Sometset Levels Case Study Flashcards
When we’re the Somerset floods
December 2013 to February 2014
What were the causes?
Low pressure systems coming across the Atlantic (weeks of rain)
Saturated soil
Wettest January on record
High tides/storm surges up Bristol Channel
Reduced river capacity due to a lack of dredging for 20 years
Who was blamed for the lack of dredging
The environmental agency
What were the social effects?
600 flooded homes
16 evacuated farms
Temporary accommodation for months
Villages cut off
Disrupted power supplies
What were the economic impacts
14000 hectares of flooded agricultural land
1000+livestock evacuated
Roads cut off
Closed railways
Estimated 10 million pounds of damage
What were the environmental impact
Contaminated river water
Debris deposited across land
Stagnant water has to be deoxygenated then pumped back into rivers
What management strategies were put in place
Straightening and rising of river banks
Somerset county council 20 million action plan
Rivers tone and parrat dredged in march 2014
Roads raised
Flood defences for at risk communities
Pumping stations built
Plans for tidal barrage at bridge water ok track for 2024