Contract Administation. Flashcards
What are the two elements needed to issue practical completion? (2 points)
- Draft O&M manual
- The works are substantially complete - premises are fit for beneficial occupation.
How can a contract end? (4 points)
- Performance under the contract
- Breach of contract
- Discharge by agreement
- Frustration
How can a construction contract be terminated? (3 points)
- Termination by the Employer
- Termination by the Contractor
- Termination by either party
Can you name some typical JCT contracts? (4 points)
- Minor works Building Contract.
- Intermediate Works Building Contract.
- Standard Building Contract.
- Design & Build Contract.
Do you know any other contract types? (2 points)
- NEC3 Contract – New Engineering Contracts: typically used for larger public sector works.
- FIDIC Suite of contracts – typically used for international projects which are contracting and funded across multiple legal jurisdictions.
What is retention? (1 point)
• Retention is a sum, usually deducted at each monthly payment notice, to provide the employer with some security in the event that defects occur after practical completion.
What is repudiation? (2 points)
Abandonment or refusal to carry out the work without lawful excuse is a repudiation.
Bad workmanship is unlikely to constitute repudiation, unless the breaches are so serious that the contractor is clearly unwilling or unable to complete the work.
What is ‘time is of the essence’? (3 points)
- Completion needed by a particular date.
- Considered fundamental breach if not achieved.
- For example, construction works required for a stadium before a certain big event.
When is the base date? (3 points)
A ‘base date’ is a reference date from which changes in conditions can be assessed.
The base date sets the reference date from which the conditions under which the tender was prepared are considered to have been known by the contractor and so are properly reflected in their price.
Typically, it is around 7-10 days prior to the date of the return of tenders.
What is the difference between the date for practical completion and the date of practical completion? (2 points)
- The date for practical completion is the date by which the contactor is required to finish the work as stated in the contract particulars or subsequently extended by the CA.
- The date of practical completion is when, in the opinion of the CA, the contractor has completed the works. It can be certified where there are very minor (de minimis) items ‘not affecting beneficial occupancy’ that remain incomplete.
What is the rectification period?
The period stated in the contract that provides for:
- the making good of minor faults and omissions; or
- items that fail to perform suitably that may be outstanding, or occur after practical completion has been reached and the contractor has handed the building over.
What is a patent defect?
A patent defect is visibly obvious or discoverable at time of construction before the Practical Completion certificate or the certificate of making good is awarded.
What is a latent defect?
A latent defect is hidden and only discovered at a later stage.
What certificate is issued at the end of the rectification period assuming the contractor has made good all patent defects?
The certificate of making good.
What are liquidated damages and how do these differ from unliquidated damages? (2 points)
- Liquidated damages are genuine pre-determined estimates set at the time that a contract is entered into, based on a calculation of the actual loss the client is likely to incur if the contractor fails to meet the completion date: loss of rent calculated on a weekly basis is the norm.
- Unliquidated damages are damages that are payable for a breach of contract, the exact amount of which has not been pre-agreed, and are typically determined by the courts.
When can LDs only be claimed? (2 points)
- On receipt of a certificate of non-completion by the CA (or EA) and
- When the employer has notified the contractor of his intention to do so.
Explain the situation when ‘time is at large’? (2 points)
- The phrase ‘time at large’ describes the situation where there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date.
- This is not a preferable to be in as it means that contractor it only obligated to complete the outstanding works in a reasonable time and as a certificate of non-completion has not been issued the employer cannot claim LD’s.
What is a collateral warranty? and provide 2 examples. (3 points)
- Agreements which are associated with the main contract and link a third party contractually to one of the members of the original contract.
- Example: tenant and contractor in case building is sold so tenant is recourse if defect in fit-out.
- Example: employer and sub-contractors in case main contractor becomes insolvent.
What contracts are collateral warranties available under, and which are they not available under? (4 points)
Available under:
- Intermediate
- Design and Build
- Standard Building Contract
Not available under:
- Minor Works
What is an ‘all risks policy’? (2 points)
- Contractors All-Risks (CAR) provides cover against loss or damage to the works and materials during construction.
- Typically issued under joint names of client and contractor.
What is a vesting certificate, and when are they typically used? (2 points)
- They are certificates which prove ownership of off-site materials to the employer.
- Typically used when advance payment by the employer is required to order particular materials/goods which have long lead times.
What is the difference between executing a contact under hand and under seal?
- Under hand = limitation period of 6 years – executing the contract as a simple contract.
- Under seal = limitation period of 12 years – executing the contract as a deed.
What is a variation?
A change to the work that the contract administrator instructs on behalf of the employer.
Variations may be an addition or omission from the work as originally specified.
What is a letter of intent and why would you use one?
Tool that allows work to commence on site while contract negotiations are concluded.