Section 5 - Inspection Examination And Testing Practices Flashcards
Our in-service pressure vessel’s in the Petrochemical industry must:
A. Have been Hydro tested prior to service.
B. Be built to ASME section VIII
C. Be post weld heat treated if the thickness is over 1-1/2”.
D. Have an inspection plan.
D. Have an inspection plan.
All in-service pressure relief devices in the petrochemical industry must:
A. Have an inspection plan.
B. Be built to a ASME section VI
C. Be set at a pressure not higher than 100% MAWP.
D. Have a balance Bellows
D. Have a balance Bellows
The inspection plan for a pressure vessel should be developed by:
Either the inspector or the engineer.
The inspection plan for a pressure relief device should be developed by:
Either the inspector or the engineer.
When developing a vessels inspection plan, who should help, we needed, to identify specific damage mechanisms and their locations?
Corrosion specialist.
A significant factor in developing an inspection plan is to determine the:
A. Anticipated cost.
B. Anticipated schedule.
C. Availability of NDE examiners.
D. Potential damage mechanisms.
D. Potential damage mechanisms.
What is the MOST important factor when selecting the NDE to use in a future inspection?
A. Ability of the method to find the anticipated damage mechanism
B. Ability of NDE method
C. Cost of NDE method
D. Ease of use of the NDE method
A. Ability of the method to find the anticipated damage mechanism
Which of the following is not a factor in determining the interval for examinations in a vessels inspection plan?
A. Cost of equipment outage
B. IOW exceedances
C. Maximan code intervals
D. Probability that the NDE will find expected damage
E. Rate of damage occurring
A. Cost of equipment outage
Which of the following is an NOT required to be included in a vessels inspection plan?
A. Name of individual that will perform the inspection
B. Next inspection date
C. Surface cleaning requirements
D. Type of and NDE that will be used
A. Name of individual that will perform the inspection
Which of the following is not required in a vessels inspection plan?
A. Lightning requirements
Capital B. Location where NDE will be performed
C. Planned pressure test
D. Planned repairs
A. Lightning requirements
What “Optional Items” should really be part of a vessel’s Inspection plan ?
A. confine entry requirements
B. Special access requirements
C. Special lighting requirements
D. Types of damage expected in the vessel
D. Types of damage expected in the vessel
In the RBI process, what are the two primary factors used to determine risk?
A. Consequence of failure and service class
B. Reliability and the On-stream percentage
C. Probability and consequence of failure
D. Inspection Effectiveness and Corrosion Mechanism
C. Probability and consequence of failure
Who is responsible to decide an RBI assessment will be used to determine inspection intervals for a pressure vessel?
A. Corrosion Specialist
B. Inspector
C. Owner/User
D. Pressure Equipment Engineer
C. Owner/User
RBI assessments should be done in accordance with ?
A. API 579
B. API 580
C. API 583
D. API 584
B. API 580
Which of the following is NOT a significant factor in an RBI assessment of a pressure vessel?
A. Vessel construction code
B. Process fluid
C. Potential degradation mechanisms
D. Effectiveness of past inspections
A. Vessel construction code
During a risk assessment, which of the following is NOT a significant factor in the Probability of failure?
A. Amount of process fluid
B. Expected damage mechanisms
C. Quality of the inspection program
D. Quality of the maintenance program
A. Amount of process fluid
During an RBI assessment of a pressure vessel, what are the two biggest factors of consequence of failure?
A. Amount of product and expected corrosion rate .
B. Amount of product and type of product
C. Expected corrosion rate and type of product
D. Quality of inspection program and Quality of maintenance program
B. Amount of product and type of product
During a RBI assessment, which of the following is NOT a significant factor in the consequence of failure?
A. Environmental damage
B. Equipment damage
C. Equipment downtime
D. Health impacts
E. Public image
E. Public image
All RBI assessments must be .
A. Thoroughly documented
B. Repeated every 5 years
C. Approved only by the authorized inspection
D. Conducted per guidelines in API 579
A. Thoroughly documented
An RBI assessment is used to determine the interval for the internal inspection.
When does the RBI assessment NOT have to be repeated?
A. After each internal inspection
B . After any significant process change
C. After any significant change in inspection personnel
D. After any significant hardware change
E. At least once every 10 years
C. After any significant change in inspection personnel
All NDE equipment used in petrochemical facilities must .
A. Have a safety rating appreciate for the gaseous environment at the exam site .
B. Be calibrated daily
C. Be used by a technician that is qualified to ASNT SNT- TC-1A
D. Have an ASME section V approval seal
A. Have a safety rating appreciate for the gaseous environment at the exam site .
Which of the following is NOT a requirement prior to performing an internal vessel inspection?
A. Review previous vessel history
B. Obtain permission from the appropriate operation personnel
C. Check that all equipment used during the inspection is safe to use
D. Be certified as an ASNT SNT-TC-1A Level 2 in VT
D. Be certified as an ASNT SNT-TC-1A Level 2 in VT
Prior to performing an inspection the inspector should ?
A. Calibrate their pit gauge
B. Familiarize themselves with prior history
C. Review API 571 for expected damage mechanisms.
D. Retake an eye test
B. Familiarize themselves with prior history
Prior to performing an inspection, which of the following is NOT a requirement for the inspector?
A. Familiarize themselves with the current inspection plan
B. Familiarize themselves with past inspection plans
C. Familiarize themselves with prior inspection history
D. Familiarize themselves with prior repairs
B. Familiarize themselves with past inspection plans
Which of the following damage mechanisms creates either general or localized corrosion?
A. Graphitization
B. HTHA
C. Naphthenic
D. Temperature embrittlement
C. Naphthenic
Which of the following damage mechanisms does NOT create either general or localized corrosion?
A. Fatigue
B. Galvanic
C. MIC
D. Sulfidation
A. Fatigue
Which of the following damage mechanisms does NOT create surface connected cracks ?
A. Chloride stress corrosion cracking
B. Hydrogen included cracking
C. Polythionic stress corrosion cracking
D. Thermal fatigue
B. Hydrogen included cracking
Which damage mechanism creates sub-surface cracking ?
A. Carbon dioxide corrosion
B. Caustic stress corrosion cracking
C. Mechanical fatigue
D. Wet hydrogen sulfide cracking
D. Wet hydrogen sulfide cracking
Which damage mechanism creates micro-fissuring which leads to macro-cracking ?
A. Creep
B. Graphitization
C. Hydrogen blistering
D. Naphthenic acid
A. Creep
The inspector should be ?
A. Familiar with process conditions.
B. Familiar with construction details
C. Familiar with potential damage mechanisms
D. With all the above
D. With all the above
Vessels in cyclic service should be inspected for ?
A. Creep
B. Excessive strain
C . Fatigue
D. Stress corrosion cracking
C . Fatigue
Where is a great place to check for damage on vessels that are subject to fatigue damage?
A. Nozzle-to- flange welds
B. Circumferential welds
C. Places of stress intensification
D. Shell-to-head welds
C. Places of stress intensification
Which of the following vessels is most likely to be affected by thermal fatigue?
A. Coke drum
B. Distillation column
C. Knockout drum
D. Overhead accumulator
A. Coke drum
Deviations from an inspection plan should be approved by the
Engineer or inspector
Who is responsible for performing the internal inspection on a pressure vessel?
Authorize Inspector
An NDE examiner can ?
A. Always assist in the internal inspection
B. Perform the internal inspection
C. Assist In the internal inspection when approved by the engineer.
D. Assist In The internal inspection when approved by the inspector
D. Assist In The internal inspection when approved by the inspector
When may inspections from ports be substituted for the internal inspection?
A. Always
B. Never
C. Only if the inspector approves
D. Only if the vessel is too small to enter
E. Only if the vessel is too small to enter or all internal surfaces of vessel can be clearly seen from the port
E. Only if the vessel is too small to enter or all internal surfaces of vessel can be clearly seen from the port
Prior to the internal inspection?
A. All removable internals must be removed
B. All process deposits must be removed
C. All removed internals and all process deposits must be removed.
D. Some removable internals may not need to be removed, but all process deposits must be removed
E. Some process deposits may not need to be removed, but all removable internals must be removed
F. Some removable internals and some process deposits may not need to be removed
F. Some removable internals and some process deposits may not need to be removed
Who is responsible to determine wether process deposits should be removed prior to the internal inspection?
Authorized inspector and corrosion specialist
Which of the following describes the needed surface preparation before performing an internal inspection?
The amount to clean and the degree of cleanliness is based on expected type of degradation mechanisms
Which of the following is true about the need to remove process deposits prior to internal inspections?
A. All deposits must always be removed
B. Amount to remove is based on the vessel classification
C. Amount to remove is based on the consequence of failure
D. Amount to remove is based on whether deposits actually protect the shell or cause corrosion.
D. Amount to remove is based on whether deposits actually protect the shell or cause corrosion.
Internal inspection is conducted on a refractory -line vessel. How much refractory should be removed to check the condition of the vessels internal surface ?
Removal of refractory is not required unless there is a reason to suspect that corrosion is according under the refractory
Who is responsible to perform a vessel o -stream inspection?
Authorized inspector or an examiner
All on-stream work performed by an examiner must be approved by the ?
Authorized inspector