Themes Flashcards
What are the 7 PRINCE2 Themes?
Business Case Organisation Quality Plans Risk Change Progress
Purpose: to establish mechanisms to judge whether the project is (and remains) desirable, viable, and achievable as a means to support decision-making in its (continued) investment
Business case
the balance of costs, benefits, and risks
Desirable
able to deliver the products
Viable
whether use of the products is likely to result in envisaged outcomes and resulting benefits
Achievable
responsible for specifying the benefits and subsequently realising the benefits
Senior user
responsible for ensuring that those benefits specified by the senior user represent value for money and can be realised.
executive
Business case products
Products:
Business case: provides the costs, benefits, expected dis-benefits, risks, and timescales against which viability is justified and continuing viability is tested.
Benefits management approach: Defines the management actions that will be put in place to ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realised
provides the costs, benefits, expected dis-benefits, risks, and timescales against which viability is justified and continuing viability is tested
Business case
Defines the management actions that will be put in place to ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realised
Benefits management approach
Purpose: to define and establish the project’s structure of accountability and responsibilities (the who)
Organisation
Levels of Management:
Directing: responsible for overall direction and management within programme or corporate constraints; accountable for success of the project
Managing: PM responsible for day-to-day management within constraints from project board; responsibility is to ensure that the project produces the required products in accordance with the time, cost, quality, scope, benefits, and risk performance goals
Delivering: team managers responsible for delivering the project product and its components to an appropriate quality within a specified timescale and cost; accountable to the PM
Levels of Management: responsible for overall direction and management within programme or corporate constraints; accountable for success of the project
Directing
Levels of Management: PM responsible for day-to-day management within constraints from project board; responsibility is to ensure that the project produces the required products in accordance with the time, cost, quality, scope, benefits, and risk performance goals
Managing
Levels of Management: team managers responsible for delivering the project product and its components to an appropriate quality within a specified timescale and cost; accountable to the PM
Delivering
Organisation products
Products: (both created during the IP process)
PID: provides the single source of reference for how the project is to be managed. Sets out the project management team structure and roles
Communication management approach: describes the means and frequency of communication to stakeholders both internal and external to the project
provides the single source of reference for how the project is to be managed. Sets out the project management team structure and roles
PID
describes the means and frequency of communication to stakeholders both internal and external to the project
Communication management approach
Mandated team roles
Executive, Senior User, Senior Supplier, Project Assurance, Change Authority, Project Manager, Team Manager, Project Support
Ultimately accountable for the project’s success and is the key decision maker. Ensure project gives value for money. Appointed during pre-project process of SU process. Role vested in one individual. Secures funding and is responsible for the business case and continued justification for the project.
Executive
responsible for specifying the needs of those (including operations and maintenance services) who will use the project product for user liaison with the project management team and for monitoring that the solution will meet those needs within the constraints of the business case in terms of quality, functionality and ease of use. Commits user resources and monitors products against requirements.
Senior User
represents the interests of those designing, developing, facilitating, procuring, and implementing the project product. Responsible for the technical integrity of the project. Responsible for providing supplier resources and ensuring that proposals for designing and developing the products are feasible and realistic.
Senior Supplier
Project Board
Executive, Senior User, Senior Supplier
Monitoring all aspects of the project’s performance and products independently of the PM. Project Board responsible. Also responsible for supporting the PM by giving advice and guidance on issues such as the use of corporate standards or the correct personnel to be involved in different aspects of the project.
Project Assurance
Who is permitted to authorise requests for change or off-specifications. Project board’s responsibility to agree to potential change, but may delegate authority for approving or rejecting requests for change. May be PM or project assurance.
Change Authority
single focus for day-to-day management. Has the authority to run the project on behalf of the project board. Singular/must not be shared.
Project Manager
primary responsibility is to ensure production of those products allocated by the PM. Reports to and takes direction from the PM. PM uses work packages to allocate work to team managers.
Team Manager
responsibility of the PM. May include providing administrative services or advice and guidance on the use of project management tools. Typically responsible for administering change control. The role is not optional, but the allocation of a separate individual or group to carry out the required tasks is. Role defaults to the PM if it is not otherwise allocated.
Project Support
Purpose: to define and implement the means by which the project will verify that products are fit for purpose.
Quality
Quality Activities
Activities:
Quality planning: defining the project product and its components, with the respective quality criteria, quality methods (including effort required for quality control and product approval) and quality responsibilities of those involved. Purpose is to provide a secure basis.
Quality control: focuses on the operational techniques and activities used by those involved in the project to check that the products meet their quality criteria and identify ways of eliminating causes of unsatisfactory performance.
Achieved by implementing, monitoring, and recording the quality methods and responsibilities defined in the quality management approach and product descriptions.