Quality Management (23) Flashcards
The placement of quality concrete will require special measures when the outdoor ambient temperature exceeds:
90 degrees
The application of a planned and systemic program that demonstrates that quality control practices and tests are being effectively implemented is called:
Quality assurance
Concrete air-entraining agents are primarily used for:
Increasing the concrete’s resistance to freezing
What is the most important factor that would indicate to the CM that the owner’s team has a significant interest in achieving high quality on the constructed project?
Clear and concise requirements for inspection and testing in the contract documents
Who is solely responsible for the quality of the work?
Contractor
The Agency CM’s role in addressing non-conformances and corrective actions involves:
Inspecting the rework to ensure it was performed per the corrective action section of the non-conformance report
Who has the primary responsibility for delivering a project in accordance with the contract documents?
The contractor
Construction quality control is important to a CM who is responsible for determining:
Whether proposed project components conform to the drawings, specifications, and applicable standards
An implied warranty is usually provided by the:
Owner
When the CM is providing inspection services, which plan should be consulted to ensure that the contractor complies with the required inspection services?
Quality Management Plan
In determining the consistency of freshly made concrete, which of the following tests are usually conducted?
Slump test
What is the regular length of time for concrete to harden to its optimal strength under normal conditions?
28 days
The project owner considers quality to be the highest priority, followed by cost and schedule. You are concerned about the level of quality specified in the contract documents, and whether or not the owner’s expectations will be met. Which of the following is the most important?
Verification that materials and workmanship are installed in accordance with the approved submittals
What is the process entitled to verify and document the performance of mechanical, electrical, and other systems?
Commissioning
Final review and verification of construction scope, schedule and quality requirements by the parties should be conducted at the:
Pre-award conference
The process of evaluating the construction documents for clarity, consistency, completeness, and ease of construction to facilitate the achievement of overall project objectives is called a:
Constructibility review
What does the Construction Manager use and establish to keep the team informed about the overall status of the project?
Management information systems
Who is responsible for evaluating the contractor’s quality assurance/quality control program against the quality standards specified in the contract?
CM
Which of the following written plans outlines a project’s scope, organization and the specific approach that the CM will take to accomplish the various management tasks?
Construction management plan
Who is responsible for implementation of the quality control requirement during construction?
Contractor
The 7 day test results from the cylinder breaks for a major concrete placement indicate that the concrete strength is below the minimum psi specified at 7 days. What should the CM do?
Reference the test results in daily reports and wait to receive the 14, 28 and 56 day break results, if necessary; closely monitor design mixes and delivery tickets for compliance with specified strength for the next placements