJ
Work performed - Architect certifies sum - P has no right of set-off.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does the superintendant certify in a progress payment?

A

The work undertaken, labour and materials and other costs in accordance with the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Construction work is defined broadly, but does not include drilling for oil and gas, or mining operations.

A

s 5 BCIPA Act 2002 (Vic)

  • “Despite subsection (1), construction work does not include any of the following work—*
  • (a) the drilling for, or extraction of, oil or natural gas;*
  • (b) the extraction (whether by underground or surface working) of minerals…”*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Security of Payment does not apply to domestic building work with a building owner.

A

s 7(2)(b) BCIPA Act 2002 (Vic)

‘…a domestic building contract within the meaning of the Domestic Building Contracts Act 1995 between a builder and a building owner …’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

On and from each reference date, a builder or supplier is entitled to a progress payment, calculated by reference to that date.

A

s 9(1) BCIPA Act 2002 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Reference dates may be calculated under the contract, or in default, every 20 days after construction work first performed.

A

s 9(2) BCIPA Act 2002 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The amount of the progress payment is as per the contract (ie installment), or as valued under the contract.

A

s 10(1) BCIPA Act 2002 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Deductions may be made for defective work.

A

s 11(1)(b)(iv) BCIPA Act 2002 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a first class claimable variation?

A

s 10A(2) BCIPA Act 2002 (Vic)

Parties have agreed that the work was done, that it constitutes a variation and the amount that it is worth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is a second class claimable variation claimable under s 10A(3)-(4)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Aside from non-claimable variations, what are the five (5) other excluded amounts in s 10B?

A
  1. Latent conditions;
  2. Time related costs;
  3. Changes in regulatory requirements;
  4. Damages under contract; and
  5. Any amount claimed at law other than under the contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Pay when paid” provisions are void.

A

s 13 BCIPA Act 2002 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A contractor entitled to a progress payment may make a payment clam.

A

s 14(1) BCIPA Act 2002 (Vic)

A person referred to in section 9(1) who is or who claims to be entitled to a progress payment may serve a payment claim…

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Under s 15 BCIPA Act 2002 (Vic) how long does a respondent have to submit a payment schedule, and what is the consequence of non compliance?

A

10 days (or less if required by the contract).

Non-compliance means claim is immediately due and payable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Under s 16 BCIPA Act 2002 (Vic), what are the claimant’s options if no payment claim is issued?

A

Suspend works, then claim for debt in court, or adjudicate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A clause providing the parties “agree on a method to resolve the dispute” is an agreement to agree and unenforcable.

A

WTE Co-generation and Visy Energy P/L v RCR Energy P/L [2013] VSC per Vickery J

Meeting skipped - sought injunction - clause unenforcable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

“What is required by ss. (3)(d)(ii), in my view is a binding dispute resolution mechanism separate from the Court system.”

A

AC Hall Airconditioning Pty Ltd v Schiavello (Vic) Pty Ltd [2008] VCC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is a good rule of thumb for identifying excluded variations?

A

Contract too expensive, or porportion to big, or there is DR clause.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Liquidated damages can offset the adjudication debt which supports a statutory demand under s 459H(1)(b) Corporations Act 2001.

A

Scrohn Pty Ltd v Newearth Constructions Pty Ltd [2015] VSC

LD proceedings - new payment claim - Queen Anne causes’ irony’ at final hurdle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

State parliaments cannot remove a court’s power to review for jurisdictional error.

A

Kirk v Industrial Court of New South Wales [2010] HCA

Industrial Court - convicted of OHS breach - privitive clause immunising judgement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What was the primary recommendation of the Senate’s Insolvency in the Australian Construction Industry report in December 2015?

A

The most significant of which is that the Commonwealth should enact national, harmonised SOP legislation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Mediation not a “method of resolving disputes” for the purposes of the Victorian Security of Payment Act.

A

SSC Plenty Road v Construction Engineering (Aust) & Anor [2015] VSC

Mediation - “capable of resulting in a binding resolution of the dispute”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

A courts must stay proceedings commenced in contradiction to an arbitration agreement unless “null, void, inoperable or incapable of being performed”.

A

s 8 Commercial Arbitration Act 2011 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Why does Australia have no specific law against phoenix activity?

A

Impossibile to target fraudulent phoenix activity without also impeding genuine business recovery and restructuring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What recourse does a Respondent have for a false statutory declaration occupanying a payment claim?

A

Misleading and deceptive conduct, or negligence.

See Chubb Insurance Company of Australia Limited v Robinson [2016] FCAFC at [5].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is the interplay between the contractual and statutory right to a progress payment?

A

They co-exist independantly. Contract may inform statute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Though not overly demanding, a payment claim must be sufficiently detailed to allow a Respondent to:

  • understand the basis of the claim; and
  • respond meaningfully.
A

Protectavale Pty Ltd v K2K Pty Ltd [2008] FCA

Usual contractual basis - total work less cash received - insufficient detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Invaid parts of a payment claim may be severed.

(cf NSW, Qld - noted to be ‘not an attractive result’)

A

Gantley v Phoenix International Group [2010] VSC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Liquidated damages cannot be offset from a payment claim.

A

Seabay Properties v Galvin Construction [2011] VSC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Certiorari is available to quash an adjudication in Victoria.

A

Grocon Constructors v Planit Cocciardi JV [2009] VSC

s 85 Constitution Act 1975 (Vic) - no expresss mention.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What are the two competing themes in interpretation of the security of payment legislation?

A

Strict technical observance - normal cashflow altered.

vs.

Practical operation - must be accessable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Who said “[t]he result of this fractured and disparate industry, and of our Federal system, is a multitude of regulations governing builders … They are a builder’s minefield; but often a lawyer’s delight…“?

A

Kirby M, “Building, Disputes and the Law” Building Dispute Practitioners’ Society Newsletter, September 1983

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Which states retain subcontractor lein based legislation?

A

Queensland, NSW and South Australia.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Why are excluded amounts a fetter on the use of the Victorian Act?

A

A party does not want to just be paid its progress payment; it wants to resolve the entire dispute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What is the key distinctions of the “West Coast” scheme?

A

Enforces contractual rights, and two way claims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

In Victoria, statistically, what percentage of a claimed adjudication amount is awarded?

A

Approximately 50%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

A ‘bona fidepre-mature payment claim is valid, as s 14(1) allows contractor’s who ‘claim to be entitled’ to lodge.

(cf NSW)

A

Metacorp v Andeco Construction Group [2010] VSC

Reference date - 25 October 2009 - emailed on 24 October.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Under BCIPA Act 2002 (Vic) service may be personal or at the “ordinary place of business”.

A

s 50 BCIPA Act 2002 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

When may a superintendant may recieve a payment claim and issue a payment certificate?

A

Agent under contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Parties cannot contract out of BCIPA Act 2002 (Vic).

A

s 48 BCIPA Act 2002

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What are the maximum payment terms the NSW SOPA Act provides?

A

Head contract 15 days - subcontract 30 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

If new reasons are included in an adjudication response, the Claimant must be given two days to respond.

A

s 21(2B) BCIPA Act 2002 (Vic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What are the three layers of defence when acting as Respondent in Security of Payment adjudications?

A

They are:

  1. Act threshold (reference dates etc)
  2. Contract threshold (time bar etc)
  3. Valuation of items
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Why is there a reluctance to use SOPA in Victoria?

A

Too aggressive - “relationship killer” - can’t claim excluded amounts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

An adjudicator is without jurisdiction to determine excluded amounts.

A

s 23(2A) BCIP Act 2002 (Vic)

‘the adjudicator must not take into account … any part of the claimed amount that is an excluded amount’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

What are three reasons contractors may avoid security of payment claims?

A
  1. Adjudicator bias means Principals do not trust process. Lodging claim seen as relationship killer.
  2. Fragmentation across states means contractors are unfamiliar with process.
  3. Speculative and complicated system - no guarantee of getting anything back.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Anecdotally, why are false statutory declarations rife?

A

Lack of enforcement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

A security of payment Claimant does not enjoy priority over other creditors in the event of a Respondent’s insolvency.

A

Belmadar Constructions v Environmental Solutions Intl [2005] VSC

“…once the processes for an orderly management and winding up of the … a company … are set in train that the statutory rights of and limitations … be respected and given effect to.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What are the two ways an ANA is susptible to bias?

A

ANA will appoint adjudictaor that pays ANA the most commission - ANA will not appoint adjudicator that Claimant does not want.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Which section of the BCIP Act (Vic) gives the claimant a right to suspend?

A

s 29 BCIP Act 2002 (Vic)

Three business days notice - not liable for damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

A Claimant has three months from a reference date to submit a payment claim.

A

s 14(4)(b) BCIP Act 2002 (Vic)

“A payment claim in respect of a progress payment…may be served only within…the period of 3 months after the reference date…”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Which are the only states that allow new reasons to be included in an adjudiction response?

A

Victoria and Queensland (complex claims only).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Which states have abolished Authorised Nominating Authorities (ANAs)?

A

Queensland only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Generally, payment under east coast security of payment is due on the date identified in the contract. Which states cap this with max payment terms?

A

Queensland (generally 15) and New South Wales (15 and 25).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What is the Principal’s most significant obligation in security of payment?

A

Submit a payment schedule within 10 days.

“There’s nothing we can do to help you.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Aside from Victorian, when the does the default reference date arise in other east coast states?

A

Last day of named month.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Complex claims allow a respondent 15 business days for a payment schedule. What is the jurisdictional cap?

A

$750,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

How does security of payment flip the normal bargaining power?

A

Gives contractors access to some money pending outcome of dispute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

As Principal, when consideringt the scope of security of payment, what is it helpful to remember?

A

Scope extends to related goods and services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

What does a sudden inclusion of the security of payment “magic words” indicate?

A

Contractor is no longer happy with contract administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

What does a sudden exclusion of the security of payment “magic words” mean, particularly at the end of project?

A

Contractor may want the benefit of settling some claim contractually (i.e. LDs), then reagitate rejected items under security of payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

In Victoria, it is untested whether a Principal can call on security to recoup liquidated damages lost in an adjudication.

What is the risk?

A

Claimant resubmits claim - security drawn down again - insufficient security for defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

If you are uncertain whether a Claimant has lodged a SOPA claim, can you ask them?

A

Yes.

Misleading answer- actionable under CCA - refusal to answer not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Is a sudden change in pattern in lodging a security of payment claim, without notification, misleading and deceptive conduct?

A

Only weakly arguable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Does a security of payment claim need to be made in “good faith”?

A

Not in Queensland, New South Wales or Victoria.

69
Q

Why is it good practice (even in Victoria) to include all possible reasons in payment certificate?

A

Making argument at early stage enhances credibility.

70
Q

If no payment schedule is received, why may a claimant wish to nevertheless pursue adjudication?

A

Court is expensive and time consuming.

Statement of claim, filing fee, 28 days for defence, then application for default judgement (no defence) or summary judgement (defence).

71
Q

How is an adjudication determination enforced?

A

As a judgement debt.

sheriff, warrant etc (no need for statement of claim etc) - $ determines whether Magistrates, County or Supreme

72
Q

In reality, how much is awarded in unopposed security of payment adjudications?

A

90%.

73
Q

When the scheduled amount is not $0, it is important for interest purposes to identify the adjudicated amount. What is this?

A

Entire amount

“must determine the amount the claimant is entitled to.”

74
Q

If you win an adjudication, what is it good practice from a GST perspective to do?

A

Prepare a tax invoice for the adjudicated amount.

75
Q

What section of Security of Payment Act (Vic) provides no defence to claimed amount on summary judgement?

A

s 16(4)(b) and 17(4)(b) BCIPA 2002 (Vic)

“the respondent is not entitled to … cross-claim or raise any defence… under the construction contract.”

76
Q

Why doesn’t an adjudication amount support a statutory demand?

A

Defendant can claim both:

  1. Genuine dispute as to underlying debt; and
  2. Offsetting claim under contract (i.e. LDs).
77
Q

A court has inherent power to order a stay on a judgement debt under security of payment. When is the limited circumstance it might consider doing so?

