Name some examples of relevant standards you use at work.

A

-Design Manual for Roads & Bridges (DMRB)
-Maintenance Design Manual (MDM)
-Traffic Signs Manual (Chapters 5 & 6)
-Guidance on the Use of Tactile Paving Surfaces (DFT)
-Safety at Street Works and Road Works (A Code of Practice)
- Highways Works Standards, Materials & Testing (A Code of Practice)
-Local Transport Notes (LTN)
-Specification for Highways Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is the fee on PV greater than your hourly rate?

A

The fee comprises of actual salary, in addition to provisions for training, equipment, technology etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What performance indicators are we appraised on?

A

Cost & Time mainly, for example actual spend as a percentage of the schemes budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a compensation event?

A

An event, not usually the fault of the contractor, that changes the cost of the time needed to complete the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of the surface course?

A
  • Skid Resistance
  • Prevent Ingress of Water
  • Resist deformation from traffic loading
  • Provide an even running surface
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the function of the binder course?

A
  • Distributes the load and stresses from the surface into the base course
  • Provides some strength
  • Provides a regulating course
  • Provide an even surface for the construction of the surface course
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the function of the base course?

A
  • Provides majority of the strength
  • Provides a platform for the construction of the binder and surface course layers
  • Protects the sub-base from frost/water damage
  • Deal with stresses associated with construction traffic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the function of the sub-base course?

A

-Protects the sub-grade from water/frost
-Spreads the load across the sub-grade
-Provides a platform for the construction of the bound layers
- Deal with stresses associated with construction traffic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the function of the sub-grade?

A

-Provide a platform for the construction of the sub-base
– Deal with stresses associated with construction traffic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describe your role under CDM and the role of TSP

A

TSP act as the principle designer. Dave acts as a representative of the principle designers and I act as a designer who prepares documents for Dave to sign off as the principle designers representative.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How does TSP act as a trading account?

A

TSP does not get given a budget for staff. Instead, TSP charges the council a flat rate for each grade based upon the hourly rate of the position and a number of overheads. The overheads include things such as training, provision of equipment etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where does the funding for schemes come from?

A

Funding streams are either capital or revenue. Capital schemes are provided a budget by central government (i.e. LCC) which is controlled by the client team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What considerations are there for typical designs?

A

Location (rural/urban)
Businesses
Utilities
Traffic management

etc..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is PEESL? (Risks)

A

All risks for a job can fit within one category based on this acronym.

e.g. Political, Economic, Environmental, Social & Legal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly