SOC Batter Board Flashcards
1
Q
- What are the four layers of construction?
A
Site/building, foundation, substructure, superstructure
2
Q
- What are the squaring Method?
A
1) Carpenters square (least Accurate)
2) Diagonal Method (Most Accurate)
3) 3-4-5 method
3
Q
- What are the building site considerations?
A
Drainage, slope, soil, tactical emplacement and commander’s desire
4
Q
- How far off the batter boards need to be from the temporary stakes?
A
4 to 6 feet
5
Q
- What is the least reliable squaring method?
A
Carpenter square
6
Q
- What is the calculating formula of Diagonal method?
A
A2+B2=C2 Pythagorean theorem
7
Q
- What is batter boards?
A
Temporary framework used to assist to in locating corners when laying out a foundation
8
Q
- What is steps of employing Batter Board?
A
a) Marking temporary point
b) Place batter board
c) Level
d) String line
e) Adjust string line & Plumb bob