Test 3 Flashcards
What is the required fire rating of the walls around the exit stairs in a three story building with a mezzanine in the lobby?
A. 2-hours
B. 1 1/2-hours
C. 1-hour
D. 3-hour
A. 2-hours
Feedback:
2-hour rated walls are required for buildings 1, 2 or 3 stories. Mezzanines are not counted as stories (basements are counted).
Arbitration is a form of alternative dispute resolution. The decision of the arbitrator is
A. Final
B. Non-Binding
C. A recommendation only
D. Delivered within 14 days of the hearing
A. Final
Feedback:
Final.
See AIA A201 General Conditions, Article 15.4.2 under Arbitration.
Which is not a best practice for indoor air quality during occupancy?
A. Building flushing
B. Controllability
C. Daylighting
D. Thermal comfort
A. Building flushing
Feedback:
Building flushing is a process of removing toxins from a building after constructing and before occupancy.
What is the most proper method for apportioning monetary value of the work by the Contractor?
A. Owner cost estimate
B. Architect cost estimate
C. Schedule of values
D. Standard value index
C. Schedule of values
Feedback:
The Schedule of Values is a detailed statement furnished by the General Contractor, outlining the portions of the contract sum. It allocates values for the various parts of the work and is also used as the basis for submitting and reviewing progress payments.
Note. The AIA does not have a form for the Schedule of Values.
Using the earth as a heat source (in the winter) or a heat sink (in the summer) is what kind of energy?
A. Fuel cells
B. Micro hydro
C. Solar thermal
D. Geo-thermal
D. Geo-thermal
Feedback:
Geothermal drills pipes deep into the ground to produce warm water that can be used for heating or cooling.
If you were replacing windows in an office constructed in the 1970s which hazardous material should you be most concerned about?
A. Asbestos
B. Lead paint
C. Mold
D. Radon
B. Lead paint
Feedback:
Lead paint was likely used on the window sills. Asbestos would be a concern if the walls or ceilings were being modified. Radon is a hazardous gas that can be present in below grade spaces. Mold may become an issue due to a defect in the windows (and may be a cause for replacing the windows) but the act of replacing the windows would not cause anyone to be at risk.
Which of the following is not produced during the Design Development Phase?
A. Site evaluation
B. Preliminary construction details
C. Updated outline specification
D. Plans, sections, and elevations
A. Site evaluation
Feedback:
Site evaluation is typically performed before the Basic Scope of Services commences.
Who issues the Certificate of Substantial Completion?
A. Architect
B. Owner
C. Building Official
D. Surety
A. Architect
Feedback:
Architect.
The Architect issues the Certificate of Substantial Completion (not to be confused with the Certificate of Occupancy which is issued by the local Building Official).
See AIA A201 General Conditions, Article 9.8 Substantial Completion.
An allowance is
A. Used in lieu of specifying a product or particular portion of the work when that product or scope of work is not specified, such as door hardware (i.e. allow $5000 for door hardware, we’ll pick it out later)
B. The amount added or deducted to the based bid for a specified product, i.e. hardwood floor is specified in the based bid, but carpet is specified as an option
C. Typically utilized during construction when a product is substituted for the one specified in the Construction Documents, i.e. no longer available, long lead time. Substitutions must be approved in writing by Architect & Owner
D. Calls out or specifies three or more trade names with a provision “or approved equal” often included
A. Used in lieu of specifying a product or particular portion of the work when that product or scope of work is not specified, such as door hardware (i.e. allow $5000 for door hardware, we’ll pick it out later)
Feedback:
An allowance is used in lieu of specifying a product or particular portion of the work when that product or scope of work is not specified, such as door hardware (i.e. allow $5000 for door hardware, we’ll pick it out later).
Can a conference room with a maximum occupancy of 25 have egress doors that open into the room?
A. Yes
B. Yes, if the door is fire rated
C. Yes, if the door is metal
D. No
A. Yes
Feedback:
50 people is the minimum occupancy requiring 2 egress doors.
The total cost to the Owner to construct all elements of the project designed or specified by the Architect and shall include contractors’ general conditions costs & overhead and profit is known as
A. Cost of Work
B. Cost to Build
C. Cost Plus
D. Cost Breakdown
A. Cost of Work
Feedback:
Cost of Work is the total cost to the Owner to construct all elements of the project designed or specified by the Architect and shall include contractors’ general conditions costs & overhead and profit.
See AIA B101 Article 6.1
What techniques are useful to maintain project quality assurance and quality control (QA/QC) on a project?
A. Team meetings to review design and progress, Checklists and documentation of key approvals
B. Checklists and documentation of key approvals
C. Standards for CAD and design document, Team meetings to review design and progress
D. Team meetings to review design and progress, Checklists and documentation of key approvals, Standards for CAD and design documents
D. Team meetings to review design and progress, Checklists and documentation of key approvals, Standards for CAD and design documents
Feedback:
Team meetings to review design and progress, Checklists and documentation of key approvals, Standards for CAD and design documents.
Quality assurance and quality control is very important in order to deliver a satisfactory project to the owner. This not only assures that the client is happy, it increases the odds of repeat or referred business. The above techniques are useful for this process.
If the Occupant Load Factor for a 9,000 sq. ft. warehouse is 300 sq. ft. per person how many exits are required?
A. 1
B. 2
C. 3
D. 4
A. 1
Feedback:
9,000 sq. ft. / 300 sq. ft. per person = 30 people < 50 people minimum requirement for 2 exits.
The Contractor’s responsibility in regards to code compliance of the project is as follows?
A. The Contractor is responsible to make sure the contract documents are in full compliance with all codes and regulations
B. The Contractor is not required to review the contract documents for code compliance. However, if the Contractor notices or is informed of elements not conforming to code, he should notify the Architect promptly
C. The Contractor has no responsibility pertaining to codes and regulations. That is the Architect’s role
D. The Contractor is responsible only to codes and regulations that pertain to work performed directly by his staff but not to work performed by sub Contractors
B. The Contractor is not required to review the contract documents for code compliance. However, if the Contractor notices or is informed of elements not conforming to code, he should notify the Architect promptly
Feedback:
The Contractor is not required to review the contract documents for code compliance. However, if the Contractor notices or is informed of elements not conforming to code, he should notify the Architect promptly.
See AIA A201 General Conditions, Article 3.2.3 under Contractor.
A landscape architect has been hired for the project. Select the BEST four issues/items you would discuss with the landscape architect
A. Budget, Contract requirements, Overall design Intent, Types of planting to be used
B. Budget, Overall design intent, Types of planting to be used, Schedule
C. Overall design intent, Types of planting to be used, Water conservation methods, Shading requirements
D. Budget, Overall design intent, Schedule, Previous experience of the landscape architect
C. Overall design intent, Types of planting to be used, Water conservation methods, Shading requirements
Feedback:
Overall design intent, Types of planting to be used, Water conservation methods, Shading requirements are the BEST four issues/items with the landscape architect.
Budget, Schedule, and Contract requirements are also relevant topics of discussion, but the most important thing is to look at the type of consultant and what is most applicable or unique to that particular consultant.
Budget, Schedule and Contract requirements are applicable to any consultant and as a result are not considered the BEST answer for this question.
According to the Standard Form of Architect’s Services, AIA B101, which is not a customary service provided by the Architect?
A. Mechanical Engineering
B. Structural Engineering
C. Architectural Interior Design
D. Electrical Engineering
C. Architectural Interior Design
Feedback:
Architectural Interior Design is not considered a Basic Scope of Service according to AIA document B101, rather is considered an additional service per Article 4.1.9.
If the foundation of a building is damaged by blocks of soil separating from one another this is the result of what?
A. Fault rupture
B. Lateral spreading
C. Landslide
D. Liquefaction
B. Lateral spreading
Feedback:
Lateral Spreading: Intense shaking during an earthquake can cause the soil to break into blocks which separate from each other. This can cause damage to the building foundation
Neurological brain damage, reproductive problems and nerve damage are know to be caused by what?
A. Asbestos
B. Formaldehyde
C. Lead paint
D. Volatile organic compounds
C. Lead paint
Feedback:
Lead has been found to cause permanent neurological brain damage, reproductive problems and nerve damage.
What is a continuous vertical or horizontal shield with a minimum fire-resistant rating of 1 hour?
A. Fire Barrier
B. Fire Partition
C. Smoke Barrier
D. Fire Wall
C. Smoke Barrier
Feedback:
A smoke barrier is a continuous vertical or horizontal shield with a minimum fire-resistant rating of 1 hour that is designed and constructed to restrict movement of smoke.
During the course of renovation of an old office building, the Contractor encounters what he believes to be asbestos. Which is NOT a correct statement?
A. The Contractor, upon finding the asbestos, must immediately stop work in the affected area and arrange for the removal or encapsulation of the asbestos
B. The Contractor, upon finding the asbestos, must immediately stop work in the affected area and report the condition to Owner and Architect
C. The Owner is responsible for hiring a testing company to test for the presence of asbestos
D. When the material or substance has been rendered harmless, work in the affected area shall resume upon written agreement of the Owner and Contractor.
A. The Contractor, upon finding the asbestos, must immediately stop work in the affected area and arrange for the removal or encapsulation of the asbestos
Feedback:
The Contractor, upon finding the asbestos, must immediately stop work in the affected area and arrange for the removal or encapsulation of the asbestos is the incorrect statement.
If the Contractor encounters asbestos or other hazardous material, the first step is to notify the Architect and Owner in writing.
See AIA A201 General Conditions, Article 10.3 Hazardous Materials.
The Owner has changed the scope of work during the Construction Documents Phase after written approval at the end of the Design Development Phase to increase the size of the auditorium an additional 1,000s.f. This change would be considered
A. Part of Basic Services
B. An additional service
C. A change order request
D. A supplemental instruction
B. An additional service
Feedback:
If the Owner makes a change in the scope of work during one of the Phases, it would generally be considered and additional service and the Architect should receive written approval before proceeding with the change.
According to AIA B201, which statement is true?
A. The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants
B. The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants only when agreed in writing and the Architect receives additional compensation
C. The Architect is not responsible for coordinating with the Owner’s consultants
D. The Owner is responsible for coordinating the work of its consultants with that work of the Architect’s
A. The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants
Feedback:
The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants is the correct statement according to AIA B201, Article 2.1.2
An Architect’s Contract Administration responsibilities begin at ________and end at ________.
A. Award of contract for construction, issuance of certificate for final payment to Owner
B. Arrival of bids, Substantial Completion
C. Groundbreaking, 60 days after Substantial Completion
D. First site visit, Final Completion
A. Award of contract for construction, issuance of certificate for final payment to Owner
Feedback:
Award of contract for construction, issuance of certificate for final payment to Owner.
See AIA B101 Standard Form of Architect’s Services, Article 3.6.1.3.
Which is not a principle of sustainable design?
A. Optimize a building’s operations and maintenance
B. The conservation of on site water use
C. Preserve the historic character of a building
D. Optimize the use of space and material in a building
C. Preserve the historic character of a building
Feedback:
The 6 Principles of Sustainable Design are: Optimize Site Potential; Optimize Energy Use; Protect and Conserve Water; Optimize Building Space and Material Use; Enhance Indoor Environmental Quality; Optimize Operational and Maintenance Practices.
According to AIA B101, unless the Owner and Contractor designate another person to serve as ____________, as that term is defined in AIA Document A101, the Architect shall render initial decisions on Claims between the Owner and Contractor as provided in the Contract Documents.
A. Responsible Control
B. Initial Decision Maker
C. Mediator
D. Referee
B. Initial Decision Maker
Feedback:
Initial Decision Maker. See AIA Document B101, Article 3.6.2.5.
According to AIA A201, which of the following statements is not true? The Owner is
A. Not obligated to pay for all approvals, including building permit, tests, and inspections
B. Not obligated to show evidence of Project financial arrangement to Contractor
C. To provide all necessary info to Contractor in order to evaluate or enforce Mechanic’s Lien Rights
D. Obligated to provide the Contractor with Surveys and a Legal Description of the Project
B. Not obligated to show evidence of Project financial arrangement to Contractor
Feedback:
The Owner is not obligated to show evidence of Project financial arrangement to Contractor is the NOT true statement.
The Owner is required to provide evidence to the Contractor, if requested, that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract. See AIA A201 General Conditions, Article 2.2.1 under Owner.
Per AIA A201 General Conditions, Article 3.7.1, the Contractor is required to pay for the building permit as well as for other permits. See Article 3.7.1 for further details. Per Article 13.5.1, the Contractor is also required to pay for necessary tests and inspections.
A fire department in an area zoned only for commercial buildings is an example of what?
A. Variance
B. Ordinance
C. Conditional use
D. Easement
C. Conditional use
Feedback:
Conditional Use: a building use that is permitted in an area that it is not zoned for, in order to benefit the public.
What is the requirement for a fire suppression not based upon?
A. Type of Construction
B. Area of the building
C. Number of occupants
D. Occupancy type
A. Type of Construction
Feedback:
The need for a fire suppression system is based on: area of the building (larger areas have more requirements); the type of occupancy (larger groups of people in one area will have stricter requirements); the number of occupants (more people trigger more requirements)
The Construction Documents Phase is taking longer than anticipated because the structural engineer has been behind schedule. To meet the agreed upon deadline with the Owner for completion of the Construction Documents Phase, you will need to have your staff work a substantial amount of overtime during the coming week and following weekend. This additional cost would be the responsibility of the
A. Owner
B. Architect
C. Structural Engineer
D. Divided among the Architect, Owner, Structural Engineer
B. Architect
Feedback:
This additional cost would be the responsibility of the Architect. The Architect is responsible for keeping the project team on schedule including the consultants.
