Case Study Question Bank Flashcards

1
Q

What is the age and construction of the property?

A

1980’s construction, steel portal frame with metal roof sheets, dividing blockwork walls, brick façade, pad foundations with concrete floor slab, mezzanine and two floors of ancillary offices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What typical foundations would you find in a steel portal frame?

A

pad foundation with ground bearing concrete slab

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why did you pick a JCT Intermediate with Contractors Design Portion?

A

requirement for named sub-contractors for the PV installation, professional indemnity insurance and collateral warranties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was the Contractors Design Portion?

A

split air source heating and cooling, PV installation, Lighting design, drainage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why did you choose an Intermediate with Contractors Portion over a Minor works with CDP?

A

named sub-contractors and collateral warranties, PI insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You mention that you are principal designer; however, in the personal involvement you do not reference this. Why is that?

A

assisted the cost consultant and PD, insurance requirement and office practice that only Chartered Surveyors carry out the lead role of PD and cost consultant to sign off variations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Procurement Section- you mention focusing on the costs rather than time and quality- why is that? Was this your preference

A

cost and programme were key client objectives, given the intention for a tenant to take the space and fit-out, bespoke furniture or fittings were not deemed critical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can you explain how you managed client expectations in terms of sustainability goals versus budget constraints?

A

formed part of the feasibility study for appraising EPC objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

During your initial site visit, how did you assess the condition of the roof, and what tools or methods did you use to identify water ingress issues?

A

internal inspection, identified points of ingress around lap joints, causing internal lining to fail, roof was inspected further once scaffolding was installed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the difference between named and nominated sub-contractor?

A

Nominated subcontractors are pre-selected by the client and then imposed on the contractor once in contract. Such arrangements are usually borne out of working together earlier in a projects development, such as the feasibility stage, where the specialist has provided input which has in turn allowed the client to drive their project forward to the build stage. The naming of subcontractors allows clients to influence the tender list but does not result in them taking on the liability of the subcontractor’s performance. In effect, the client lists a minimum of three subcontractors they have deemed as acceptable to carry out the works. In many cases, the client may already have a quotation agreed for the works with each subcontractor.

  • Benefits of nominated includes, feasibility of specialist input, starting procurement of long lead items, design certainty, may create trust with sub-contractor if the client routinely uses them
  • Cons – performance delays or insolvency, Contractor must agree as may be taking on the burden if the nominated sub-contractor becomes insolvent, less competition (client is at risk for non-performance and contractor can be issued an EoT)
  • Named sub-contractor shows that the Client has a preferred option and influences the tender list, but does not bind the main contractor to using them (nominated sub-contractor clauses have been removed from JCT)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What specification was used for the roofing system?

A

proprietary specification (In general, proprietary specifications are descriptions of materials that either cite a specific brand name or are written so restrictively that only one vendor or manufacturer can supply the desired items).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What were the minimum roller shutter U-Values?

A

1.4 w/m2.k minimum is 4.5 w/m2.k

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What was the existing fire protection of the steel frame?

A

existing vermiculite was retained in the office areas and any damaged areas were replaced with cement board and intumescent mastic. Main portal frame did not need fire protection as does not form a compartment floor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What was the existing EPC rating of Thomas Road Industrial Estate

A

EPC D rating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How are EPCs calculated?

A

Standard Assessment Procedure, considers end users and models building materials against benchmarks to establish thermal performance. Standard Assessment Procedure (SAP) methodology, which underpins the Energy Performance Certificate (EPC). The assessment is based on standardised assumptions for occupancy and behaviour. This enables a like-for-like comparison of dwelling performance. Related factors, such as fuel costs and emissions of carbon dioxide (CO2), can be determined from the assessment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What do you need to be qualified to assess EPCs?

A

carry out a course, can either be Domestic Energy Assessor, On-Construction Energy Assessor (newly build homes) and Non-Domestic Energy Assessor (only commercial)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What way does the property face?

A

South West

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How did you appoint your EPC assessor?

A

Agreed scope of services, fee draw down, capacity, PI insurance, assumptions & exclusions, Terms & Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What assessments did you undertake for the proposal of the PV panels

A

this was undertaken by the PV manufacturer prior to undertaking the works.

Sub contractor used solar edge designer which works out orientation, generation, shading (no shading here) etc, but no glare assessment on this one - a glint and glare study is only usually required if requested by the client if you are near an airport

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Was planning permission required for the PV panel installs?

A

no, fell under permitted development order 2015 (Class J, Part 14, Schedule 2 of the GPDO)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What consent can you look to obtain for permitted development if unsure

A

Certificate of Lawfulness of Permitted Use or Development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What was the specification for the lighting?

A

CIBSE guide for lighting, 140 lumens per watt 100% light output ratio. Typically require 500 lux level for offices and 300 lux for offices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What qualifications did the PV installer have?

A

MCS self-certification scheme (The Microgeneration Certification Scheme (MCS) is a mark of quality assurance in the renewable energy sector. It’s aimed at businesses that install small-scale renewable or low-carbon heat and power solutions, and it indicates that these businesses operate to high industry standards, as outlined by the MCS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Who regulates GDPR in the UK?

A

ICO - Information Comissioners Office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Can you explain to me what CSR is

A

Corporate social responsibility (CSR) is a broad business concept. It usually describes a company’s commitment to carry out its business in an ethical way. This means managing their business processes while taking account of their social, economic and environmental impact, and considering human rights.

26
Q

What is the Considerate Contractor’s Scheme?

A

The Considerate Constructors Scheme is the national initiative set up by the construction industry to improve its image. Construction sites and companies that register with the Scheme are monitored against a Code of Considerate Practice, designed to encourage best practice beyond statutory requirements.

27
Q

Garland Liquid applied coating process

A
  • Technical rep must attend site and carry out an adhesion test to ensure that the membrane is suitable for the substrate
  • Substrate must be cleaned of any microorganisms using appropriate solutions and/or fungicidal solutions and power washed with a minimum of 2000 psi
  • Existing coatings or paint must be eliminated by shot blasting or grinding
  • Non-adherent or friable areas should be removed
  • Substrates must not have a moisture content higher than 4%
  • Surface water and contaminants must be cleaned from the substrate
    Installation:
  • Vacuum clean surface to remove dust and apply metal primer with hand roller
  • Apply 1 no layer of dura-system membrane mixed with membrane mix at 30:70 ratio to prevent slumping
  • In the wet coating, bed in minimum 150mm wide strip of grip polyester soft reinforcement centred onto the sheet laps and heads and apply second coat of dura-system membrane
  • Mask off areas and apply dura systems coloured topcoat (contains resin) (dura-coat must first be mixed with the catalyst for a minimum of 1 minute
    o If contaminants or moisture is present then remove topcoat with dura-systems cleaner
28
Q

What is the Garland Dura-coat made out of?

A

Epoxy resin Polyurethane modified methyl-methacrylate (MMA) resin

  • Roofing system should be installed in inclement weather
  • Air temperature must be between 0-30 degrees but substrate must be 5 degrees above dew point
29
Q

How do photovoltaic solar panels work?

A
  • PV cells located in panels which convert the UV rays into DC current
  • Current then flows to inverter which converts to AC electricity
  • Current is fed through a meter and into consumers unit
  • Power purchase agreement is then agreed with the Tenant to sell the energy to them
30
Q

How did you ensure the PVs were permitted development?

A
  • Must not protrude more than 0.2m beyond the external pitch of the roof
  • Must not be higher than the highest pitch of the roof (excl. chimneys, flues etc)
  • Must minimise its effect on the external appearance of the building
31
Q

What brickwork repairs did you undertake?

A
  • Defective pointing to be removed to a minimum depth of 25mm. All joints to be repointed in sand:cement 1:5 mix, to include all admixtures as required to match existing shade and finish. All new pointing to comprise neat finish to match adjoining surfaces and to be undertaken in accordance with BS 5628: Part 3
32
Q

What was the window specification?

A
  • multilight construction, with outward opening side or top-hung casements. Finished in polyester paint finish colour
33
Q

What are double glazed windows?

A
  • One pane of glass is fitted with the spacer bar in position before being moved through an argon-filled chamber. The second pane is pressed on top to seal the unit and trap the argon gas, creating a vacuum. Argon gas is used for double glazing because it is more dense, slow-moving and less conductive.
34
Q

What is a U-Value?

A
  • the ability of an element to transmit heat from a warm space to a cold space in a building, and vice versa to change the temp by 1 degree. The lower the U-value, the better insulated the building element.
35
Q

What was the required U-Value for the windows?

