Test 1 Flashcards

Master practice test 1

1
Q

Which SAFe Core Competency describes a set of values and practices that encourages individuals and the enterprise as a whole to continually increase knowledge, competence, performance, and innovation?

A

Continuous Learning Culture

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the part of Inspect and Adapt (I&A)?

A

PI System Demo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In a Portfolio Kanban System, at which stage is a Minimum Viable Product (MVP) build and evaluated?

A

Implementing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

True or False. The Release Train Engineer summarizes the team objectives into the ART PI Objectives in a format suitable for management communication.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who owns features in SAFe?

A

Product Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Product Managers are expected to collaborate in planning the amount of upcoming Enabler work by establishing what?

A

Capacity Allocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the primary purpose of PO Sync

A

To assess progress of the PI and adjust scope & priority as needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When does PI System Demo occur?

A

At the end of each PI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which core competency in SAFe 6.0 has the purpose to help drive Built-In Quality practices (including critical skills of Scrum, Kanban)?

A

Team & Technical Agility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the pattern for splitting Features into Stories? (there are 10, know all)

A
  1. Workflow Steps
  2. Business rule variations
  3. Major effort
  4. Simple/complex
  5. Variations in data
  6. Data entry methods
  7. Defer system qualities
  8. Operations
  9. Use case scenarios
  10. Break out a spike
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

During Epic creation, Lean Business Case can identify the impact on Sales and which other areas?

A

Deployment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Content of the Team Backlog are?

A

User Stories

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The WIP limit at Analyzing step of the ART Kanban is based on the overall availability of Product Management, other subject matter experts, and the capacity of which other roles?

A

System Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Features in ART Backlogs can result from what?

A

Decomposing Epics or Capabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How frequently should the ART Backlog be reviewed?

A

Continuously