A

Claimant is actually insolvent – no chance to clawing back.

“…nearing insolvency insufficient as non-payment may cause insolvency.”

78
Q

In Queensland, a contractor cannot claim under both security of payment and Subcontractors Charge Act 1974. In the event of a clash, which takes priority?

A

Subcontractors Charge Act 1974

79
Q

In which state is it possible to lodge a subcontractor charge on Principal as a means of enforcing an adjudication amount?

A

New South Wales.

80
Q

On what “nuclear” basis could a large, voluminous payment claim be challenged?

A

Abuse of process

Adjudication certificate - becomes court judgement – need to control processes.

81
Q

Despite some judicial fatigue, only approximately what percentage of adjudication applications are subject to judicial review?

A

2%.

82
Q

In security of payment, can liquidated damages be set off in other states (excl. Vic)?

A

Only if contractual methodology allows.

83
Q

Why is a false statutory declaration unlikely to prevent a reference data arising?

A

Because:

  • Brigenshaw / s 140(2) requires convincing proof of fraud
  • Requirement of stat dec likely unenforceable as attempt to contract out.
84
Q

What are the three stages of enfrocement of a security of payment debt in Victoria?

A
  1. No payment schedule - debt only.
  2. Adjudication determination - debt only - can seek adjudication certificate - seek injunction to restrain certificate.
  3. Adjudication certificate -register with court as judgement debt - s 28R(5) prevents judicial review.
85
Q

Even outside Victoria, damages may not be claimable under Security of Payment as they bear no relationship to the construction work on which the right to a progress payment is based.

A

Quasar Construction v Demtech [2004] NSWSC

86
Q

To award delay costs under security of payment (excl Vic), the adjudicator must accept an extension of time was granted, or what?

A

That the superinteant, acting fairly, would have awarded an extension of time.

87
Q

Anshun estoppel can apply to a claim that ought have been bought in a prior adjudication application.

A

Wiggins Island Coal Export Terminal v Monadelphous [2016] QSC

Jetty road delay - claimed but not adjudicated - attempted to adjudicate next time.

88
Q
A
89
Q

Payment delays cause slippages to material delivery which in turn impacts what?

A

Labour productivity in the construction industry.

90
Q

What are the grounds on which “certiorari” may be issued by a superior court?

A

They are:

  1. Jurisdictional error;
  2. Error of law on the face of the record.

Parliament may not limit the power to review for jurisdictional error: Kirk

91
Q

Jurisdictional error is much narrower for inferior courts compared to inferior tribunals, as a regular part of a courts function is to interpret the law.

A
  • Craig v South Australia* (1995) HCA
  • Dietrich v The Queen* adjournemnt - prosecutor sought certiori.
92
Q

In Victoria, once a adjudication certificate is registered as a judgement, s 28R(5) prevents judicial review for error on face of the record, which would otherwise be available.

Jurisdictional error not excludable (Kirk).

A

Amasya Enterprises v Asta Developments (Aust) [2015] VSC

Privative clause - validly enacted - applies to setting aside judgement.

93
Q

In Queensland, unlicenced builders cannot utilise the security of payment act (cf NSW).

A

Cant Contracting v Casella [2006] QCA

s 42 QBSAA - no monetary or other consideration - policy.

94
Q

At general law, can an owner claim a legal or equitable set off against a progress claim?

A

Yes.

Unless expressly excluded by contract.

95
Q

Which case briefly held that payment certificates were enforcable by summary judgement, with set offs to be determined only at court, as “cash-flow is the life blood of contractors”.

A

Dawnays Ltd v Minter Ltd (1971) per Lord Denning MR.

(Overturned by House of Lords in 1974).

96
Q

While contract can give “temporal finality” to a payment claim by excluding set off, what are the three limitations on contractual regulation of cash flow.

A

Three issues:

  1. Certifier may delay / go slow in certifying amounts.
  2. Long payment cycles or pay when paid can slow cashflow.
  3. Presumes all parties solvent, and can collapse on an insolvency.
97
Q

What year did Singapore introduce the Building and Construction Industry Security of Payment Act?

A

2004.

