Slide 7 Flashcards
_____ is an integral part of engineering and system execution
Interface Managment
Which kind of projects rank interfaces as most important for project execution?
EPC Projects
Name 4 things that interfaces must include/have
Scheduling
Installation & Operations
Management of Change
High level of involvment
Name 5 objectives of Interface management
- Identify technical, execution, and organization interfaces
- Create clear understanding of roles
- Define, implement, monitor, document, interfaces and the closeout of those interfaces
- Ensure timely execution within project constraints
- Resolve Problems
Work elements of an interface include using a structured process as the initial step and documenting expectations from different groups. Name three others
- Ensure agreement between parties
- Create interface for info transmission
- identify critical interfaces and minimize impact of concerned parties
Between the prime contractor and subcontractor is what kind of interface?
Internal
Between the Prime contractor and project team is what kind of interface?
Internal
Between two prime contractors is what kind of interface?
External
Between the project team is what kind of interface?
Internal
Between the coventurer, regulartory bodies, media, what kind of interface?
External
Between prime contractors, regulatory bodies, and host communities, what kind of interface?
External
What is an Interface Register?
A way to document and track things which include a reference number, description of the expected/required deliverable, date info is needed, delivery date, a ‘closeout’ date, and status
What is the first step in creating interfaces?
Identify the what and when, then agree with other parties
What occurs to the schedule if interfaces are not properly meshed/married
Schedule will lead to unrealistic delivery and costly rework
Although the overall project schedule will be interactive, when do you have to freeze it and why? What else must be frozen?
Schedule and Preliminary design must be frozen. You have to freeze the schedule as early as possible to avoid completion slippage. Once schedules & prelim designs are frozen, a management of change procedure is activated