5: Executing the PI Flashcards
PO Sync, System Demo, Innovation & Planning Iteration, Inspect & Adapt
Which 2 roles can facilitate the PO Sync?
Product Management OR RTE (Release Train Engineer)
Who participates in the PO Sync?
PMs, POs, stakeholders, SMEs
How often does it occur & for how long?
Weekly or more frequently
30-60 minutes
How often should a Demo of the full system increment occur?
Every 2 weeks
Demos occur after what?
the Iteration Review
(may lag as much as 1 Iteration max.)
Which environment should demos happen in?
Staging environment that resembles production as much as possible
What are the 4 SAFe Core Values? (ARRT)
Alignment
Respect for People
Relentless Improvement
Transparency
When PI Planning and IP Iteration happen in relation to one another?
PI Planning occurs on cadence w/in the IP Iteration
These 3 aspects are parts of what event?
1. PI System Demo
2. Quant & Qual Measurement
3. Retrospective & Problem-Solving Workshop
Inspect & Adapt event