Which of the following activities is NOT included in the scope of API 510.
A. Rerating a vessel
B. Operating a vessel
C. Replacing a vessel head
D. Internally inspecting a vessel
B. Operating a vessel
Which of the following activities is not included in the scope of API 510.
A. Setting relief device intervals
B. Performing vessel alterations
C. Performing vessel fabrication
D. Performing vessel maintenance
C. Performing vessel fabrication
Which of the following equipment types is not covered by Api 510.
A. heat exchanger
B. Safety relief valve
C. Distillation column
D. Process heater (Furnace)
D. Process heater (furnace)
API 510 can be used?
By petro-chemical facilities and any other industry
API 510 takes affect.
Once the vessel is placed in service.
APR 510 covers vessels constructed to which fabrication code?
Any fabrication code.
When does APR 510 stop applying to vessels?
Retired and abandon
During repairs and alteration most of the code requirements come from.
ASME Section VIII Or the construction code.
During a vessel repair, if there is a conflict between the requirements of API 510 in the construction code which should be followed?
API 510
During a vessel alteration, if there is a conflict between the requirements of API 510 in the construction code which should be followed?
API 510
Companies that use API 510 must.
Either employer or have access to an authorized inspection agency
Which of the following individuals must be directly employed by the owner?
A. Authorize inspector
B. Examiner
C. Pressure vessel engineer
D. Repair organization
E. No one all can be contracted personnel
E. No one all can be contracted personnel
Who is responsible for responding to inspection results that require corrective of action?
Owner/user
An in-service vessel is being repaired or Altered if there’s a conflict between the requirements of API 510 and the Legal Jurisdiction, which should be followed?
A. API 510
B. The legal Jurisdiction
C. The one with the most stringent requirements
D. Either set of the requirements based on engineer in AI approval
C. The one with the most stringent requirements
An in-service vessel is being inspected. If there is a conflict between API 510 in the legal jurisdiction, which should be followed?
A. API 510
B. The legal Jurisdiction
C. The one with the most stringent requirements
D. Either set of the requirements based on engineer in AI approval
C. The one with the most stringent requirements