A
  • 1.4 W/(m2K)
36
Q

What are the required U Values for Roofs, Walls and Floors?

A
  • Pitched Roofs: 0.16 W/m²K.
  • Flat Roofs: 0.18 W/m²K.
  • Walls: 0.26 W/m²K.
  • Floors: 0.18 W/m²K.
37
Q

What is an R Value?

A
  • An insulating material’s resistance to conductive heat flow is measured or rated in terms of its thermal resistance or R-value – the higher the R-value, the greater the insulating effectiveness. The R-value depends on the type of insulation, its thickness, and its density.
  • 10 cm of insulating material with a ƛ of 0.05 W/mK results in a R-value of 2 m2K/W.
  • The better the insulating material (lower ƛ), the thinner the layer insulation needs to be to achieve the same result in terms of thermal insulation.
    o The ƛ-value measures the thermal conductivity of materials. It is also called the thermal conductivity coefficient.
    o i.e. width of insulation / thermal conductivity coefficient
38
Q

What were the existing rooflights?

A
  • Filon GRP single skin rooflights to be fully adhered to the profiled roof sheet covering with 50mm butyl double sided adhesive tape with permanent stretch backing applied over the lap and to be suitably fixed to the profiled roof deck to achieve minimum 150mm overlap detail. All fixings to the existing roof covering are to be capped with a suitable plastic capping to leave a fully watertight construction detail. New roof lights are to achieve a minimum Class B non-fragility.
39
Q

What are the fragility classes for rooflights?

A
  • Class 1 – this describes glass that is designed to be walked on for occasional maintenance. This usually refers to cleaning which in return will support the weight of people and equipment without the outer pane breaking.
  • Class 2 – this describes glass that is not designed to be walked on but is still required to be non-fragile in the event of a person falling on the surface. The glass in this case will support the fall but may become damaged.
  • Class 3 – this describes rooflights which are considered to be fragile. In this case additional measures and safety considerations should be taken into account and guard rails erected to prevent falls.
40
Q

How was the warehouse floor prepared?

A
  • Remove all redundant fixing bolts in the warehouse floor slab by grinding back to recess below finished floor level. Resin fill all holes, large indentations, etc. with Watco Flowpatch rapid set self levelling epoxy mortar’
    o Wire brush cracks and vacuum to clean area, use SBR primer, mix 3 part mixture then leave to set for 2-4 hours and lightly trowel finish
  • Abrasive clean floor slab to remove tackifiers by vacuum assisted diamond grinder
  • Install of watco epoxicote high build
    o Clean floor of grease, dirt or moisture
    o Apply 1 coat of high build primer
    o Apply 1 oat epoxicote high build
    o Cures for light traffic within 8 hours
     Strong chemical resistance
     220 microns thickness
41
Q

How is asbestos encapsulated?

A
  • Isolate area from the rest of the building by sealing off doors, windows and ventilation systems as well as setting up negative air pressure units and using specialised equipment such as HEPA filters to capture airborne asbestos fibres
  • Clean and repair asbestos by removing loose/damaged asbestos fibres and reparing or sealing any cracks or gaps in the ACMs
  • Apply encapsulation material / coating to create protective coating
    o Perfect primer is the best asbestos sealer
42
Q

Why were the works not notifiable or licenced?

A

Permitted works as per the HSE government guidance:
* Cleaning up small quantities of loose/ fine debris containing ACM dust (where the work is sporadic and of low intensity, the control limit will not be exceeded and it is short duration work)
* Drilling of textured decorative coatings for installation of fixtures/fittings
* Encapsulation and sealing-in work on asbestos-containing materials (ACMs) that are in good condition

43
Q

How do split AC air-source heating and cooling pump systems work?

A
  • Split air conditioning systems operate using the refrigeration cycle to pull hot air out of your home and replace it with cool air. Air from your home is pulled into the system using return vents. This air is circulated through the system and will eventually blow over the evaporator coil—housed in the indoor unit of a split system—where it will rapidly cool before being put back into your home via the supply vents.
    The refrigeration cycle, another common HVAC term, refers to the compressor, condenser, and evaporator coils located in your HVAC system. The compressor and condenser are located outdoors and are responsible for expelling heat (this is why the large fan on your outdoor unit is always blowing hot air). Once heat has been expelled, the refrigerant returns to the indoor unit where it will rapidly expand, which creates a strong cooling effect that runs through the evaporator coils, which is where your circulated air is being pushed through before it returns to your home.
  • 2 pipe system can do either heating or cooling, 3 pipe system can do both simultaneously
44
Q

What were the performance requirements for the AC?

A
  • System to be designed to COP (Coefficient of performance) 4, SEER (Seasonal energy efficiency ratio) 5, (Energy Efficiency Ratio) EER 3.5
45
Q

When was Approved Doc T Introduced?

A

October 1st 2024

46
Q

What are the key changes to Approved Document T?

A
  • No longer permitted for both sexes to use the same WCs and hand wash facilities in the same room. This requirement is first and foremost. Universal toilets for use by both sexes can be provided in addition to the single-sex toilets - these will be single rooms or cubicles with integral basins. If space restrictions will not allow the provision of single-sex toilets, universal toilets can be provided only.
47
Q

How would you ensure the roof works fell under permitted development?

A
  • the development is within the curtilage of an existing industrial building or warehouse
  • constructed using materials which have a similar external appearance to those used for the existing industrial building or warehouse
48
Q

When would overcladding not be permitted development?

A

(a)it would materially affect the external appearance of the premises of the undertaking concerned; or
(b)any plant or machinery would exceed a height of 15 metres above ground level or the height of anything replaced, whichever is the greater.

49
Q

What section is overclad included within PDO 2015?

A
  • Class H (The erection, extension or alteration of an industrial building or warehouse), Part 7, Schedule 2
50
Q

How does an air source heat pump work?

A
  • brings in hot air (even as low as -15 degrees)
  • Then compresses the refrigerant to increase its temperature and turn it into a gas using a compressor
  • set to indoor units and passes over the unconditioned air to heat / cool
51
Q

Why was the mezzanine not fire rated?

A

All mezzanines that act as an additional storey within your premises, like a retail or office mezzanine, will need to be fire rated to ensure the safety of members of the public and employees. However, some mezzanines that are used solely for storage purposes won’t need to be, as long as:

  • The area of the mezzanine does not exceed 400m2
  • The mezzanine floor is <50% of the total size of the room that it is installed
  • The mezzanine floor is less than 20m in each direction
52
Q

What goes into nominating a contractor?

A
  • Quality of submission, clearly understanding the scope and nature of works
  • Competitiveness
  • Qualifications, accreditation
  • Providing contractor proposals, programme of works, evidence of insurance
  • PQQ’s
  • Assessing finances
53
Q
  • Can you talk me through the EoT process for this project?
A

variations and leak from the adjoining tenants demise. Reviewed the facts and information received, critical path analysis to establish if the delays materially impacted the programme, and reviewed proposed vs actual progress. Contractor submitted a cause and effect statement.

54
Q

What is the difference between performance and prescriptive specification?

A

Performance is outcome focused, allowing design input from the contractor, prescriptive retains design intent and advises on performance requirements, e.g. u-values & British Standards.

55
Q

What fire certification was provided with the PVs?

A

IEC class C (International Electrotechnical Commission) (minimum requirement and assesses spread of flame and burn brand test)

56
Q

What was the spec of the PVs

A

Longi mono-facial modules

57
Q

What guarantee was provided for the install?

A

12 years product warranty for PVs and 5 years for the inverter

58
Q

What is a collateral warranty and why did you have one?

A

Created a contractual link between the sub-contractor and Employer in the event of insolvency of the main contractor, which is supplemental to the main building contract. Grants the rights to a third party for redress for the design / workmanship.

59
Q

What is permitted development?

A
  • grants planning permission for certain types of development without the requirement for approval from the local planning authority.
60
Q

What is the difference between local authority and Registered Building Control Approver?

A
  • Local authority is typically cheaper as are a non-profit and fee’s are published via the Council website, where as RBCA will be on a job-by-job basis
  • Will have a Registered Building Control Approver dedicated to the project so will likely be more responsive and quicker
    o Therefore will typically pay a premium for this
  • If using LA, you will need to apply for the Final Certificate yourself
61
Q

What are the EPC ratings

A

A+ - under 0 (net zero CO2)
A - 0-25
B - 26-50
C - 51-75
D - 76-100
E - 101 - 125
F - 126-150
G - >150

62
Q

What was the Unit’s updated EPC rating?

A

-13 A+