Q

When we’re the Somerset floods

A

December 2013 to February 2014

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the causes?

A

Low pressure systems coming across the Atlantic (weeks of rain)
Saturated soil
Wettest January on record
High tides/storm surges up Bristol Channel
Reduced river capacity due to a lack of dredging for 20 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who was blamed for the lack of dredging

A

The environmental agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What were the social effects?

A

600 flooded homes
16 evacuated farms
Temporary accommodation for months
Villages cut off
Disrupted power supplies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What were the economic impacts

A

14000 hectares of flooded agricultural land
1000+livestock evacuated
Roads cut off
Closed railways
Estimated 10 million pounds of damage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What were the environmental impact

A

Contaminated river water
Debris deposited across land
Stagnant water has to be deoxygenated then pumped back into rivers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What management strategies were put in place

A

Straightening and rising of river banks
Somerset county council 20 million action plan
Rivers tone and parrat dredged in march 2014
Roads raised
Flood defences for at risk communities
Pumping stations built
Plans for tidal barrage at bridge water ok track for 2024

How well did you know this?
1
Not at all
2
3
4
5
Perfectly