PMP TEST 3 Flashcards
1A key characteristic of a High-Performing team is that team members:
SELECT THE CORRECT ANSWER
Are familiar with each other
Have a shared understanding of the project
Live in the same location
Have the same cultural background
Correct Option:B
EXPLANATION
High-performing teams have a shared understanding of and commitment to the project.
2A project team is performing the work of the project to achieve its objectives. Which of the following is not potentially a project team?
SELECT THE CORRECT ANSWER
Project management staff who perform budgeting and reporting.
Project staff who create project deliverables.
Customer representatives who provide requirements
Stakeholder group
Correct Option:D
EXPLANATION
Stakeholder group is the larger group of people and organisations and not all are part of the project team
3A project manager is performing project resource management. Which of the following is NOT a critical part of this activity?
SELECT THE CORRECT ANSWER
Obtain people
Facilitate interactions
Develop project scope
Manage team personnel changes
Correct Option:C
EXPLANATION
Project scope is part of Plan and Manage Scope while Project Resource management is concerned with the team.
4Your project manager is working on preparing a stakeholder register. Who among the following would be his least priority?
SELECT THE CORRECT ANSWER
Sponsor of your project
Functional managers for team members
Director of procurement in your organisation
Project team member of a competing organization
Correct Option:D
EXPLANATION
Sponsor, functional managers for team members and Director of procurement in the organisation are relevant stakeholders to consider as they can have direct impact on the project. A project team member of a competing organization might be the least of his priority while identifying and developing an appropriate stakeholder engagement strategy for a project.
5A project manager has been working with the team on task assignment and following were the final assignments for developing project management plan: John and Steve were assigned as Responsible for the task William and James were assigned as Accountable for the task. Jacob was identified as the SME and was marked under Consult Program Manager Jack was marked under Informed of the RACI chart. Which of the following statements are true about RACI chart
SELECT THE CORRECT ANSWER
Chart cannot have more than one person assigned for Responsible
Chart cannot have more than one person assigned as Accountable
Chart cannot have more than one person assigned as Informed
Chart cannot have more than one person assigned for Consulted
Correct Option:B
EXPLANATION
We have only one person assigned for Accountable in RACI chart
6Project ABC is geographically distributed and has members from different backgrounds. Project manager Sam is working on building a productive climate for the team. Which of the following is not an attribute of diversity and inclusion?
SELECT THE CORRECT ANSWER
Team members using a local language in project communication
Team members being conscious of group contrasts
Objecting to discrimination and bigotry
Establishing conditions where different types of groups can thrive
Correct Option:A
EXPLANATION
Communication is one of the key challenges in virtual teams. The team should agree on a common language to be used which is conducive to members of all regions. The team members using the local language in project communication can be detrimental to the team as not all of them might understand the local language if the team is geographically distributed.
7A project team along with their project manager are working on identifying activity resources. Which of the following do you need to consider while producing a resource calendar?
SELECT THE CORRECT ANSWER
Working days and holidays
Availability of physical resources
Attributes like skills and geographies
All of the above
Correct Option:D
EXPLANATION
Resource calendar includes all of the above, along with identifying details of when and how long the resources are available for the project.
8Virtual teams could be ideal for geographically distributed projects, but they have their certain challenges. Which of the following is a challenge for virtual teams?
SELECT THE CORRECT ANSWER
Recruiting experts from all around the globe
Bonding with geographically dispersed team members
Higher cost of operations
Lack of information radiators to help share information
Correct Option:B
EXPLANATION
Virtual teams are groups of people with shared goals with little or no time spent on face-to-face interactions. These teams are distributed across geographies with occasional physical meetings, while some never get a face-to-face meeting. Bonding and team identification can be difficult because finding ways to provide a sense of team spirit and cooperation is difficult compared to a co-located team.
9Key members of a project are in the process of defining and assigning individual and team responsibilities. Which of the following is most critical for this team while the project management method is still not finalized?
SELECT THE CORRECT ANSWER
Understanding the location and time zone of team members
Knowing the attitudes of team members
Having open communication and effective collaboration
Skill and experience of team members
Correct Option:C
EXPLANATION
Project responsibilities within a team Open communications and effective collaboration are critical regardless of the specific project management method chosen
10A project team is trying to agree on actions that are acceptable and unacceptable in the project management context. This is done to set expectations for performance and decrease risk of confusion. Which of the following stakeholders are an important part of this?
SELECT THE CORRECT ANSWER
Project sponsors
Customer representatives
Project management staff
Project team members
Correct Option:D
EXPLANATION
Team charter and ground rules should be produced by the team or at least with the teams active participation
11Negotiations ensure mutual understanding prior to entering a contract. Which of the following might not be included in the agreement documents?
SELECT THE CORRECT ANSWER
Statement of Work
Benefits management
Subcontractor approvals
Termination clauses
Correct Option:B
EXPLANATION
Statement of work, subcontractor approvals, and termination clauses should be included in the agreement document.
12An important feature in Agile is to maintain a prioritized list of backlog. Which of the following is NOT a prioritization technique?
