SOC Batter Board Flashcards

1
Q
  1. What are the four layers of construction?
A

Site/building, foundation, substructure, superstructure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. What are the squaring Method?
A

1) Carpenters square (least Accurate)
2) Diagonal Method (Most Accurate)
3) 3-4-5 method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. What are the building site considerations?
A
Drainage
Slope
Soil
Tactical emplacement
Commander's desire
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. How far off the batter boards need to be from the temporary stakes?
A

4 to 6 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. What is the least reliable squaring method?
A

Carpenter square

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. What is the calculating formula of Diagonal method?
A

A2+B2=C2 Pythagorean theorem

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. What are batter boards?
A

Temporary framework used to assist to in locating corners when laying out a foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. What is steps of employing Batter Board?
A

a) Marking temporary corners
b) Place batter board 4-6 feet behind stakes
c) Level batter boards
d) String line (NS then EW)
e) Square string line
f) Plumb bob permanent corners

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What should a foundation be?

A

Square and level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What tools are needed for batter boards?

A
Line level
100’ tape measures
Nylon cord
Carpenters square
Levels (torpedo, 4’-8’)
Laser level(if available)
Black markers
Sledge hammers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly