1
Q
Allowed controllable totex?
A
£1,667m
2
Q
ED1 spend?
A
£1,667m
3
Q
Non-controllable allowance?
A
£583m
4
Q
IQI?
A
-£7.0m penalty
5
Q
IIS?
A
£19.50m
6
Q
Guaranteed standards (reliability)
A
-£0.8m penalty
7
Q
Broad measure customer service (BMCS)
A
£8.0m reward
8
Q
Guaranteed standards (connections)
A
-£0.4m penalty
9
Q
Connections profit?
A
£8.0m
10
Q
Losses?
A
£2.3m reward
11
Q
Outperformance?
A
£0.0m
12
Q
IRR?
A
5.98%
13
Q
Value spread?
A
105bps
14
Q
Total allowance?
A
£2,240M
15
Q
Excluded corporate costs?
A
£52M