Section 4 Flashcards
Define Construction Manager
An individual or company employees to oversee the construction of a project, usually the whole of the construction elements and the parties who are to perform the,; a company that contracts with an owner to perform such services for a fee.
Define “Design-Build”
Method of project delivery where an entity or alliance (design-builder) contract with the owner to provide both professional design services (can be architecturally or engineering) AND the construction
Define “Program” with the context of Project Management
a group of related projects managed and coordinated in a way to benefit them in way unavailable if manage individually
Define “Transmission Loss”
Used in the context of sound transmission, is equal to the reduction in sound intensity as sound passes through a material. Average TL is a rating of performance in preventing transmission of airborne sound.
Define “Project”
A temporary endeavour undertaken to create a unique result. The design of a building is a project. The construction of a building is another project.
Define “Project Manager”
A person responsible for a projects scope, schedule, cost and quality. Many may be involved but typically within a practice the person charged with managing the project for its respective company, may be called a project manager.
Define “Addendum”
A change to the Bid Package, in the form of drawing or specification change. Issued during bud period and before execution of the contract.
Define “Base Bid”
The base value without any adjustment because of alternatives or substitutions that the BIDDER offers to perform the work within the BID Documents.
Define “Bid or Tender”
A bid is an offer to a formal ball for bids, it contains a price or estimate in response to the call. The offer forms a BID CONTRACT until the acceptance period is over.
Define “Bond”
A financial security for the performance of an obligation. Typically a written document with the support of collateral
Define “guarantee”
A promise to answer for payment of a debt or performance of an obligation if the person liable in the first instance failed to make payment or perform obligation.
Define “Pre-Purchasing”
Purchase of materials prior to the award of the prime contract.
Define “Pre-Selecting”
The owner pre-qualify and selecting a manufacturer or supplier before contract award.
Define “Pre-Tendering”
A procedure for calling tenders buy the owner prior to the prime contract tender call. A contactor can be instructed to include the amount of the pre-tender in their own tender.
Define “Surety”
The Party (Surety Company) that issues a bond which guarantees the performance of the person bonded.
Define “Warranty”
A statement of quality intended to be relied upon by another party, carrying with it a promise to remedy upon breach.
List some example why there are different types of contrsuctino/owner contracts?
Over time, owners have increase requirements, increase project risk, more urgent time frames, increase building performance, economic pressures
Describe “Project Delivery”
A General term to describe the method of designing and construction a building.
What is the best method of project delivery?
There is no one-size fits all, different methods have different advantages and disadvantages.
What type of contract is CCDC 2?
Design-Bid-Build, Stipulated Price Contract
What are the 5 types of CCDC Contracts
Design-Bid-Build, Construction Management, Design-Build, Public-Private-Partnership, Integrated Project Delivery
What type of contract is CCDC 3?
Design-Bid-Build, Cost Plus Contract
What type of contract is CCDC 4?
Design-Bid-Build, Unit Price Contract
What type of contract is CCDC 5A?
Construction Management Contract for SERVICES
What type of contract is CCDC 5B?
Construction Management Contract For Services and Work
What type of contract is CCDC 14?
Design-Build Stipulated Price Contract
What type of contract is CCDC 15?
Design-Build - Buiilding/Consultant Contract (Subcontract)
What type of contract is CCDC 30?
Integrated Project Delivery?
What is the Standard Form of Contract of Public-Private Partnerships.
No standard form of contract.
Describe the owner-COnstructor Relationship in a Construction Management Project Delivery Method?
Owner engages architect to provide design, Architect and Engineers prepare CD. Owner engages Construction Manager as a consultant, providing input on construcitbiliy, cost estimating, scheduling, sequential bidding, and coordination of contract negotiations and award. Purchase of critical materials, cost control, and coordination of construction activities.
At what stage on construction managment delivery is the cost accurately projected?
As the project progresses, accuracy of pricing will be increased, with a high level of accuracy the road of the construction manager CAN transition into General Contractor, with this risk is transferred from owner to GC (CM).
Describe Owner-Architect relationship in Design-Bid-Build Project Delivery?
Owner engages architect for design, architect and consultants prepare CD. CD is issued for competitive bids. Contract is awarded to winning bidder. Architect Administers specific aspects of the construction contract.
Describe the Owner-Architect Relationship in Design-Build Contracts
Owner enters into contract with a single design/Construction entity. This entity is responsible for the design, AND construction. Design Services can be performed in-house or contracted out to an external architect.
Describe Integrated Project Delivery
A single purpose entity that involves all parties in the design-construction program. Owner, Design Team, Contractor, and Subtrades enter into a multi-party contract. Shared Risk, and profit is distributed based on the divided risk pool.
What is the most common method of project delivery that architects are involved with?
Stipulated Price Contract, Design-Bid-Build. Architect has more responsibility when it comes to fulfilling the terms of the contract.
In what circumstances should a CCDC 2 contract be used?
When the circumstances surrounding price are known, and construction costs have a high level of certainty
How is the contractor selected in CCDC 2
The contractor is selected by Winning the Contract following there Bid Submission after being invited to bid, or submitting to an open bid.
Describe what stipulated price means?
A fixed price for completing construction.
Who may be considered a design-builder?
Anyone who contracts with an owner to perform design and construction services. This can be a contractor, an architect, a broker, or a joint venture between contractor and architect.
When would you use CCDC 15?
When a design-builder contracts an architect to perform design services.
What is a risk with a Design-Build Contract?
Prices established before design is complete may be a source of conflict. There may be uncertainty what is included in the price.
Describe the difference between CCDC 2 and CCDC 3?
CCDC 2 has the largest risk and profit margin for the contractor. A contractor can mitigate risk by using a CCDC 3. CCDC 3 promises a fee to be paid to the contractor for the work ON TOP of the actual costs of work. This fee can be fixed or a percentage of costs.
What is an alternate method of Describing CCDC 3?
Time & Materials
What type of projects are best suited for a CCDC 3 Contract?
A Cost-Plus contract is best suited for small, complex projects, in which total costs are initially difficult to determine.
What is the simplest type of contract to execute?
CCDC 3 - Cost Plus, Reimbursement to contractor is the simplest.
Under what circumstances can the work performed under a CCDC 3 contract be ceased?
Work can cease when the construction costs equal the funds provided under the contract.
Under what Project delivery method is there a “Guaranteed Maximum Price Option?
CCDC 3 - Cost Plus contractor can be compensated for actual costs, plus a fee to AN AGREED UPON MAXIMUM PRICE. contractor bears all costs beyond the pre-determined maximum.
What type of Project is suitable for CCDC 4?
CCDC 4 - Unit Price Contracts have limited use scenarios, and are typically used in Canada for Civil Engineering Work.
What determines a contractors pay under CCDC 4?
A pre-determined price for each unit or quantity of work.
What determines the final contract price under CCDC 4?
CCDC 4 Unit Price, Final price is determined based on the final unit price and schedule of prices multiplied by the quantity of each item.
List 6 reasons why to use CCDC Documents?
Reliable, Standardized, Fairly Allocates Risk, Developed Collaborativley, Reduces Disputes, Legal Precedents, Updated Regularly
What is the General Contractors Responsibility in CCDC 2?
Fulfilling the requirements of the Construction Project. Hiring Trades and Subtrades. Provide price based on design drawing assessment.
What is the difference between A General Contractor and a Design-Builder?
A General Contractor is responsible for the construction of the project, A Design-Builder is responsible for both the construction and the design.
What trade contractors may be involved in fulfillment of the contract?
Mechanical, Plumbing, Electrical, masonry, Carpenter, Steel.
What is the architects responsibility in the bidding process?
assist client in pre-qualification of bidders, and assist in calling for bids.
What is a bid depository?
Facility operated by local construction association to collect and register bids from subcontractors and suppliers, and transmit these bids to GC’s
What method is used to award the contract to a contractor?
Letter of Acceptance from the client
Upon receipt of the letter of acceptance, what work can begin?
Contractor can begin immediately.
Do unsuccessful bidders need to be notified? If so, why may it be important?
Promptly, as contractors need to make arrangements with bonding companies, staff and subcontractors to bid on other projects.
When signing contracting, How many hard copies of the contract must there be?
Two Original contracts, one for client, one for contractor. Both sealed. An architect can retain a copy
Under what circumstances is a contract “executed”
Upon sign and seal on the covers of both documents, and the cover page of the drawings and specifications.
Within a standard CCDC Do the pages containing supplementary conditions need to be signed?
Sometimes every page of supplementary conditions should be initialed
Under which 3 methods can a contractor be selected?
Open Bids, Invited Bids, Direct Selection
What are the 7 steps of the tender process?
- Notify Bidders (public or invite) 2. Issue Bid Documents to Bidders 3. Conduct Bidder Conference, (Bidders ask questions, tour site 4. Respond to inquiries 5. Receive and Evaluate Proposals 6. Negotiate Outstanding Conditions to the Contract 7. Award the Construction Contract
What are the 7 PRIMARY components of a Bid Package?
- instruction to bidders 2. Contract Forms and Bond Requirements 3. Specifications 4. Site Information 5. Drawings 6. Construction Scheduling (Milestones) 7. Addenda
What documents are contained with Instruction to Bidders?
- Bid Form, 2. Bid Security Requirements 3. Agreement to Bond 4. Pre-Bid Information and meeting
What are the typical components of the Contract Forms and Bond requirements with a bid package?
General Conditions, Supplementary conditions including Insurance Requirements, Performance Bond, Labour and Materials Bond requirements, Cash Allowances, and Contingency Allowances.
When Selecting Contractors, what items should be obtained to understand qualifications?
Experience Statement, Financial Reference from Bank and Bond Company, Key Personnel, List of Major Construction Projects, List of Principal Projects in last 5 years.
True or False, information provide by the architect must be the same for all bidders?
True
Who selects the winning bid?
The architect can advise, but it is the clients decision.
When reviewing a bid, what should an architect look for?
Completeness, Bid Amount, Construction Start Date, Inclusion of ALL addenda, Subcontractors listed, Manufacturers listed, Unit Prices
Upon review of bid submissions what does the architect do?
Report in writing, findings and include and relevant comparisons in price and bid information.
What are the two methods an architect may describe a bid?
A bid is either compliant or non-compliant.
Describe what is a non-compliant bid?
Non Complaint bids can be informal, non responsive, Incomplete, Improperly Qualified, or conditional.
When is a bid considered non-compliant?
Does not meet requirements, Missing addenda, No bid Bond or security, Improperly signed, Bonding requirements not submitted (Consent of surety)
When recommending successful bidders, what is the architects responsibility?
Limit advice to to client, only indicating a bid IS OR IS NOT COMPLIANT. Amounts, and that there is no obvious reason a bid should be rejected.
What is the CCDC term for “Tender”?
Bid
Do you have to use a CCDC contract for project delivery?
Technically no but it is highly recommended as it is recognized as an industry standard. Certain clients may have there own Standard Form of Contracts.
Really simply, what is the Architects role in the execution of the Construction Contract?
To provide impartial treatment to the client and the construction manager, as the person tasked with interpreting the construction documents for both parties.