98
Q

In a time where the Act was relatively unused, the developer was found liable for almost $14 million after failing to respond in time to a claim served on 20 December 2002.

A

Walter Construction Group v CPL (Slurry Hills) (2003)

99
Q

What is equitable set off?

A

A connection between claims making it unconscionable for one party to insist on legal rights without first accommodating the set off.

100
Q

Explain the progression of judicial review in New South Wales.

A
101
Q

Explain the availablity of judicial review in Victoria.

A
102
Q

Which privative clause prevents challenging an adjudiction after it has been registered as a judgement?

A

s 28R(5)(iii) BCIP Act 2002

“is not, in those proceedings, entitled … to challenge an adjudication determination [unless non claimable variation].”

103
Q

Who said:

“The Security of Payment Act gives very valuable… advantages to builders and subcontractors…the availability of those rights should depend on strict observance of the statutory requirements…”

A

McDougall J in Chase Oyster Bar [2010] NSWCA

Contractor - late notification of referal to adjudication - 20 day limit.

104
Q

Given the speed and robostness of Payment Act adjudications will invariably produce errors, what is the legislative challenge?

A

Delinieating the proper limits of appeal.

105
Q

(If applicable) the rules of natural justice involve primarily, the rule against bias and the right to be heard.

A

Kioa v West [1985] HCA

Deportation - scheme to bypass migration laws - failure to put allegation.

106
Q

Adjudicators must afford natural justice, there being no legislative intention to exclude that fundamental right.

A

Musico and Ors v Davenport and Ors [2003] NSWSC

Adjudicator - must settle dispute before them - cannot undertake independent inqiry without seeking submissions.

107
Q

In what circumstance in adjudications is the hearing rule of natural justice often argued?

A

s 22(5)(a) BCIPA.

Failure to request further submissions.

108
Q

A decision may be subject to judicial review if “so unreasonable that no reasonable decision maker could have reached it”.

A

Wednesbury Corporation [1948] EWCA

Cinema licence - Sunday operation - no child under fifteen.

109
Q

Without the 5 day extension, how long does the adjudicator have to make a determination?

A

10 business days: s 22(4) BCIPA 2002

Time starts when notice of acceptance served on both parties.

110
Q

Payment Act adjudicators are immune from suit for anything done in good faith.

A

s 46 BCIPA Act (2002) (Vic)

“An adjudicator … is not … liable for anything done …in good faith.”

111
Q

While natural justice applies to Payment Act adjudications, what must also be remembered?

A

The Act is rapid, robust and interim only.

112
Q

A payment dispute with one of the parties about adjudictor’s fees may reveal a reasonable apprehension of bias.

A

Allpro Building Services [2010] NSWSC

Payment dispute - adjudictor retort “recent invention” - apprehended bais.

113
Q

Administrative officials are not subject to a general common law duty to provide reasons for their decisions.

A

Public Service Board of NSW v Osmond [1986] HCA

Promotion recommendation - refused reasons - “overwhelming authority”.

114
Q

The standard of reasons required and the consequences of non-compliance is an exercise in statutory interpretation.

A

Wingfoot Australia Partners v Kocak [2013] HCA

Medical panel - certiorari too late - reasons denying adequate.

115
Q

What is the threshold for a review adjudication under s 28A BCIPA 2002 (Vic)?

A

$100,000.

116
Q

The only grounds of appeal for a review is that the adjudicator considered an excluded amount.

A

s 28B(3) BCIP Act (Vic) 2002

117
Q

If you win an adjudication, what are your commercial options?

A

They are:

  1. Do nothing - experience - losing party often is disheartened - will pay sum.
  2. Seek commercial settlement - capitalise on win - resolve once and for all - prevents court months or years later.
118
Q

The claimant may claim directly from the Principal if they have obtained a judgement debt.

A

s 30 and s 31 BCIP Act 2002 (Vic)

If the circumstances set out in section 30 apply, the claimant may obtain payment of the adjudicated amount​…

119
Q

The Payment Act does not disturb the underlying rights of the parties, which may be independently pursued.

A

s 47 BCIP Act 2002 (Vic)

Subject to section 48, nothing in this Part affects any right that a party to a construction contract​…

120
Q

What is the “no contracting out” provision under the Queensland Payment Act?

A

s 99 Building and Construction Industry Payments Act 2004 (Qld)

121
Q
A
122
Q

In New South Wales, judical review may be sought for non-jurisdictional error.

A
  • Probuild Constructions (Aust) v Shade Systems* [2016] NSWSC
  • Brodyn* not followed - Kirk casts doubt - ratio only concerns availability to unlicenced builders.
123
Q
A
124
Q

In the “West Coast” model, how does a reverse ambush work?

A

Principal files adjudication before Contractor can develop claim.

125
Q

What are the inverse of liquidated damages?

A

Delay damages / costs.

Compensate’s Principal delay. Must be breach (“damages”) or contract specifically provides (“costs”).

126
Q

Very clear words are required for parties to deny the common law or equitable right to set off on a payment claim.

A

Gilbert Ash (Northern) [1974] UKHL

“… one starts with the presumption that neither party intends to abandon any remedies … arising by operation of law.”

127
Q

When have parties achieved “joinder of issue”?

A

The pleadings are closed and issues for trial are identified.

128
Q

In the UK, can an adjudicator appoint appoint experts, assessors or legal advisers?

A

Yes.

129
Q

What three important principals does Metacorp Australia v Andeco Construction Group [2010] VSC stand for?

A
  1. Good faith pre-mature service is valid.
  2. Service on person with actual or ostensible authority (agent) is valid “service” on “person liable to pay” under s 14(1).
  3. s 50 is not a code - other forms of service (s 109X Corporations Act) permitted.
130
Q

Though other forms of service (s 109X Corporations Act) are permitted, what forms of service does s 50 BCIPA 2002 (Vic) allow?

A
  1. personal delivery;
  2. lodging, posting or faxing to ordinary place of business; and
  3. in any other manner specified in the construction contract.
131
Q

What is the starting point for analysing whether service on a superintendant is valid?

A

s 14(1) BCIPA Vic 2002

Requires “service” on “person liable to pay”.

132
Q

What are the two primary ways s 109X Corporations Act 2001 permits service on companies?

A
  1. Leaving at or posting to registered office.
  2. Person delivery to director residing in Australia or external territories.
133
Q

What is the general argument in favour of a Principal calling on a security bond to recover an adjudicated amount?

A

The Act preserves, rather than overrides, the parties’ contractual rights notwithstanding the adjudication.

i.e. s 47 BCIPA Vic 2002 - “Effect of Part on civil proceedings”.

134
Q

Why are progress payments the standard method of payment in the construction industry?

A

Contractors cannot fund project until completion.

135
Q

What is an “entire contract”?

A

No payment until (substantial) completion.

136
Q

What is an on account progress payment?

A

Payment does not constitute acceptance of works.

137
Q

Unless otherwise agreed, domestic building contracts must have progress payments at the following milestones - base, frame, lock up and fixing.

A

s 40 Domestic Building Contracts Act (1995) Vic

A builder must not demand or recover or retain…50 penalty units.

138
Q

In Victoria, only one payment claim for each reference date is permitted.

A

s 14(8) BCIPA Vic 2001

139
Q

Why is the East Coast model known as the Default Model?

A

It uses consequences of default to prompt action.

140
Q

The prohibition on raising a defence or cross claim on a summary judgement application does not extend to alleging the payment claim was served in misleading or deceptive cirumstances.

A

Bitannia v Parkline Constructions [2006] NSWCA

Not a “defence under construction contract”- blanket prohibition on offset breachs s 109.

141
Q

The security of payment regime is not inconsistent with the Kable principle.

A

Birdon v Houben Marine [2011] FCAFC

“…nothing about the enforcement …at odds with … the judicial process.”

142
Q

What percentage of East Coast and West Coast determinations under judicial review were quashed in 2013?

A

80% and 8%.

143
Q

How is the NZ secuirty of payment regime a hybrid of the East Coast and West Coast models?

A

It has:

  1. Default payment system;
  2. Able to litigate two ways and all controversies under contract.
144
Q

How did the 2001 Cole Report recommend harmonising security of payment legislation?

