Test 2.4 Flashcards

1
Q

Open Specifications
o Suitable wording “or approved equal

Janitor door: with Vonciles name

A

following a brand name

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Open Specifications
o Or-equal provisions

ground janitors closet: with a trash can of non GP products going in.

A

use of alternate materials or products without adversely affecting quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

open specifications in terms of owner

shelves: with empty spaces for recommendations

A

Achieving benefits from competitive bidding and contractor expertise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

open spec. how to determine equal

hallway: made of money of different bills with BQP ice cream truck

A

could be used only to save money

equal doesn’t mean Not identical!
o Carefully determined based on the quality and performance when compared to brand-name products listed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Other Material Specification Types
 Combination type

walker chairs visitation: with bleach being poured all over it.

A

Base-bid materials specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Other Material Specification Types
 Contractor prepares a base bid based on

wood glue pane: create wood spec book

A

provided specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

who makes decisions of approved substitutions…

and approved substitution will what

walker and his chair: changing glue line name

A

owner

will be incorporated into contract documents or into the contract by change orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost estimation

walker assistant:
helping out with paper work, layout, running and dropping off the papers.

A

compilation of many items that influence to the cost of project.
 Performed before the physical performance of the work
 It requires detailed study of the bidding documents and site conditions
 The most accurate estimate possible within the given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

 Construction costs are estimated to serve a variety of purposes
In competitive bidding

assistant deck: sliding money under the table.

A

It allows contractors to win the bids and stay in business

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

 Construction costs are estimated to serve a variety of purposes
In negotiated contract

walkers microwave: using popcorn button

A

The contractor is expected to provide reliable cost information to continue the relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

 Construction costs are estimated to serve a variety of purposes
In design-build and construction management contracts

ram bow room door: seniority room

A

Input from cost estimating plays an important role in developing the final design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Construction estimating vs. industrial practices

ram bows microwave:
standardized broken date.

unique foods break it.

floor space: standardized wooden floor, but room has weird angle.

A

 Standard costs and conditions allow manufacturers to predetermine the unit cost in an almost exact way
 Unique situations in construction projects and complicate factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

estimating
 No standard procedures

ram bow desk:

A

 Form of worksheets, order of procedures, mode of applying costs, etc.
 How to suit construction companies’ need

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Lump-sum estimates

ram bow: yearly salary given to him on the first

A

Contractor agrees to perform a prescribed package of work for a fixed amount price.
(General building construction)

contractor agrees to carry out its responsibilities even though the cost may exceed the stipulated amount

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Lump-sum estimates applied when

cabinets” artistic cover.

A

When the nature of work and quantiles are well defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Lump-sum estimates simple process to owner

paper in cabinets: with money equations being written on them

A

Making financial arrangements easier for the project

17
Q

Lump-sum estimates starts with

ram bows window: equipment survey

A

quantity takeoff” (or quantity survey

18
Q

Unit-price Estimates used when and applied when

conference room: with management discussing common goal of MOPED

A

 Often used for engineering construction project

 Applied when the nature of the work is well defined, but not the quantities

19
Q

Unit-price Estimates quality survey in each bid item serving as a basic for

computer: emailing steel bros

A

computing costs and checking the accuracy of engineers estimated quantities.

20
Q

Unit-price Estimates

excel segregation on color and zooming in.

A

 All costs are kept segregated according to the bid requirements
 Certain contract provisions make adjustment to the unit cost when actual quantity is above or below estimated amount significantly

21
Q

Approximate Estimate is also called what
and is what in terms of GC

tables conference room:: set up for bid day

A

 Also called “conceptual cost estimate”

  • To check subcontractor’s quotes or set up target estimate for the owners.
22
Q

Approximate Estimate in terms of owner

chairs conf. room: designed sitting.

A
  • To establish a preliminary budget during the (preliminary) design phase
23
Q

Approximate Estimate based on

white board conf. room: time line

A

historical cost data with necessary adjustment to reflect current project conditions

24
Q

Approximate Estimate commonly used methods

exit door conf. room: cost

A

▪ Cost-per-function estimate: i.e $/space
▪ Area cost estimate: $/SF for home const
▪ Volumetric cost estimate: $/CY

25
Q

Approximate Estimate commonly used methods
- Modular takeoff estimate

adam’s room door: buidling

A

Estimated cost of a representative module

26
Q

Approximate Estimate commonly used methods
Panel unit cost estimate

cabinets adams: sop plans

A

: Based on unit costs per SF of floors, walls

27
Q

Approximate Estimate commonly used methods
- Parameter cost estimate

chipper window: units

A

Unit prices established for building components

28
Q

Approximate Estimate selecting number fro

adams guest chair. about finishing

A

Books, trade magazines, journals, and contractor’s past experiences