Output is
Fixed by customer
To improve efficiency
Reduce associate power By relocating workers
4 elements of S. W.
Takt time
Capacity = operational time / (process time + setup / interval)
Work sequence
Work in progress
Key tools
Product capability charts - how many parts and people we need
Standard work analysis sheets- work layout. Process steps and times. Used for training
Standardized work combination chart
Operator balance chart also known as yamazumi stack chart. Broken up into tasks
SWIP time formula
Process time / takt time
Batch size no larger than
Cycle time / takt time
Standard work instructions
Are visual method of structuring every job providing easy info for operators and allowing kaizen
Efficiency formula
Efficiency = output/manpower