SOP - Time Management Flashcards
What is the most prevalent CPM network process used today?
- AOA
- ADM
- PDM
- PERT
PDM
(Precedence Diagram Method)
What are the objectives of CPM scheduling?
- Manage time, safety, and cost; integrate multiple parties; eliminate change orders; resolve disputes
- Manage time, resources, and cost; integrate multiple parties; evaluate options; resolve disputes
Manage time, resources, and cost; integrate multiple parties; evaluate options; resolve disputes
What are the four essential ingredients of the CPM schedule?
- Critical Path, Float, Constraints, Actions
- Activities, Early Start, Late Start, Float
- Logic Relationships, Activities, Constraints, Float
- Activities, Durations, Logic Relationships, Constraints
Activities, Durations, Logic Relationships, Constraints
CPM schedule includes the four main ingredients:
Activities
Durations
Logic Relationships
Constraints
Which of these is not a type of constraint?
- Date
- Cost
- Duration
- Float
Cost
Constraint types include date, duration and ________.
Float
What does the forward pass calculate?
- Early start/finish dates
- Start/finish dates
- Float
- Late start/finish dates
Early start/finish dates
Total Float =
- Early start – Late finish
- Late finish – Early finish
- Early finish – Late start
- Late finish – Early start
Late finish – Early finish
Late finish – Early finish = ___________
Total Float
Define the critical path.
- The critical path is the shortest continuous path of activities that controls the completion of the project.
- The critical path is the longest continuous path of activities that controls the completion of the project.
- The critical path is the most efficient path of activities that controls the completion of the project.
- The critical path is the most cost-effective path of activities that controls the completion of the project.
The critical path is the longest continuous path of activities that controls the completion of the project.
The critical path is the ________________________ that controls the completion of the project
longest continuous path of activities
What specifications are needed related to schedule requirements?
- Software, acceptance of contractor’s schedule
- Requirements for time-impact analysis, early completion
- Who owns float, weather delays, liquidated damages
What are the characteristics of a good schedule?
- Realistic, sufficient time, specialty work
- Open ended activities included, inflated durations as needed
- CPM activities indicate an early completion
- Schedule includes open ended activities
Realistic, sufficient time, specialty work
Who typically gets the benefit of the float?
- The owner
- The contractor
- The CM
- Whoever uses it first
Whoever uses it first
What type of delay is caused by unusually severe weather?
- Non-excusable delay
- Non-compensable delay
- Excusable delay
- Compensable delay
Non-compensable delay
The ___________ is the longest sequence of activities that controls the completion of the project.
Critical Path