Slide 4 Flashcards

1
Q

What happens to outcomes and opportunities as the project progresses

A

Before we start a project, we have ample oppurtunities, but as the project progresses, criteria becomes more strict and we decrease our range of outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Net Present Value. What is it good in measuring?

A

Sum of all the expenses (Costs and Inflow) either discounted or non-discounted. It is good to measure the value or scale of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define Profit Investment Ratio

A

Net present value divided by capital investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Economic hurdles for PIR0 and PIR9

A

PIR0>1.00

PIR9>0.30

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Internal Rate of Return

A

The discount rate at which the NPV=0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What economic indicators does PEEP give out?

A

PIR, NPV, IRR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you decide which projects to green light?

A

It all depends on the budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In the Dawson Creek, how were the projects ranked?

A

Based on Suplpy Cost, IRR, and PIR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is DBM

A

Design Based Memorandum

Conceptual design is the preparatory stage of the whole design process. At these stage some rough sketch, drawings like paintings are presented to give a general view of the project. There are also rough estimates regarding cost of the project. The costs are usually arrive using benchmark, meaning, how much it cost when it was done in this and that countries.

Design Basis Memoranda are issued to guide the desing consultant on their activities. These are important document for designer since any deviation from the memoranda is a variation to their scope of work. For example, the client require the designer for 35 story building, after halway to the work, the client decided to change from 35 storey to 50 storey. So the new instruction from the client is a deviation from the design memoranda.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In modern times, is it often cheaper to hire an in-house team or contract out for non permanent projects?

A

Cheaper to higher outside because the project may not be permanent project. If the project is permanent, would be better to higher in house

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which should have a higher IRR %, Exploration or Exploitation?

A

15% for Exploration

20% for Explotation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

NPV can be compared between projects of different sizes (T or F)

A

False, NPV should not be compared to projects of different scopes or sizes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

NPV0=0$ means what for IRR?

A

A breakeven analysis where IRR=0%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are supply costs for oil and gas usually measured in (at least in his slides)

A

$ US / MMBTU

US dollars per million British Thermal Units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly