Summary of Experiance Questions Flashcards

1
Q

1) Simply describe the differences between the different forms of building contracts and when they are most suitable to use.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

1) What was the project under a JCT Intermediate Building Contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

1) What are the different forms of procurement, and when are they utilised?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

1) Explain why an accurate specification is important during the tendering and works process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

1) What’s the advantages and disadvantages between single stage and negotiated tendering?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

1) Whats the difference contractually between MW & IC Contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

1) What do preliminaries contain?

A
  • A general summary
  • Management of staff
  • Site establishment
  • Temporary services
  • Security
  • Safety and environemental protection
    (etc. etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

2) What were the challenges you faced whilst acting as contract administrator for the industrial unit refurbishment at st Andrew’s way?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

2) What are the payment timeframes listed in the contract?

A

MW = one month after the works commencement and thereafter at monthly intervals.
IC = one month after the date of posession and thereafter at monthly intervals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

2) What is the importance of accurate meeting minutes?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

2) What are the contractual effects that happen at PC?

A
  • Half of the retention is released.
  • Insurance transfers to the employer.
  • Posession thransfers to the employer.
  • Liquidated damages not recoverable.
  • Rectification period commences.
  • Instructions no longer given by the CA.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

3) Why did you not choose any of the other methods of procurement other than traditional for Waterside

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

3) What were the causes of the high-level windows being at a higher level of deterioration than the ones on the ground floor at Berry Street?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

3) If the client disputes the revised completion date, what process would you use to resolve this?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

3) What was the CD Portion to Waterside contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

3) At Berry Street what could you have added to the specification to prevent an EoT and allow the contractor to allow for replacement in the contract?

A

Defined PS

17
Q

3) How did you review the contractors EOT application? What did you review programme wise?

A