Section 4 Flashcards

Bidding + Contract Negotiations • Construction Phase-Office • Construction Phase-Site • Project Management

1
Q

What is a Stipulated Price Contract (Design-Bid-Build)?

A

Most building projects follow this traditional
method of project delivery (sometimes referred
to as “Design-Bid-Build”) in which:

  • The owner engages an architect to prepare the design, drawings, and specifications
  • The owner hires a contractor by competitive
    bidding to build the facility under a
    construction contract (usually CCDC 2,
    Stipulated Price Contract);
  • The architect administers the contract, and
    reviews and certifies the construction.

This design-bid-build form of project delivery
is characterized by:

its three distinct phases;
its two independent contracts between:
the architect and the client/owner;
the contractor and the client/owner; 
the linear sequencing of the process.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the advantages to a stipulated price contract?

A
  • Widespread use and familiarity;
  • Clear roles assigned to each party;
  • Generally a transparent process
  • Thorough resolution of the program requirements and design prior to construction;
  • Direct professional relationship between the client / building users and the architect; has a known price before construction begins
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the disadvantages to a stipulated price contract?

A
  • Separation of design and construction
    restricts useful communication;
  • Clients sometimes perceive “extras” to be
    more prevalent and costly in this form of project delivery than others (although every form of project delivery carries a construction contingency);
  • The contractor is unknown when the construction documents are prepared
  • Contracts, particularly for public sector projects, are awarded to the low bidder who may not be well-qualified to do the work. Prequalification of contractors on public sector bids is not common
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do typical responsibilities of a Construction Manager (CM) include?

A

Typical responsibilities of a CM include:

  • Assisting in preliminary planning relative to the design requirements for the project;
  • Advising on schedules, budgets, and costs of various alternative methods, on material selection and availability, and on detailing during the design phase;
  • Advising on and arranging for all services and all trade contractors and suppliers to carry out the various phases of the work;
  • Planning, scheduling, coordinating, and supervising the activities of all trade contractors;
  • Providing technical and clerical services in the administration of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Public Private Partnership? (P3)

A

P3s occur when the private sector works with
governments or other public agencies to bring
private sector capital and/or expertise to provide
and deliver public services. The scale of a P3
project usually is significant and may include
financing, design, construction, and very often
facilities management and operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the main difference between PROJECT MANAGEMENT and CONSTRUCTION MANAGEMENT?

A

The main difference between PROJECT
MANAGEMENT and CONSTRUCTION MANAGEMENT
is that the Project Manager has a contract with a client and in turn employs the architectural and engineering consultants to form his group, whereas under the Construction Management aspect the owner engages the architectural and engineering consultants, and at the same time or shortly afterwards, engages the services of a Construction Manager.

In this delivery method, the Project Manager (PM) is usually hired by an owner during the pre-design phase to manage the entire project and engage all the disciplines required, including the architect and the consulting engineers.

The typical project management project may
have the same three phases (Design-Bid-Build)
as traditional project delivery, or it may use
sequential tendering to achieve earlier
completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Just in Time project delivery method?

A

This approach combines aspects of fast tracking,
partnering, systems architecture, and strong incentives for repeat work. Large projects are broken into small work packages. Small teams of architects and contractors program, plan, demolish, and construct these areas on an hourly basis driven primarily by schedule, where time is the most critical factor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Turnkey Development?

A

Turnkey is generally described as a project delivery method that includes various real estate functions as well as design and construction. These functions may include site acquisition, entitlements, construction and/or long-term financing or other functions. This method may be carried out under Design-Build or developer proposal methods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Unit Rates project delivery?

A

Use of this method is limited primarily to heavy
civil engineering work — such as roads, and site preparation — where the contractor is paid for measured quantities at quoted unit rates. The method could be appropriate for the cost of repetitive units or identical buildings. The architect should ensure that unit rates are applied only to the design and documentation phases. The bidding and contract negotiations phase, as well as the contract administration phase, require full services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Lease-Back project delivery?

