Summary of Experience Questions Flashcards

1
Q

Why was it considered acceptable to remove the speed ramp at Catford shopping centre?

A

Suggested that the ramp had deteriorated due to heavy laden trucks going over it, which was no longer protecting the movement joint. Cracks were equal width at top and bottom suggesting it was not heave or subsidence. (ramp was mainly there to protect the movement joint)

Result of differential movement and not aware if crack was progressive. This would need to be reviewed via specialist vibration monitoring which is why removing the speed ramp was a short term recommendation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What was the proposed new movement joint?

A

Wabo®ElastoFlex (EFJ) provides a continuous membrane combined with heavy duty, steel reinforced EPDM rubber blocks. The system is designed for heavy duty applications in parking decks, loading docks, elevated roadways, convention centers, stadiums and other vehicle and forklift traffic conditions.

ElastoFlex is a watertight continuous membrane system for joints with movements up to four inches. The system uses mechanically fastened EPDM anchor blocks with molded-in steel inserts to support heavy duty and high impact loads.

The winged flange of the durable elastomeric seal is locked between the anchor block and concrete slab and recessed flush for a smooth walking and driving surface. A sealant bedding compound is applied between the winged flange and concrete slab to enhance the product’s watertightness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How would you have assessed the crack movement?

A

Shock 300 Vibration Monitoring System and Logger and plastic tell tails.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Banbury Court – How did you assess the EoT was valid?

A

reviewed the facts and information presented, assessed the critical path (floor works had to be done at the end of the programme), and reviewed actual vs planned works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you summarise what you understand from the RICS Design and Specification Guidance?

A

1st edition, 2013 – details information around the appointment, design and lead consultant, (compliance, sustainability and safety), risk management, design process management (occupational – end user, use centered – general facility for broad range of users, KISS, pragmatic – creative & multiple concepts, critical design – key drivers for the space,e.g. open plan or sustainable materials), establishing the project (brief and feasibility), preparing the design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some of the changes for the new JCT 24 suite of contracts?

A

express provision to collaborate in good faith (no longer supplemental provision), new epidemic relevant event has been included and grounds for termination, unexploded ordinance, asbestos and contaminated land should no longer give rise to an automatic relevant event or matter, notifications of disputes in order to promote ‘good faith’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you name me 2 types of RCA?

A

Day one reinstatement, reinstatement including inflation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is IPMS? Why is it important?

A

An International Property Measurement Standard (IPMS) will ensure that property assets are measured in a consistent way, creating a more transparent marketplace, greater public trust, stronger investor confidence, and increased market stability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you explain the internal dominant face rule?

A

The internal finish comprising more than 50% of the floor to ceiling height for each IDF Wall Section. If such does not occur, the Finished Surface is deemed to be the IDF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Client Care and how did you ensure this was met at Grosvenor Place?

A
  • Providing a standard of service that is in line with the clients requirements including
    o Professionalism
    o Honesty, integrity
    o Good quality and diligent service
  • I achieved this by maintaining strong communication with the client, establishing a strong project brief and achieving the key KPI’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Workman’s business plan?

A
  • To have an inclusive environment and happy workplace
  • To provide a high standard of service
  • To achieve 5% increase in profits.
  • Promote sustainability,
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a fire strategy?

A
  • A complex document specifically tailored to a building, reviewing all aspects of the building’s fire safety features including construction, compartmentation strategy, means of escape and other fire safety features/measures.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Are you aware of any other methods which could be used to investigate the tracking water?

A

Dye Penetration Testing
- Flat Roof Electronic Leak Detection (Non-invasive) – involves an electrical pulse through a wire ring circuit chooses a path across the moisture to where the leak is located. Roof membrane is non-conducting.
- Dynamic leak investigation – combines ELD and rainfall simulation to confirm whether a leak has been sealed correctly.
- Electrical capacitance test is non-destructive test which identifies entrapped water within a roofing construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If a client asks you to act on his behalf in a dilapidations situation, what questions would you ask?

A
  • Are you landlord or tenant? Who is the landlord/tenant?
  • At what stage in the lease is it/What is the current situation?
  • Is it a full repairing and insuring lease or an internal repairing lease only?
  • Can I have a copy of the lease and any associated documents licences to alter, licences to assign, schedule of condition etc?
  • How can I arrange access?.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you ensure your dilapidations survey/claim is accurate?

A
  • Review lease covenants to understand extent of tenant’s obligations.
  • Establish whether there is a schedule of condition.
  • Review any LTA information to establish extent of tenant’s alterations.
  • Establish client’s intentions to understand whether there is any limitations to repair.
  • Take measurements on site to allow for accurate rates.
  • Consult specialist consultants i.e Structural Engineer or M&E engineer if deemed necessary.
  • Use BCIS, Previous Tender/QS rates to provide accurate costs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How did the schedule of condition affect your dilapidations claim?

A
  • Repair covenant was limited as tenant was to return the unit to the condition as stipulated within the schedule of condition so elements of repairs couldn’t be claimed for.
  • Any guidance or legislation you can refer to?
  • Section 18 – Landlord and Tenant Act 1927.
  • RICS Guidance Note on Dilapidations in England and Wales 7th Edition 2016.
17
Q

What is the case of McGlinn v Waltham Contractor’s Ltd?

A
  • However, the case of Ian McGlinn v Waltham Contractors Limited lays down some useful general principles that will be taken into account when a court needs to determine if an Architect or Project Manager has fulfilled their inspection duties.
  • The frequency and duration of inspections should be tailored to the nature of the works going on at the site from time to time.
  • Depending on the importance of the particular element or stage of the works, the inspecting professional can instruct the contractor not to cover up the relevant elements of the work until they have been inspected.
  • The mere fact that defective work is carried out and covered up between inspections will not automatically amount to a defence to an alleged failure on the part of the Architect to carry out proper inspections.
  • If the element of the work is important because it is going to be repeated throughout one significant part of the building, then the inspecting professional should ensure that he or she has seen that element of the work in the early course of construction/assembly so as to form a view as to the contractor’s ability to carry out that particular task.
  • Reasonable examination of the works does not require the inspector to go into every matter in detail.
  • The Architect does not guarantee that their inspection will reveal or prevent all defective work. It is not appropriate to judge an Architect’s performance by the result achieved.
18
Q

How do you assess quality on site? How do you communicate this to PC and client?

A
  • Works are being undertaken as per schedule of work workmanship and materials.
  • Works are as per any design drawings.
  • The project is being constructed in accordance with current legislation and contract documentation.
  • Works are in-line with RAMs.
  • The consultants to attend site to review specialist works at correct times of the programme.
  • Note any design changes on site.
  • Snagging lists
19
Q

Summarise the Fire Safety Act 2021

A
  • April 2021 & amended the Regulatory Reform (Fire Safety) Order 2005
  • The act clarifies that Responsible Persons for multi-occupied residential buildings must manage and reduce the risk of fire for the structure and external walls, including cladding, balconies and windows, entrance doors to individual flats that open into common parts.
  • Introduction of the Fire Risk Assessment Prioritisation Tool
  • Responsible persons must carry out FRA and allows the Fire and Rescue Service to enforce against non-compliance
  • A Responsible Person is defined in the Fire Safety Order as anyone who has control or anyone who has a degree of control over certain areas within the premises.
  • The definition of control is wide-ranging and includes, for example, landlords, tenants, occupiers, employers, and managers.
20
Q

Do you have to have a Fire Strategy?

A
  • Where a building is erected or extended, or has undergone a material change of use, Regulation 38 of the Building Regulations requires that a package of fire safety information must be assembled and given to the responsible person of the premises.
21
Q

When must a building have more than 1 fire escape staircase?

A
  • When they are between 18-30m in height they must have at least 2 fire escapes
22
Q

What is the lime cycle?

A

The image illustrates how limestone (calcium carbonate) turns into quicklime after heating, then into hydrated lime (slaked lime or calcium hydroxide) after adding water and finally back into chalk by combining with carbon dioxide from the air.

23
Q

Why is the lime cycle important?

A

The lime cycle shows the stages from quarrying the limestone through to the production of mortars and plasters for our buildings and how it slowly, through the re-absorption of Carbon Dioxide, reverts to its original chemical form (Calcium Carbonate) in the wall.