Section 4 - Owner/user Inspections Organization Flashcards

1
Q

Who is responsible to ensure that all of API 510 requirements are met?

A

Owner/user

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is responsible to ensure that the authorize inspection agency functions in accordance with the requirements or API 510?

A

Owner/user

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Each owner/users that uses API 510 must?

A. Maintain a quality assurance inspection/repair management system.

B. Employee (direct-hire)At least one pressure equipment engineer.

C. Maintain an “R” stamp for vessel repairs.

D. Employ (direct-hire)at least one qualified welder who can make repairs to pressure vessels.

A

A. Maintain a quality assurance inspection/repair management system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which of the following is NOT required to be in the owner/user quality assurance inspection/repair management system?

A. Training requirements for inspection personnel

B. Calibration of NDE equipment

C. Directions on how to document inspection results

D. Specific approval process for calculations performed during vessel rerating

E. Ensure all inspectors attend MSTS classes

A

E. Ensure all inspectors attend MSTS classes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Inspectors shall have an Eye test every?

A

12 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the name of the inspector is mandatory Eye test?

A

Jaeger - with J-1 letters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who is responsible for implementing in effective management of change process?

A

Owner/user

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

a MOC system should be used to review in control changes made to

A

Either the process or the hardware

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who needs to be involved in the approval process for MOCs that affect pressure vessel integrity?

A

Inspection group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who is responsible for implementing an effective program for Establishing integrity operating windows (IOWs)?

A

Owner/user

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who should be made aware of deviations outside the (IOWs)

A

Inspection/engineer in personnel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When repairs and alterations are being conducted, which individual or organization is responsible for quality control?

A

Repair organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When repairs and alterations are being conducted, which individual or organization is responsible for validating that the materials meet the requirements of API 510?

A

Repair organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the following is NOT a role for the API 510 inspector?

A. Provide the owner assurance that the all rerates meet requirements

B. Provide the owner assurance that all NDE examinations meet requirements

C. Provide the owner assurance that all welding meet requirements

D. Provide the owner assurance that all pressure testing meet requirements

A

A. Provide the owner assurance that the all rerates meet requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

During a vessel repairs, all examinations results must be excepted by?

A

Authorized inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following is a roll for the API 510 inspector?

A. Provide solutions when welding problems occur

B. Train on-site NDE personnel

C. Authorize substitution of pre-heat in Lieu of PWHT during vessel repairs

D. Evaluate and except NDE results

A

D. Evaluate and except NDE results

17
Q

Who is responsible to maintain certification records for NDE examiners?

A

Examiner’s employer

18
Q

Operations should inform inspectors or engineers when which of the following occurs?

A. Decontamination procedures Planned for upcoming outage

B. Operation temperature exceeded the (IOW)

C. Nozzle leak has occurred

D. Significant change in feedstock

E. Unusual noises are occurring in the vessel

F. All of the above

A

F. All of the above

19
Q

Each owner/users organization should be audited

A

Periodically

20
Q

When an audit of the owner/user organization is being conducted, the team members should be.

A. Accredited by the NAAA (North America auditors association).

B. Members of the owner/users pressure equipment group.

C. Third-party auditors or employed at in other owner/user site.

D. Individuals that have an active API 510 certificate.

A

C. Third-party auditors or employed at in other owner/user site.

21
Q

The owner/users should:

A. Establish a tracking mechanism for non-conformance found by the audit team.

B. Correct all non-conformance found by the audit team within one year.

C. Correct all non-conformance since found by the audit team that the owner/user agrees with.

D. Shut down affected unit until all non-conformances are corrected.

A

A. Establish a tracking mechanism for non-conformance found by the audit team.