In which Phase would you focus on a single design strategy and select the structural system?
A. Pre-Design
B. Schematic Design
C. Design Development
D. Construction Documents
C. Design Development
Feedback:
Design Development Phase is when you would focus on a single design strategy and select the structural system. See AIA B101 Article 3.3
Collecting rainwater to be used later for irrigation is an example of what?
A. Optimize site potential
B. Adaptive reuse
C. Resource efficiency
D. Water conservation
D. Water conservation
Feedback:
Two considered for the construction documents to “Protect and Conserve Water” are: Specify low-flow or waterless fixture; Collect rainwater or graywater for reuse.
The Owner and Contractor has selected someone other than the Architect to act as Initial Decision Maker with the terms according to AIA A201 General Conditions. Which of the following is true?
A. The Initial Decision Maker will render an initial decision approving or rejecting the claim
B. The Initial Decision Maker will review and issue the Certificate of Substantial Completion
C. The Initial Decision Maker will review Applications for Payment and issue Certificates for Payment
D. The Initial Decision Maker will act in the role of “mediator” as defined by the American Arbitration Association
A. The Initial Decision Maker will render an initial decision approving or rejecting the claim
Feedback:
The Initial Decision Maker will render an initial decision approving or rejecting the claim.
See AIA A201 General Conditions, Article 15.2.1 and 15.2.5 under Initial Decision.
A nursing home has what Occupancy Group Classification?
A. Residential
B. Institutional
C. Medical
D. Assembly
B. Institutional
Feedback:
The institutional occupancy group is defined “places where people are physically unable to leave without assistance” (hint there is no “medical” occupancy group).
Closing off a portion of a building for future restoration is called?
A. Mothballing
B. Restoration
C. Adaptive reuse
D. Resource efficient
A. Mothballing
Feedback:
Mothballing: historic preservation term where certain areas of a building or city block are closed up so they can be repaired or restored at a later date (later phase of project).
If a soils report is required for a project, according to document AIA B101, which of the following statements is true?
A. The Architect is obligated to hire a geotechnical engineer consultant for the project
B. The Owner is obligated to furnish services of a geotechnical engineer for the project
C. The Contractor may hire a geotechnical engineer for the project
D. The Architect must provide soil samples
B. The Owner is obligated to furnish services of a geotechnical engineer for the project
Feedback:
The Owner is obligated to furnish services of a geotechnical engineer for the project if required. See AIA B101, Article 5.5 under Owner’s Responsibilities.
The Owner and Contractor shall commence all claims and causes of action against the other arising out of or related to the Contract in accordance with the California statute but not more than ____ year(s).
A. 1
B. 3
C. 5
D. 10
D. 10
Feedback:
See AIA A201 General Conditions, Article 13.7 Time Limits on Claims.
The buildable area created by setbacks from a property line are used to protect what?
A. Public access to light and air
B. The government’s access to areas for easements
C. The pursuit of financial profit
D. A developer’s access to an exit discharge
A. Public access to light and air
Feedback:
Minimum setback requirements and lot size requirements help set the scale and density in residential areas. Setback lines are also an important part of protecting access to light and air, the quality of the streetscape and adequate sight lines for traffic.
Which of the following is not a consideration for optimizing operation and maintenance practices?
A. Life-cycle cost
B. Resource depletion
C. Waste generation
D. Resource costs
B. Resource depletion
Feedback:
Resource depletion is a consideration of material use.
Which of the following is NOT one of the Architect’s roles during Contract Administration?
A. Prepare Change Orders
B. Approve Applications for Payment
C. Direct subcontractors at the site
D. Collect Affidavit of Lien Releases
C. Direct subcontractors at the site
Feedback:
Direct subcontractors at the site.
Architects have no authority to stop work or direct subcontractors or employees of the General Contractor.
According to AIA B101, the Architect grants to the Owner a nonexclusive license to use the Architect’s ___________ solely and exclusively for the Project, provided the Owner substantially performs its obligations, including prompt payment of all sums when due.
A. Drawings & Specifications
B. Instruments of Service
C. Copyright
D. License
B. Instruments of Service
Feedback:
Instruments of Service. See AIA B101, Article 7 - Copyrights and Licenses, Article 7.3