Slide 4- Bakersfield Bulk Plant Operations Flashcards
What PSI Does Halliburton’s Pneumatic Bulk Plant Operate On
20 PSI
What Day to Day General Maintenance Tasks Need To Be Done
- Check 5” Air Actuated Valves for Damage
- Check the Oil Level In All Four Compresors Plus The Blower
- Bleed Off Air and Check High and Low Pressure Lines For Condensation
- Check all shipping lines and hoses for leaks
How Many Storage Silos Does Bakersfield Have
13
What Is The Total Cubic Footage For Our Storage Silos
2560 Cubic Feet
How Many Holding Silos Does The Bulk Plant Have
3
What is The Total Cubic Footage for Our Holding Silos
1500 Cubic Feet
How Many Blend Tanks Does Bakersfield Have and What is The Cubic Footage
2 Blend Tanks At 410 Cubic Feet
How Many Scale Tanks and What Is The Cubic Footage
1 Scale Tank At 410 Cubic Feet
What Size Are The Shipping Lines and Hoses
5”
How Many Compressors Does The Bulk Plant Use For Shipping
Three High Volume/Low Pressure Compressors are Used to Ship Material At 20 PSI
How Many Compressors Does The Bulk Plant Use For 5” Air Actuated Flapper Valves
One High Pressure/Low Volume Compressor
What Does The Bulk Plant Blower Do
It Pushes Silo Material Through Shipping Lines While High Volume/Low Pressure Compressor Pulls The Material
What Cement Material Do We Have In Silos
SSA-1 (Silos 8&9), Pozmix (Silo 10), MPC (Silo 5, 7) Junk Tank (Silo 6), Type 3 (Tank 3), Spherelite (Tank 4) Barite (Tank 1)
Can Various Material Be Put In These Silos
No! Each Silo Is Permited For A Specific Material
What Is The Bulk Plant Computer System Called
PLC
How Many Times Do We Transfer Blends Through The Scale and Blend Tanks
4 Total Transfers Before Shipping To Bulk Truck
How Large Should One Batch Blend Be
No larger than one transport tank load
What is Halliburton’s Accuracy Standard for Cement and Additive Measurments
Accuracy of .1% of the gross capacity of the scale (25lbs for 25,000lb scale or 200lb for 200,000lb scale)
What is HMS procedure for “Sandwiching” Additives with Cement
HMS requires the 1/3, 1/2, 1/3, 1/2, 1/3 method. Add 1/3 of required cement for the batch, then 1/2 of the additives, then 1/3 of cement, then 1/2 of additives, followed by 1/3 cement.
When Should Samples Be Pulled for Lab
After the 4 pneumatic transfer. Bakersfield uses automatic in-line sampler operated throughout the complete transfer (total sample size should be around one gallon)
What Type of Pneumatic Cement Bulk Plant Does Bakersfield Have
Vacuum- Pneumatic Plant with one scale tank, two blend tanks and blend material holding tanks