Test 6 Flashcards
1 NEXT
You are an experienced project manager. You are in the middle of a hybrid project, the duration of which is 2 years. A lot of deliverables are delivered to the customer in the last 7 months. Your team has come up with a new deliverable that they can deliver on time. Once it comes to you what should you do before reaching out to the customer for validation?
SELECT THE CORRECT ANSWER
You should call the customer yourself and get the validation done
You should send the deliverable to the quality team
The team should take the deliverable to customer for validation
You should check with the sponsor on what to do next
Correct Option:B
EXPLANATION
According to the project management framework, once the deliverable comes out of execution process, the next step is the internal verification by the quality team. Once the quality team verifies the deliverable, the project manager should take it to the customer for validation.
2 NEXT
You are managing a waterfall project. In the middle of the project the customer asks you to revise the scope defined at the beginning of the project. As an experienced project manager what should you do?
SELECT THE CORRECT ANSWER
Deny the request as the scope of work was frozen during planning
Accept the request and update the project charter
Generate a change request and follow the change control process
Consult with your sponsor on the customer request
Correct Option:D
EXPLANATION
The customer wants to change the scope defined at the beginning of the project. That scope was a part of the project charter, which is the responsibility of the sponsor. Hence, the project manager needs to talk to the sponsor.
3 QUALITY
During the quality testing of the new software integration project, the results show performance variance from the quality management plan. Thus, the project manager asked the quality team to investigate the root cause of the variance and resolve it to get back on track. What type of action did the project manager request?
SELECT THE CORRECT ANSWER
Corrective Action
Preventive Action
Defect Repair
Project Tracking
Correct Option:A
EXPLANATION
Finding the root cause and taking action to bring the project back on track come under Corrective Action.
4During test planning, two team members disagree about adding a test case to the UAT. The team is not able to take a decision. As a project manager, what should you do?
SELECT THE CORRECT ANSWER
Add the test case
Reject the test case
Postpone the discussion for a later stage
Ask the team members to logically explain their opinions
Correct Option:D
EXPLANATION
The project manager cannot decide whether to add or reject a test case without understanding the need. So, they should ask both the team members to come up with a logical conclusion.
5 NEXT CLOSING
Your company decided to terminate your 24 months’ project in the 7th month of execution because of insufficient budget. What you should do as a project manager?
SELECT THE CORRECT ANSWER
You must meet the top management and convince them to reconsider their decision.
If the management decide to terminate the project, the project manager cannot do anything.
You must submit a report mentioning that you completed the project successfully as you have been delivering the deliverables on time for seven months.
You should transfer the finished and unfinished deliverables to the relevant stakeholders.
Correct Option:D
EXPLANATION
If the project is terminated as a result of insufficient budget, it is most likely a project exit criteria. The project manager should look at the project closing process, which includes handing over the deliverables to the relevant stakeholders.
6 AGILE
You joined in as the project manager of an ongoing hybrid project after 6 months of project start date. You heard the team members saying that despite a robust change control system, there are too many changes in the project and the requirements keeps changing. What should you do?
SELECT THE CORRECT ANSWER
Halt all the changes until you know the reason for the previously done changes
Consider changing the development approach
Update the change management plan
Tell the team that changes are normal in hybrid projects
Correct Option:B
EXPLANATION
If the requirements are changing too rapidly, the project manager should consider changing the development approach from hybrid to agile.
7In the middle of a 50-million dollar construction project, a change request is submitted for approval. As per the change management plan the change request could be approved by unanimity voting by 8 board members. In which case will you go ahead with the change?
SELECT THE CORRECT ANSWER
7 out of 8 approve the change
All 8 approve the change
5 out of 8 approve the change
All 8 reject the change
Correct Option:B
EXPLANATION
Unanimity voting is when all the voting members approve the change.
8During the sprint review of an agile project, the project manager is taking votes around a specific decision. During voting, one of the team members shows a closed fist to the project manager. What does that mean?
SELECT THE CORRECT ANSWER
The team member does not want to participate in the voting.
The team member is OK with the decision.
The team member disagrees with the decision.
The project manager has his 100% support.
Correct Option:C
EXPLANATION
Fist of five is an agile technique in which five fingers means full support and fist means disagreement.
9 NEXT AGILE
You are the project manager of an ongoing agile software development project and you completed your second release. What should you do to prepare for the next release?
SELECT THE CORRECT ANSWER
Manage changes to the scope baseline of the previous release
Review the backlog items
Confirm the validity of the project scope statement
Review the resource utilization
Correct Option:B
EXPLANATION
In agile projects, the project manager and product owner need to reprioritize the backlog items based on the work done during a sprint and the release, so after finishing the release, the project manager and product owner should review the backlog.
10
During the project management plan review meeting, one of the senior directors raised a concern that one major deliverable was missing in the scope of work. What should you do as a project manager?
SELECT THE CORRECT ANSWER
Initiate change management process
Tell the director the change can not be added as the scope is already defined
Review the requirement documentation and requirement traceability matrix (RTM)
Change the plan to include missing deliverable
Correct Option:C
EXPLANATION
As a project manager, you should look into the requirement documentation to see if the requirement was captured.
11You are an experienced project manager. You are starting a new project and discussing the project charter with the team. One of the team members says, “We all are experienced professionals and we have done many similar projects in the past, shouldn’t we spend this time to plan and start the project early?” The rest of the project team members seems to agree with him. How should you respond to this?
SELECT THE CORRECT ANSWER
If everyone agrees, we can move ahead without the project charter.
We can use the team charter of the previous similar project to save time.
We need to define the project charter as this is one of the requirements of the PMO.
We need the project charter as it helps us in understanding the objectives of the project, remove conflicts, and improve efficiency.
Correct Option:D
EXPLANATION
The project charter defines the objectives of the project and helps the team eliminate any confusion or conflict.
12The project manager is working on a new project and meets the customer for the first time. At the end of the meeting the customer asked the project manager for a high-level schedule estimate. The project manager checked her last 4 similar project schedules and gave a high-level estimate to the customer. Which technique did the project use for estimation?
SELECT THE CORRECT ANSWER
Bottom Up Estimation
Parametric Estimation
Analogous Estimation
PERT Estimation
Correct Option:C
EXPLANATION
Historical data analysis comes under Analogous Estimation.
13 NEXT CLOSING
You were managing a project to set up a car assembly line. The assembly line is almost ready and you have closed all the procurements, submitted the final report, and also took feedback from all the relevant stakeholders. What should you do next?
SELECT THE CORRECT ANSWER
Hand over the assembly line to the operations team
Prepare a report to show how the project achieved all the business objectives
Give final payment to all the vendors and contractors
Send out formal notice to close the project
Correct Option:A
EXPLANATION
Once the project finishes, the project manager and the project team need to hand over the project to relevant stakeholders
14 NEXT PLANNING
You are about to start the planning of a large and complex project in a very regulated environment. Due to the size and regulatory considerations, the planning becomes really critical. What is the first thing you should do to start the planning process?
SELECT THE CORRECT ANSWER
Start stakeholder identification so that you can engage the required stakeholders in the planning process
Get the statement of work from the customer and share it with all the stakeholders so that everybody knows what the priorities are
Review the project charter to understand high-level requirements of the project
Conduct a project kick-off meeting with the stakeholders to inform and engage them and to take their commitment
Correct Option:C
EXPLANATION
Project charter gives all the high-level information, and the information becomes the base for detailed planning.
15 VZORCE
You are working on a cement plan maintenance project. The total estimated budget for project is $100000. At 40% completion of the actual work, the actual cost spent is $60000. At the same pace, how much more money will it take to complete the project?
SELECT THE CORRECT ANSWER
$123,512
$97,889
$122,678
$89,254
Correct Option:D
EXPLANATION
The question says “how much more” money you would need to complete the project. So the question requires us to calculate the ETC. First we will calculate EV by using the formula %completeBAC(40%100000), which would be $40000, then we will derive the CPI by the formula EV/AC (40000/60000), which would be 0.67. We need to use the CPI to calculate EAC by the formula BAC/CPI (100000/0.67), which would be 149254, and finally we need to calculate ETC by the formula EAC-AC (149254-60000) = 89254.
16 MONITORING AND CONTROL
Your are managing a large construction project. Currently, you and your team are following the monitor and control project work process. Which of the following activities you and team might carry out during this process?
SELECT THE CORRECT ANSWER
Accepting or rejecting the change requests
Performing quality control activities on the deliverables
Getting formal acceptance on the deliverables from the customer (customer validation)
Comparing the actual progress against the baseline and the project management plan to keep the project under control
Correct Option:D
EXPLANATION
The question asks about the process of monitor and control project work and not about monitoring and controlling process groups. The process group includes all the options, but the process of monitor and control project work includes comparing the actual progress against the project management plan and making sure the project runs on track.
17You are in the middle of a large construction project. There are a lot of unexpected issues and they are threatening the project budget and schedule. What is the best course of action for the project manager to address the issues?
SELECT THE CORRECT ANSWER
Use the contingency reserves to get the project back on track
Check with the finance department if you could get some more money to cover up the cost variance
Use management reserve
Check how you controlled the cost and the schedule in the last similar project
Correct Option:C
EXPLANATION
Because most of the issues are unexpected, the project manager should utilize the management reserve.
18 QUALITY ASSURANCE
You are managing a defect rate reduction project for a manufacturing process. To analyze and improve the process, you and the team are now involved in the quality assurance process. Which of the following could help in improving the process?
SELECT THE CORRECT ANSWER
Add a zero inventory process to the project
Consult with the quality control department
Make a process improvement plan with a Kanban expert
Consult with a Six Sigma Black Belt consultant
Correct Option:D
EXPLANATION
Six sigma is a lean project management concept, which is centralized around process improvement. The six sigma consultant can help in reducing the error rate.
19Your project sponsor calls you in the middle of the project and asks for a document that explains the description, owner, and status of all the requirements. Which document will you present to the sponsor?
SELECT THE CORRECT ANSWER
Requirement Traceability Matrix
Requirement Management Plan
Requirement Documentation
Stakeholder Expectation Document
Correct Option:A
EXPLANATION
Requirement Traceability Matrix (RTM) is a document that contains the description, owner, and status of all the requiremen
20During the project review meeting with the team, you identified a significant variance. It is because of an issue in configuration. If the issue is not fixed before the next client inspection, your project might be canceled, However, after further review with the team, you came to know that bringing the project back on track is only a minor correction to the configuration element. What should you do first?
SELECT THE CORRECT ANSWER
Contact your sponsor
Talk to the customer and inform them about the findings
Raise a change request
Change the configuration element to bring the project back on track
Correct Option:C
EXPLANATION
Because the change is in configuration, the first thing the project manager should do is to raise a change request.
21
You are an experienced project manager working on a large software development project. Using a hybrid approach in this project, you are trying to break the work package into activities for scheduling purposes. During the decomposition of the testing work package, you need more information about the project which will come only once the development work is at least 60% complete. Since the development work will take about four months to complete, how you would proceed with the decomposition?
SELECT THE CORRECT ANSWER
Review the project scope statement to check if there is a possibility to reduce some work from development work package
Review the project management plan to determine how to proceed with the decomposition
Contact the solution architects to see if they could help in decomposition
Breakdown the development work package for now and decompose the testing work package later after getting the required information
Correct Option:D
EXPLANATION
One of the decomposition techniques is Rolling Wave Planning. The project manager decompose the work packages as they move into execution and more information is available. The best option here is to decompose the development work package for now and wait for the required information to decompose the testing work package later.
22 DEFINITION
You and the team are trying to estimate the time periods required by each activity. In this process, you are using a document which contains information on categories of labour, material, and equipment resources. To complete the project work, you also want to know the skill set, grade of supplies, and required certifications. Which of the following documents would you primarily refer for this purpose?
SELECT THE CORRECT ANSWER
Resource management plan
Work breakdown structure
Resource breakdown structure
Project management plan
Correct Option:C
EXPLANATION
The team is in the estimate activity duration process. One of the inputs to that process is the resource breakdown structure, which has information related to labour, material, and equipment resources.
23 RESOURCE MAN. PLAN
You are using a rented facility from where the team of developers and testers are working. The weekly renewal of the facility is bound to happen on Monday, next week. The development work is delayed and will take another week. You had a discussion with the landlord to renew the contract for one more week but the landlord informs you that the facility is already booked. What should you do next?
SELECT THE CORRECT ANSWER
Update this risk in your risk register
Update this issue in the issue log
Update the resource management plan
Update procurement documentation
Correct Option:C
EXPLANATION
Since the issue has already occurred, there is no need to change the facility. The facility is a part of physical resources, the resource management plan needs to be updated with this change.
24 RISK
The project management plan explains that the predictive life cycle has been selected to produce the project deliverables. During which of the following areas will the overall project risk be the lowest?
SELECT THE CORRECT ANSWER
Initiation
Planning
Monitor and control
Closing
Correct Option:D
EXPLANATION
The overall project risk is highest at the beginning of the project and is lowest during the closing.