Permitting / TTROs Flashcards
If a Section 58 is required, how much notice must be given?
A minimum of 4 months is required
How much notice is required to raise a TTRO?
How much notice is required to raise a road closure order?
Minimum 13 weeks lead in for TTRO
Minimum 16 weeks lead in for road closure
What is the absolute minimum departure made by the traffic orders team when raising a TTRO or Road Closure?
10 weeks lead in
What is the maximum duration you can raise a TTRO for?
18 months
To ensure road space is booked and permitted, what needs to be done? (4)
Confirm job for permit
Permit application made to permitting officer
Road space booked with permitting officer
TTROs raised
How is a permit raised for non term contract works?
Confirm job raised in Confirm
Permit application raised 3 months ahead of project start
How are dates amended for permits? When can dates not be amended?
Street works and permitting team (SW&P) are to be notified immediately. So long as the permit is active, it can be extended with their approval.
Permits cannot be amended when the dates have expired already.
Under the TMA 2004, within what time period is ‘excessive noise hours’?
23:00-07:00
Can dates for a road closure be brought forward when adverts have been placed?
No
How do you know when a road requires closing for works?
Refer to road closures widths document on QMS