T/F. A CPR must be submitted even if a contractor did not perform work during a certain week.

A

FALSE
A Statement of Non-Performance is submitted when work is not performed during a certain week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

T/F. Custodial services are subject to prevailing wage.

A

FALSE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

T/F. The Fringe Benefit Statement is penalizable.

A

FALSE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

T/F. eCPR submitted onto the DIR website is sufficient to satisfy payroll records per Labor Code 1776(a).

*Bonus question: What is Labor Code 1776(b) about?

A

FALSE.

Per Labor Code 1776(a), each Public Works contractor must submit regular COR and keep accurate payroll records for the Payroll Commissioner, who provides A-1-131.

Labor Code 1776(b) explains the requirement of CPR, including verification by declaring “under penalty of perjury”; true and correct payroll information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

T/F. Warranty Work is covered under prevailing wage.

A

TRUE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

T/F. A contractor is responsible for a tier sub-contractor.

A

TRUE.
Prime is always responsible for all subs working on a project.
(Contractor Information Sheet)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

T/F. Only a canceled check is sufficient as proof of payment to employees.

A

FALSE.
Proof of Payment AND Itemized Wage Statements is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

T/F. Certified Payroll Records must contain full SSN of employees.

A

TRUE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

T/F. Proof of submission is required to verify DAS 140 & DAS 142 forms.

A

TRUE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

T/F. Training contributions need to be paid if a contractor utilizes an apprenticeable craft.

A

TRUE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

T/F. Marking Box 2 on the DAS 140 indicates signatory status.

A

FALSE.
Box 2 indicates the contractor is non-signatory to a union, but still adheres to the Laborer Union Trust standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

T/F. An apprentice can be alone on-site.

A

FALSE.
However, if a Union contractor has a CBA or MLA that allows an apprentice to work alone, then it is okay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

T/F. If a worker that is classified as an apprentice on payroll is NOT certified, he/she must be paid the JM Rate.

A

TRUE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

T/F. Training payments need to be made for all hours worked for every apprenticeable classification.

A

TRUE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

T/F. Contractors can reduce the BHR in order to raise the Training Payment.

A

FALSE.
The BHR must be met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

T/F. Employer payments are a credit against the obligation to pay the employee’s prevailing wage BHR.

A

FALSE.
Employer payments are separate from the BHR. The BHR is a prevailing wage obligation that must be met.

17
Q

T/F. THR has to be met as long as BHR and Training are each being met.

A

TRUE.

18
Q

T/F. A contractor is non-compliant if they have not given Alliant CPR in 14 days.

A

FALSE.
As long as the contractor submits CPR within 30 DAYS, they remain compliant.

19
Q

T/F. An RFI is sent to the Prime or Sub to explain discrepancies in payroll documentation and how to correct them.

A

TRUE.
RFI’s are a communicative tool to request any documentation or to advise a contractor.

20
Q

T/F. A completed RFI should be saved as a Word Doc with the date on which it was sent out.

A

FALSE.
A completed RFI should be saved as a PDF, not a Word Doc.

21
Q

T/F. The RFI items must be highlighted and deleted from the latest draft once the clerk receives the request items from the contractor.

A

TRUE.