What is a NRSWA major works enquiry?
Works of any description which consists of the carriageway being altered in some way. I.e widening, reconstruction, level alteration etc.
What is a C2 NRSWA?
A preliminary enquiry which provides detailed utility plans for an area requested
What intervals do you need to provide coordinates for on a C2 request?
60m
If apparatus is to be affected by a design, what must be done next?
A draft budget estimate is requested (C3 scheme enquiry) involving negotiation with statutory undertakers
If the design is not amended, and a utility diversion is to go ahead, what must happen next?
A final detailed estimate (C4 final enquiry) is logged and negotiations with SU carry on
What is a C5? What must be provided with it
A C5 is an advanced order for a utility amendment and must be placed with a covering letter before diversionary works are undertaken