A

s 51(xx)

Federal Government - corporations power.

145
Q
A
146
Q

How is Komptence-Kompetence governed under the Commercial Arbitration Act 2011 (Vic)?

A

s 16 Commercial Arbitration Act 2011.

Power to determine own jurisdiction subject to Court review.

147
Q

What is the Protectvale problem in payment claims?

A

Contractual convention (total progress less amounts paid) does not “identify the construction work” (s 14(2)).

148
Q

Right to an unbiased decision maker is a basic human right.

A

Antoun v The Queen [2006] HCA per Kirby J.

Standover man - no case submission - “that application will be refused”.

149
Q

In Victoria, parties can agree on three or more ANAs that must be selected by the claimant.

A

s 18(4) BCIPA Act

150
Q
A
151
Q

What are the two most common adjudicated issues nationwide?

A

EOTs and variations.

152
Q

How are inadequate reasons dealt with in an adjudication context?

A

Failure to exercise jurisdiction.

“…the parties to an adjudication application are still entitled to see some intellectual process that leads to the conclusion…”

153
Q

Akin to an inferior court, an adjudicator has jurisdiction to decide questions of law “authortatively and wrongly”.

(i.e. no jurisdictional error).

A
  • O’Donnell Griffin v John Holland* [2009] WASC
  • Craig* dichotomy - purpose of Act - significance reduced after Probuild?
154
Q

What is the difference between a broad and narrow jurisdictional fact?

A

Narrow: Actual existence of fact

and

Broad: Reasonable satisfaction of existence.

155
Q

What variations can be included if the contract DOES have a method of resolving disputes?

A

If consideration is:

  • <$150,000 - unlimited.
  • $150,000 to $5 million - 10%.
  • >$5 million - nil.
156
Q

What variations can be included if the contract DOES NOT have a method of resolving disputes?

A

Unrestricted.

The question of whether there is a method of resolving disputes is therefore of critical importantce.

157
Q

In Western Australia, a failure to adequately grapple with the construction contract is a jurisdictional error.

A

Laing O’Rourke Australia Construction v Samsung [2016] WASCA

Spectrum - reasonable error of construction - no consideration at all.

158
Q

What is the risk when labelling a payment claim or schedule “without prejudice”?

A

Document will be ruled inadmissable.

Privilege belongs to all parties, not just one.

159
Q

While an insolvent contractor may use security of payment, what are two barriers to enforcing adjudication outcome?

A

They are:

  1. Stay of enforcement on basis money will be non-recoverable; and
  2. s 553C Corporations Act 2001 offset.
160
Q
A
161
Q

What is the impact of long payment terms?

A

Subcontractors fiannce works.

Studies showed average of 45 - 80 days, and up to 120 days in NSW.

162
Q

How does a Project Bank Account (PBA) work?

A

Simultanteous payments from bank to subcontractors, head contractors, and retention.

163
Q

What are two, currently unchallenged, issues with Project Bank Accounts?

A

They are:

  1. Insolvency rights; and
  2. Interaction with existing contractual rights.
164
Q

Why are Project Bank Accounts not favoured by head contractors?

A

Increases administrative burden and reduces ability to manage cashflow.

165
Q

How do Project Bank Accounts potentially fundamentally alter construction parties relationships?

A

Creditor-debtor to trustor-trustee.

166
Q

The existence of a reference date is a precondition to the making of a valid payment claim.

A

Southern Han Breakfast Point v Lewence Construction [2016] HCA

Substantial breach - work taken from contractor - no further reference date.

167
Q

In New South Wales, the Security of Payment Act does only permits review on the basis of jurisdictional error.

A

Shade Systems v Probuild Constructions (Aust) [2016] NSWCA

Overturned first instance - undermine Act’s purpose - many decisions based on Chase Oyster Bar.

168
Q

In Victoria, why is the existance of a method a of resolving disputes so important?

A

Existence of method severely limits right to claim variations.

169
Q

For the purposes of determining an adjudication application, the adjudicator may request further written submissions.

A

s 22(5)(a) BCIPA 2002 (Vic)

may request further written submissions …must give the other party an opportunity to comment on those submissions.