SELECT THE CORRECT ANSWER
Monte Carlo simulation
Kano model
MoSCoW analysis
100 Points Method
Correct Option:A
EXPLANATION
Monte Carlo simulation is a technique used to understand the impact of risk and uncertainty in prediction and forecasting models.
13It is critical to understand the required competencies when forming and developing high-performing teams. Which of the following is used to determine team weaknesses?
SELECT THE CORRECT ANSWER
KANO model
PERT
SWOT
100 Points Method
Correct Option:C
EXPLANATION
SWOT is a technique used to analyze Strengths, Weaknesses, Opportunities, and Threats. Project manager can leverage SWOT analysis to improve overall team performance as well as challenges, that the team will need to overcome for better performance
14Estimations are fundamental in every project. Which of the following is used as an estimate in Agile projects?
SELECT THE CORRECT ANSWER
Absolute time estimate
Relative measures
Three point estimate
Hours of effort
Correct Option:B
EXPLANATION
Story Point estimating uses relative measures, which can be helpful as an integrated assessment to provide time estimates.
15Teams in Agile approach take accountability to ensure that all the work required for an iteration is delivered. Which of the following statements is not true?
SELECT THE CORRECT ANSWER
Agile teams are self-organized.
Task accountability need not be tracked.
Team members pull work for an iteration.
User stories are decomposed into required tasks.
Correct Option:B
EXPLANATION
Accountability of tasks should be tracked in an Agile approach.
16Tuckman’s ladder model describes 5 stages of team development . Which of the following is not true about this model?
SELECT THE CORRECT ANSWER
Teams are in the Forming stage at the beginning.
Team disperse as part of the Adjourning stage.
Conflicts are high during Storming stage
Teams do not find themselves returning to a stage once they have passed it.
Correct Option:D
EXPLANATION
Teams find themselves returning to one or more stages at different times in a project. Strong innovative people will disagree from time to time.
17The Project Manager of a team observes that the project team is spending too much time during standups though this is meant to be a 15-minute ceremony every day. What could be the possible cause of this?
SELECT THE CORRECT ANSWER
Team members might not be sticking to the agenda
The team might be trying to find solutions to problems that were brought up.
Team might not be making effective use of parking lot to discuss issues post the standup meeting
All of the above
Correct Option:D
EXPLANATION
Standup meetings should be focusing on the following 3 questions for every team member and are typically timeboxed for 15 minutes: What did you do yesterday? What will you do today? Are there any impediments?
18It is important to have a clear vision for every project. Sam states that Vision is about bridging the gap between where we are and where we want to be. John mentions that Vision is about satisfying customer needs based on the requirements provided. Vinod says that Vision is only meant for the organization as a whole and not required for a project. Joe states that Vision is a desired end state. Who among them is correct about Vision?
SELECT THE CORRECT ANSWER
Sam and John
Vinod and Joe
Joe
Vinod
Correct Option:C
EXPLANATION
Vision is a desired end-state and it is critical to have a clear vision of the desired end objectives for a new project.
19Project Charter is a document issued by the:
SELECT THE CORRECT ANSWER
Project Team
Sponsor
Project Manager
None of the above
Correct Option:B
EXPLANATION
Project Charter is a document issued by the Sponsor or project initiator
20Agile has certain ceremonies like daily standup, sprint review, and sprint retrospective. Which of the following is not true about the ceremonies?
SELECT THE CORRECT ANSWER
Daily standups are status meetings.
Sprint planning is a collaborative event for planning the project release.
Both A and B are wrong
Both A and B are correct
Correct Option:C
EXPLANATION
Sprint planning plans the work for the current sprint, not an entire project. Daily standups are not status meetings. The are required for a team to reaffirm commitment to its objectives, coordinate work among team members, and surface potential blockers.
21Kanban board is a tool that: (Mark all correct choices)
SELECT THE CORRECT ANSWER(S)
Enables teams to create WBS
Helps identify bottlenecks
Helps in project selection
Works as an information radiator
Correct Option:B, D
EXPLANATION
Kanban board is a visualization tool that enables improvements to the flow of work by making bottlenecks and work quantities visible
22Fist of five technique is used for building consensus. A fist is a statement of:
SELECT THE CORRECT ANSWER
Agreement with a team’s conclusion
Strong disagreement
General agreement with minor questions
Minor disagreement
Correct Option:B
EXPLANATION
A fist (or 0 fingers) is a strong statement of disagreement and will require adjudication.
23A project team is discussing story points to be used for estimates. Which of the following is correct when it comes to story points?
SELECT THE CORRECT ANSWER
Story points must strictly follow the Fibonacci sequence.
A story point of 5 indicates a day’s work.
The team decides on the benchmark for story points.
8 story points indicate 8 hours of effort.
Correct Option:C
EXPLANATION
Story points are unit-less and attempt to capture the overall impact of work. The team agrees on a benchmark based on known level of work which can be used for relative comparison.
24XP Metaphor describes a common vision on how a program works. Metaphors are not intended to be:
SELECT THE CORRECT ANSWER
Simple
Technical
Helpful in understanding the overarching approach
Easily understood by a broad array of stakeholders
Correct Option:B
EXPLANATION
Metaphors should be simple and non-technical to enable a large array of stakeholders to understand the overall program.