substation construction - foundations Flashcards

1
Q

When preparing an equipment foundation for a pour (concrete pad), frozen soil must be removed.

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When preparing an equipment foundation for a pour (concrete pad), ? should be placed and compacted where the pad is to be poured.

A

crushed rock

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Aluminum conduit or other aluminum products should not be encased in concrete because aluminum will ?

A

corrode

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A ? and/or leveling scope are both used to ensure that concrete forms are placed at the correct grade.

A

transit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If an anchor bolt is not in the exact required location, minor welding or bending of an anchor bolt is acceptable.

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

To ensure rebar meets specifications, a person should check the ?

A

rebar tags for suitable identification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A ? can be used on site to ensure that the concrete being delivered meets the required consistency.

A

slump test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Concrete should be vibrated ?

A

until it becomes uniformly plastic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Upon completion of the concrete pour, recheck the ? for correct location and elevation.

A

anchor bolts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A tremie pipe should be used to pour concrete ?

A

when concrete is to be dropped vertically more than 6’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

While there is still about 1/4 inch of water pooling on the concrete, the initial troweling with a wood float can be done.

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A ? is required over freshly poured concrete to aid the curing process.

A

plastic sheet that acts as a vapor retarder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Foundations poured during very warm weather may require that water be sprayed on the concrete surface at 24-hour intervals during the first three days.

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Forms are removed after concrete has set sufficiently, typically ? after a pour.

A

24 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly