Slide 4 Flashcards
What happens to outcomes and opportunities as the project progresses
Before we start a project, we have ample oppurtunities, but as the project progresses, criteria becomes more strict and we decrease our range of outcomes
Define Net Present Value. What is it good in measuring?
Sum of all the expenses (Costs and Inflow) either discounted or non-discounted. It is good to measure the value or scale of a project
Define Profit Investment Ratio
Net present value divided by capital investment
Economic hurdles for PIR0 and PIR9
PIR0>1.00
PIR9>0.30
Internal Rate of Return
The discount rate at which the NPV=0
What economic indicators does PEEP give out?
PIR, NPV, IRR
How do you decide which projects to green light?
It all depends on the budget
In the Dawson Creek, how were the projects ranked?
Based on Suplpy Cost, IRR, and PIR
What is DBM
Design Based Memorandum
Conceptual design is the preparatory stage of the whole design process. At these stage some rough sketch, drawings like paintings are presented to give a general view of the project. There are also rough estimates regarding cost of the project. The costs are usually arrive using benchmark, meaning, how much it cost when it was done in this and that countries.
Design Basis Memoranda are issued to guide the desing consultant on their activities. These are important document for designer since any deviation from the memoranda is a variation to their scope of work. For example, the client require the designer for 35 story building, after halway to the work, the client decided to change from 35 storey to 50 storey. So the new instruction from the client is a deviation from the design memoranda.
In modern times, is it often cheaper to hire an in-house team or contract out for non permanent projects?
Cheaper to higher outside because the project may not be permanent project. If the project is permanent, would be better to higher in house
Which should have a higher IRR %, Exploration or Exploitation?
15% for Exploration
20% for Explotation
NPV can be compared between projects of different sizes (T or F)
False, NPV should not be compared to projects of different scopes or sizes
NPV0=0$ means what for IRR?
A breakeven analysis where IRR=0%
What are supply costs for oil and gas usually measured in (at least in his slides)
$ US / MMBTU
US dollars per million British Thermal Units