Steam Boilers Module 15 Sessions 3 and 4 Flashcards
The most important fitting on a boiler is the \_\_\_\_\_\_\_\_\_\_\_. A. Low water fuel cutoff B. Feedwater regulator C. Superheater D. Safety valve
D. Safety valve
To prevent failure from pressure over the MAWP, all steam boilers must be equipped with at least one \_\_\_\_\_\_\_\_\_\_\_\_. A. Safety valve B. Blowdown valve C. Gauge glass D. Feedwater heater
A. Safety valve
A safety valve will \_\_\_\_\_\_\_\_\_\_\_. A. Control the boiler operating range B. Control high or low water C. Prevent the boiler from exceeding its MAWP D. Control high and low fire
C. Prevent the boiler from exceeding its MAWP
Safety valves are designed to _______________.
A. Open slowly to prevent water hammer
B. Pop open
C. Open only by hand
D. Open and then close with no drop in pressure
B. Pop open
Superheater safety valves are set to open
A. After the main safety valves are opened
B. Before the main safety valves are opened
C. Only when header pressure is 6% above the MAWP
D. When the boiler is coming off-line
C. Only when header pressure is 6% above the MAWP
When testing a safety valve by hand, there must be \_\_\_\_\_\_\_\_\_\_\_\_\_\_. A. At least 75% of the popping pressure B. No pressure on the boiler C. An inspector present D. Someone watching the water level
A. At least 75% of the popping pressure
Any repairs to a safety valve should be done by the _____________.
A. Chief engineer
B. State inspector
C. Manufacturer’s authorized representative
D. Maintenance department
C. Manufacturer’s authorized representative
The setting or adjusting of a safety valve should only be done by the ____________.
A. Boiler inspector
B. State inspector
C. Person in charge of the shift
D. Qualified person who is familiar with the construction and operation of a safety valve
D. Qualified person who is familiar with the construction and operation of a safety valve
If it is necessary to test the relieving capacity of a safety valve ____________.
A. An accumulation test is put on the boiler
B. A hydrostatic test is put on the boiler
C. The boiler must be secured and off-line
D. A bench test must be done
A. An accumulation test is put on the boiler
The relieving capacity of a safety valve is measured in ____________.
A. British thermal units
B. Boiler Horsepower
C. Btu per boiler horsepower
D. Pounds of steam per hour capable of discharging under a given pressure
D. Pounds of steam per hour capable of discharging under a given pressure
The main purpose of a water column is to ____________.
A. Reduce turbulence in the gauge glass to get a more accurate reading of the water level in the boiler
B. Reduce surface tension
C. Provide a means of putting an accumulation test on the boiler
D. Provide a place to install the boiler gauge glass
A. Reduce turbulence in the gauge glass to get a more accurate reading of the water level in the boiler
Try cocks are \_\_\_\_\_\_\_\_\_\_\_\_. A. Found on watertube boilers A Found on firetube boilers C. A secondary means of determining water level in a boiler D. Used to collect boiler water samples
C. A secondary means of determining water level in a boiler
When replacing a broken gauge glass, the water level is checked by ____________.
A. Blowing down the gauge glass
B. Blowing down the water column
C. Using the try cocks
D. Never check the water level; secure the boiler during repairs
C. Using the try cocks
The water column and gauge glass should usually be blown down \_\_\_\_\_\_\_\_\_\_\_\_. A. Once per week B. Once per shift C. When the boiler is coming off-line D. Never blow down under pressure
B. Once per shift
A Whistle valve is used to ____________.
A. Indicate it is 12:00 noon
B. Indicate a shift change
C. Warn the operator of high or low water
D. Warn the operator of a leaking blowdown line
C. Warn the operator of high or low water
A steam pressure gauge is calibrated in \_\_\_\_\_\_\_\_\_\_\_\_. A. Pounds per cubic inch B. Btu per pound C. Pounds per temperature increase D. Pounds per square inch
D. Pounds per square inch
A siphon protects the steam pressure gauge from \_\_\_\_\_\_\_\_\_\_\_\_. A. Boiler pressure B. High temperature of steam C. Water entering the Bourdon tube D. Air entering the Bourdon tube
B. High temperature of steam