A

Under this method, the project is financed,
constructed, and owned by the builder, and
the building is “leased-back” to the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Cost-Plus project delivery?

A

In the cost plus method, the contractor is compensated for the actual costs of the work, plus a fee. The fee is based on:

  • an agreed-upon fixed sum; or
  • a percentage of the cost of the work.

Often called “time and materials,” this method
is appropriate for small, complicated projects in
which time is a factor or total costs are initially
difficult to determine. A variation of cost plus
is “cost plus to a maximum upset price” or guaranteed upset price. The cost plus method normally uses CCDC 3, Cost Plus Contract, but is now frequently replaced by the construction management delivery method, which includes many of the advantages and few of the
disadvantages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the most common type of fixed-price contract?

A

CCDC 2, Stipulated Price Contract:

The stipulated price is established through bidding — either open bidding or invitation of bids from pre-qualified bidders. The successful contractor is paid a fixed price for the completed construction. The fixed price or time for construction can only be adjusted by Change Orders.

The contractor is required to perform work called for in the contract, regardless of what it actually costs. Thus, the contractor must take great care when pricing such work, taking into account potential cost increases caused by inflation, material shortages, or difficulties in meeting performance requirements.

A stipulated price contract can produce maximum profit for the contractor, who also assumes maximum risk, including the risk of unexpected additional costs such as those that might result from inflation or material shortages. This type of contract should be used when the construction costs are reasonably predictable and
when full documentation is available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the features of a cost-plus contract?

A

A cost plus contract is one of the simplest types of cost-reimbursement contracts. It has the following features:

  • The owner reimburses the contractor for the allowable costs incurred in the course of construction;
  • Costs are paid regardless of the progress of the work and no matter how far the task is from completion;
  • Work may cease when the construction costs equal the funds provided for under the contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a Unit Price contract and how are contract prices determined?

A

Unit Price Contract (CCDC 4)

In a unit price contract, the contractor is paid a pre-determined price for each unit or quantity of work or material used in the project’s construction. The unit price can be derived through bidding or negotiation. The actual quantities involved are generally verified by
independent inspection, for example, by a clerk of the works or a quantity surveyor.

Unit prices form the basis for payment of the contract price. Quantities in the schedule of prices are estimated. The contract price is:

  • The final sum of the product of each unit price stated in the schedule of prices; multiplied by
  • The actual quantity of each item that is incorporated in or made necessary by the work; plus
  • Lump sums and allowances, if any, stated in
    the schedule of prices.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Construction Manager’s role?

A

A CM is an individual employed to oversee and direct the construction elements of a project, usually the whole of the construction elements, and the parties who are to perform them; a company which contracts with an owner to perform such services for a fee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Design-Build?

A

Methods of project delivery in which one business entity or alliance (Design-Builder) forges a single contract with the owner, and undertakes to provide both the professional design services (architectural/engineering) and the construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a Project Manager’s role?

A

A PM is the leader of the team of all necessary disciplines (design, construction, supply, etc.). The project manager provides all major essentials for the project. (The term “project manager” may be confused with construction manager; the meaning has become blurred and is currently often used merely for the individual within the conventional hierarchy.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Explain the purpose of the CCDC construction documents.

A

To form a standardized set of legal relationships (Agreement between Owner and Contractor; Definitions; and General Conditions) that are reviewed periodically by the CCDC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

In the construction industry, what is a bond?

A

A bond permits a contractor to provide an owner with a guarantee from a bonding company, known as a surety. The guarantee ensures that the contractor satisfactorily performs his/her obligations under a contract.

Bonds are a “useful means of ensuring responsible contract performance and financial security and, consequently, are often an essential requirement in construction procurement today” (CCDC 22, A Guide to
Construction Surety Bonds).

A bond is not an insurance policy but instead a three-party undertaking whereby the surety agrees to indemnify the owner against loss arising from the failure of the contractor to perform obligations under contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the three main types of bonds?

A
  • Bid bond;
  • Performance bond;
  • Labour and material payment bond.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are Open Competitive Bids (or Public Tender Call)?

A

In this type of tender call, the bidders are not usually “screened” or otherwise pre-qualified, and the capability of the contractor may be uncertain. The contractor may be selected on price alone. This type of tender call is frequently used when the project involves public funds.

A Notice of Tender is often prepared and is advertised on various websites or electronic tendering services, in daily newspapers and construction journals.

The Notice enables contractors to decide whether
or not they are interested in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are Invited Competitive Bids

(or Invited Tender Call)?

A

At the outset, pre-qualification helps to eliminate candidates who do not demonstrate that they have the necessary financial capacity, relevant experience, and human resources for the project at hand. Refer to CCDC 11, Contractor’s Qualification Statement.

Once pre-qualified, bidders should generally be considered to be equal in competence and the contract should then be awarded to the lowest bidder.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What types of projects are invited bids typically used for?

A
  • projects with private clients who prefer to select from a group of proven contractors;
  • specialized projects that require particular expertise;
  • small projects that might not attract the attention of contractors if they were advertised publicly.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Which types of construction contracts does Direct Selection and negotiation often lead to?

A
  • stipulated price (such as CCDC 2, Stipulated Price Contract);
  • cost plus, or cost to a guaranteed maximum price (such as CCDC 3, Cost Plus Contract);
  • construction management contracts.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is a bid bond?

A

The bid bond submitted by the contractor (bidder) guarantees that if the bid is accepted within the time period stated, the contractor will enter into a formal contract with the owner.

If the contractor fails to enter into a contract, the surety will guarantee — up to the amount of the bid bond — to pay the difference in money between the amount of the contractor’s bid and the amount for which the owner legally contracts with another contractor for the project.

Bid bonds are usually between 5% and 10% of the estimated construction cost; on very large projects, 2.5% is considered an appropriate amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which CCDC form is used if a bond bond is selected as the appropriate form of bid security?

A

CCDC Form 220, Bid Bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is a performance bond?

A

The function of a performance bond is to indemnify the owner up to the amount of the bond in the event of default (bankruptcy or insolvency) on the part of the contractor.

In the event of a contractor’s default, the performance bond will cover the costs of completing the contract as well as other costs for which the surety is liable, up to the total amount of the bond. Frequently, the amount of a performance bond is based on a percentage of the contract amount, such as 50% or 100% of the contract amount.

Bid bonds do not ensure that a surety will provide the necessary performance bond once the bid is accepted; therefore, it is prudent to request a separate undertaking signed by a surety company to issue a performance bond if the contractor is awarded the contract.

A performance bond will not cover payment of labour and material claims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is a labor and material payments bond?

A

A labour and material payment bond guarantees
that claimants (sub-contractors, sub-trades, and
suppliers who have direct contracts with the
contractor) will be paid for labour and materials provided to the contractor for use on the project identified in the bond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What CCDC form is used for performance bonds?

A

The use of CCDC Form 221, Performance Bond,
is recommended for performance bonds;
however, many sureties have their own type
of documentation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What CCDC form is used for labor and materials payment bond?

A

The use of CCDC Form 222, Labour and Material
Payment Bond, is recommended; however, many
sureties have their own type of documentation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

In preparing a bid package, what CCDC document should architects refer to?

A

CCDC 23, a Guide to Calling Bids and Awarding Construction Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

When would an architect prepare an addenda to the bid documents?

A

When those preparing bid documents (contractors, sub-trades, and manufacturers) identify omissions or contradictions in the project documents or items which need clarification or correction. The architect and engineers may also discover inconsistencies or omissions. Additional products which are approved as alternatives may have been identified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is an addendum?

A

A change to the bid package (usually a modification of the drawings and specifications) issued during the bid period and before execution of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What are the two possible solutions when the lowest of the formal bids is higher than construction cost estimates, and the client does not wish to revise the budget or abandon the project?

A
  1. If the difference is >15% of the construction cost estimate:

The Canadian Standard Form of Contract Between Client and Architect: RAIC Document Six states that architect, if requested by the client, will revise the construction documents and administer a new tender call, at no additional fee;

  1. If the difference is <15% of the latest approved cost estimate:

It is generally possible to propose alternatives and to negotiate an acceptable price with the lowest bidder.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What is included in a bid package?

A
  1. Bid information & requirements
  2. Contract forms & bond requirements
  3. Specifications
  4. Site information (legal, i.e. topo, survey, utilities)
  5. Drawings
  6. Construction scheduling restrictions & milestones (phasing & occupancy requirements)
  7. Addenda
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is a Design-Bid-Build project delivery method?

A

A Design-Bid-Build is when the Owner engages the architect to provide design services and prepare construction documents which are issued for competitive bids. General contractors submit bids for the project and the construction contract is awarded to the lowest bidder. The architect administers the construction contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What contracts are typically used in a Design Bid Build?

A

RAIC Doc 6 followed by CCDC 2 Stipulated Price Contract

CCDC 3 or CCDC 4 may also be used

38
Q

What is a Construction Management project delivery method?

A

A CM project delivery method is when the Owner engages the architect to provide design services and prepare construction documents. The Construction Manager works for the Owner as a consultant providing services that normally include design input on constructability, cost estimating, scheduling, bidding, coordination of contract negotiations and award, timing and purchase of critical materials, cost control and
coordination of construction activities

39
Q

What contracts are typically used in a Construction Management project delivery?

A

CCDC 5a - Construction Management Contract for Services

CCDC 5b - Construction Management Contract for Services and Work

40
Q

What is a Design Build project delivery method?

A

A Design Build is when the Owner contracts directly with a single entity that is responsible for both design and construction services for a construction project.

41
Q

What contracts are typically used in a Design Build project delivery method?

A

CCDC 14 Design-Build Stipulated Price Contract

CCDC 15 Design-Builder / Consultant Contract (subcontract)

42
Q

What is a Public Private Partnership (P3)?

A

A P3 is a form of partnership between the public and private sectors where a combination of financing, design, construction, operation and maintenance of public projects relies on alternate sources of financing and revenue to cover all or part of the capital costs (including debt servicing, principal payment and return on equity), as well as operating and maintenance costs for the project.

There is no standard form a contract for P3 delivery method.

43
Q

What is the purpose of CCDC documents?

A

CCDC construction documents:

  • Are relied upon as familiar industry standards.
  • Provide balance, uniformity and standardization for bidding and contracting procedures.
  • Respect the interests and preserve the rights of all parties involved in a construction project by equitably allocating risk to the party most able to manage it.
  • Are developed in a collaborative environment that allows for the serious consideration of the rights, interests and obligations of all parties.
  • Balanced contracts reduce the risk of claims and disputes, avoiding needless expense and loss of time to the construction process.
  • Recognize legal precedents established by the courts.
44
Q

What are the architect’s responsibilities in a construction contract?

A

The architect’s specific office functions include:
- Representing and providing advice to the client; review of the construction schedule and contractor’s schedule of values;
- Preparing all documentation for the contractor and the client and others, including: Supplemental Instructions; Field Review Reports; Change Orders; Change Directives; summary of Change Orders; certificates;
- Coordinating the services of consultants;
evaluating contractor’s proposed substitutions and progress claims;
- Reviewing shop drawings;
- Reviewing operating and maintenance manuals at project close-out;
- Rendering interpretations;
- Follow-up with warranty items during the warranty period

45
Q

What are the client’s responsibilities in a construction contract?

A

The client or owner is the entity which has entered into a contract with the contractor. The client’s basic responsibilities are:

  • Providing financing information if required;
  • Making payments to the contractor;
  • Authorizing changes in the work;
  • Providing prompt decisions and directions
46
Q

What are the consultant’s responsibilities in a construction contract?

A

Consultants assist the architect in office functions by:

  • Reviewing relevant shop drawings;
  • Interpreting their part of the contract documents;
  • Issuing supplemental instructions on their part of the contract documents;
  • Assisting in the preparation of Change Orders when required;
  • Reviewing their portion of the work to determine the percentage complete (which assists the architect in the preparation of Certificates for Payment);
  • Providing advice to assist the architect in the preparation of other certificates.
47
Q

What are the contractor’s responsibilities in a construction contract?

A

As a party to the contract with the owner, the contractor is responsible for the execution of all the work, means, and procedures required to carry out the construction work as described in the contract documents.

Specifically, the contractor:

  • Studies the contract documents and fulfils all requirements including regulatory requirements to the extent provided for in the contract documents;
  • Supervises and coordinates the work of all trades and sub-contractors;
  • Executes the work by selecting all construction methods, techniques, sequences, etc.;
  • Is usually responsible for construction safety and all workplace regulations;
  • Pays for all labour, products, and subcontracts.
48
Q

What is the purpose of construction administration?

A

Contract administration describes the services provided by the architect to fulfill the roles in standard construction contracts such as those duties outlined in General Condition GC 2.2 of CCDC 2, Role of the Consultant. The construction contract also describes their respective roles and obligations of the contractor and the owner.

In addition, contract administration provides an opportunity for the architect to assist in realizing the project by providing the contractor with technical interpretations and information.

The nature and scope of the architect’s services during the construction phase are defined by both the construction contract (such as CCDC 2) and the client-architect agreement (such as Canadian Standard Form of Contract Between Client and Architect: RAIC Document Six).

49
Q

What are the four main stages of office functions during the construction administration phase?

A
  • prior to construction;
  • during construction;
  • at close-out;
  • during the warranty period
50
Q

What tasks does the architect carry out during the Prior-To Construction Stage during CA?

A

• Assists in the preparation of the contract form in duplicate for signing by the owner
and the contractor;
• Assembles the required number of sets of contract documents
• Assembles and issues sets of drawings and specifications required by the contractor for the work;
• Issues (in some cases) a set of updated
documents showing all changes and revisions made during the bidding period to ensure that:
- There is no confusion over the appropriate document;
- No obsolete document remains in
circulation.

51
Q

During construction, what is architect required to do based on a CCDC 2 contract + RAIC 6 document?

A
  • Review shop drawings, sample & product sheets
  • Respond to RFIs and issue SIs
  • Review, prepare and issue PCOs, Change Directives, and Change Orders as needed
  • Review progress payment requests to monitor construction progress against the contractor’s schedule, and compare schedule of work vs. actual work performed
  • Prepare Certificate for Payment
  • Conduct period site reviews and issue field review reports
  • Attend site meetings as needed
52
Q

At Close-Out (end of construction), what documents is the contractor generally required to submit for review by the architect?

A
  • Occupancy permit
  • Record drawings & specifications
  • Manuals (maintenance & operating), warranties, and permits/certificates for authorization
  • Clearance Certificate from the respective provincial or health & safety agencies
  • Statutory Declarations for application for release of holdback from the GC & all sub-contractors
  • Final reports on work to correct deficiencies
  • List of all contractors & sub-contractors
  • Replacement materials, maintenance products, special tools, etc.
53
Q

What are shop drawings?

A

Shop drawings ensure and confirm the accuracy, size, and other specific data about a product or material prior to final purchase, fabrication or delivery.

The contractor is responsible for verifying: 
• quantities;
• dimensions;
• accuracy;
• completeness;
• compliance with the specifications.
54
Q

What is an RFI?

A

The RFI is a procedure for the contractor to request clarifications when the intent of the contract documents is:

  • unclear,
  • incorrect, or,
  • information is missing.

During the construction phase of a project, the general contractor, who is unable to find the information through review of the contract documents, often
seeks information from the architect or the
architect’s consultants.

55
Q

What are supplemental instructions? (SIs)

A

The architect (sometimes with the assistance of consultants) issues Supplemental Instructions to clarify or interpret the contract documents.

Supplemental Instructions can also be issued to provide direction to the contractor concerning a problem which may have resulted during the course of construction.

56
Q

What is a Change Order?

A

Change Orders cover adjustments to the scope of work that require a change changes to the contract price or contract time. Sometimes the process for making changes can be demanding and time-consuming. Can also confirm charges or adjustments to contingency or cash allowances in the contract.

Issuing Change Orders is the final step in the process of confirming and recording changes in contract price and/or changes in contract time for a construction contract.

57
Q

What are some reasons why a Change Order would be issued?

A

• additional requirements or changes in the requirements made by the client/owner;
• new or different interpretation of requirements by Authorities Having
Jurisdiction;
• work not described in the contract
documents;
• work inaccurately or incorrectly described in the contract documents;
• substitutions which may affect the contract time or contract price.

58
Q

What is the purpose of a Proposed Change Order (PCO)?

A

A PCO can preclude a Change Order. The purpose of this form is to alert the contractor to the proposed change and to provide the contractor an opportunity to submit a quotation for additional cost (or credit) or a change in time (if any) for the proposed change.

PCOs are also known as:

  • Notice of Change
  • Contemplated Change Order
  • Change Notice
59
Q

What is a Change Directive?

A

A Change Directive is used when further time is required to finalize or negotiate the changes to the contract price and contract time, but work on the project cannot be delayed.

The Change Directive authorizes the change in the work to proceed and indicates that the adjustment to contract price and contract time will be finalized later by Change Order.

May be issued without a preceding PCO.

60
Q

What is a Certificate for Payment?

A

In typical stipulated-sum construction contracts, the architect is responsible for preparing Certificates for Payment indicating when and how much a client must pay the contractor.

Certificates for Payment are based on:
• the schedule of values agreed to and 
prepared at the start of construction;
• the architect’s determination of the 
percentage of work completed, based  
on a field review;
• the applicable holdbacks required in the 
provincial or territorial lien legislation
61
Q

What is a Certificate of Substantial Performance?

A

A certificate issued under the appropriate lien legislation attesting that the contract between the owner and the contractor is substantially complete.

In most provinces, the date of substantial
performance of the construction contract must be documented. This certificate sets a date which triggers the beginning of the warranty period (as outlined in CCDC 2) and the release of holdback monies (lien funds) which have been established to provide some financial protection to sub-contractors.

62
Q

What is a holdback?

A

A percentage of the monetary amount payable under a (construction) contract, which is held as security for a certain period of time. The percentage and period of time are based on the provincial
lien legislation.

63
Q

What is a lien?

A

A legal claim on real property to satisfy a debt owed to the lien claimant by the property owner. This claim can carry the right to sell the property upon default.

64
Q

What are some reasons why general contractors might abuse the RFI process by issuing an excessive number of unnecessary or “frivolous” RFIs?

A
  • To ask the architect is easier than taking the time to find information readily available within the contract documents;
  • To attempt to transfer to the architect the contractor’s responsibility for acts or omissions (refer to the General Conditions, GC1.3.2 and GC1.3.3 of RAIC Document 6, 2002);
  • To imply non-existent errors or omissions in the documents to support claims for additional work;
  • To set up circumstances to support subsequent unjustified delay claims; or
  • To discredit the architect’s competence while, at the same time, promoting the contractor’s mastery of the construction process.

The prudent architect ensures that the client/architect agreement includes provisions for appropriate compensation by the client for additional work related to:
• Changes to the Contract Price or Contract Time resulting from RFIs, or
• Changes in scope initiated by the client.

65
Q

How can the architect ensure that they will be reimbursed for the expense of responding to unnecessary RFIs issued by the GC?

A

Consideration should be given to adding the following Supplementary Condition to the CCDC 2 General Conditions, revising GC 5.8 Withholding of Payment to state:

• The architect may determine that certain RFIs issued by the contractor are unnecessary and shall, in responding to such unnecessary RFIs, give the reasons for the determination in each case;
• If the contractor continues to issue unnecessary RFIs, the architect, after having identified a minimum of five [for example] RFIs as unnecessary, will invoice the client for the additional administrative cost of responding to each of the subsequent unnecessary RFIs;
• The architect will notify the contractor and client each time such an additional administrative cost is charged;
• The client shall reimburse the architect for the monthly total of such additional administrative costs; and
• The monthly total of such additional administrative costs shall be charged to the general contractor by showing the monthly total as a credit on each subsequent Certificate for Payment. This
constitutes a change to the contract price and must be handled as a Change Order.

66
Q

Why is “supervision” and “inspection” a level of service not provided by the architect?

A

“Supervision” implies the overseeing of the
construction work, including the activities undertaken by workers on site, which is the responsibility of the contractor, not the architect.

“Inspection” means a “close examination” (of construction); once again, this level of service is beyond the architect’s responsibilities.

67
Q

What are the three main purposes of a field review?

A
  1. To monitor the contractor’s performance in maintaining both the construction schedule and the standards or quality of construction;
  2. To provide guidance to the contractor by interpreting the contract documents and issuing necessary Supplemental Instructions;
  3. To fulfil performance standards of general review as required by the client-architect agreement, Authorities Having Jurisdiction, and provincial or territorial associations of architects.
68
Q

What is the architect’s role while present on site?

A
  • conduct a general or field review;
  • attend site meetings;
  • interpret contract documents or resolve problems;
  • observe testing or other procedures;
  • review and accept samples, mock-ups, etc.;
  • meet with consultants, contractors or the client regarding the progress of the construction;
  • determine the percentage of the work completed (information which is used to prepare certificates).
69
Q

What is the client’s role while on site?

A

This depends on the client’s expertise and interest in the construction phase of a project. Some clients will assign a representative dedicated to this phase or hire a clerk of the works to monitor and account for construction activities. On the other hand, some clients rely exclusively on the architect as their representative. The client or designated representative usually attends regular job-site meetings.

70
Q

What are the role of the consultants on site?

A

Consultants usually review the portion of the work which they have designed or for which they are responsible. They also determine, whether their portion of the work is in general conformity with the contract documents. In addition, consultants assist the architect in preparing certificates by attesting to how much of their portion of the work has been completed. Consultants may also be involved with other inspection and testing procedures.

71
Q

What is the role of the contractor while on site?

A

The role of the contractor is described in a construction contract, such as CCDC 2, and in the project specifications. Generally speaking, the contractor is responsible for the construction schedule, the quality of construction, and the construction methods and procedures.

The contractor is also responsible for supervising the crew and coordinating sub-contractors. Typically, if a project is of a certain minimum value, most contractors will assign one individual to manage the project. This person — known as the site superintendent — is usually assigned to only one project at a time, frequently setting up an office temporarily in a construction trailer or part of a building which is under renovation. The contractor usually contacts the architect at varying stages of the project to schedule reviews.

72
Q

Who is responsible for safety on the construction site?

A

Typically the constructor (i.e. general contractor) is solely responsible for construction safety at the workplace and:

  • Complying with the rules, regulations, and practices required by the applicable occupational health and
    safety legislation;
  • Initiating, maintaining, and supervising all safety precautions and programs in connection with the performance of the work.

Neither the client nor architect is responsible for safety at the construction site, unless the owner has awarded separate contracts or is using the owner’s own forces for parts of the project?

73
Q

What is the architect not responsible for on site?

A
  • the means, methods, sequence, procedures, techniques or scheduling of construction activities;
  • job-site safety;
  • electrical and mechanical services
74
Q

List general milestones on when to conduct a field review.

A
  • At project start-up and/or excavation;
  • At the start of major sub-contractors’ work on elements forming the enclosure of the building, such as:
  • forming and framing;
  • structural steel;
  • masonry;
  • waterproofing;
  • cladding;
  • window systems;
  • roofing;

• At the start of finishing trades, such as:

  • floor finishes;
  • cabinetwork;
  • wall finishes;
  • painting;

• When significant new materials and
equipment are delivered to the site.

75
Q

Additional field reviews should be considered immediately before and during concrete placement to review:

A
  • key dimensions;
  • placement of reinforcing steel and inserts;
  • presence of any debris, rust, water, etc., within formwork;
  • placement of electrical and mechanical services;
  • concrete placement.
76
Q

When the work of one trade is covered up by
another trade, it is too late for observation; therefore, field reviews must be done before the following work is covered up:

A
  • insulation;
  • fireproofing/firestopping;
  • vapour barriers;
  • blocking and furring;
  • electrical and mechanical services.
77
Q

The architect usually conducts a field review after any serious or unexpected change in the weather — which can have an adverse effect on work in progress — to determine whether any damage has been done to existing work, such as:

A
  • undermining or weakening of footings or foundations by heavy rain;
  • freezing of concrete or mortar due to sudden drops in temperature;
  • frost penetration of sub-soil;
  • damage to roofing membranes and unbraced walls by strong winds;
  • improper curing or drying out of materials from prolonged heat.
78
Q

What is “The Construction Site?”

A

The construction site — the location identified in the contract documents where the building is situated — is called “Place of the Work” in CCDC documents.

79
Q

What is an “Extended Site?”

A

An extended site refers to a location where products may be stored away from the construction site. The value of major items delivered to an off-site location may be considered eligible for payment, subject to the
terms of the contract or once the following conditions have been met:

  • after authorization or approval (usually for products which are costly or custom-made);
  • after the contractor has made provision for:
  • secure storage (for example, a bonded warehouse);
  • insurance;
  • bonding;
  • after the architect has made visits to observe the items at their storage location.
80
Q

What are the three locations an architect may be required to conduct a review?

A
  1. The Construction Site
  2. The Extended Site
  3. Plant or Off-Site Location
81
Q

What is a “Plant or Off-site Location?”

A

Review of work which is fabricated or assembled
in a plant may also be necessary. The architect
or consultants observe work in the plant to:

• examine the manufacturing facilities and
capabilities of the sub-contractors before a contract is awarded;
• check or confirm progress of items, such as:
• items whose schedule for delivery is critical to the progress of the project;
• items which come to the construction site pre-assembled and could not be properly reviewed after delivery;

82
Q

What is the relationship between independent testing agencies and the architect?

A
  • inspection and testing is usually recommended by the architect or the engineers;
  • these specialists do not supersede the architect’s authority;
  • these services are ancillary to the architect’s basic construction administration services;
  • the architect must ensure that he/she is only assisting in the process and does not assume a contractual obligation;
  • inspection and testing firms undertake tests and issue timely reports, but they do not interpret the results of these tests or issue instructions to the contractor;
  • interpretations are made by the contractor in the first instance and finally by the architect and the engineering consultants.
83
Q

Name 5 examples of inspection and testing required.

A
  1. Concrete - testing for compressive strength
  2. Thermal & Moisture Protection - testing for fireproofing/firestopping
  3. Conveying equipment - elevator testing & certification
  4. Fire Suppression - test & certify sprinkler system
  5. HVAC - air balancing
84
Q

List some tips for site observations?

A

Aesthetics, code requirements, drainage, expansion & control joints, fireproofing, fire protection, envelope

85
Q

What are the 5 essential elements of field review for building code matters?

A
  • site visits;
  • written reports;
  • changes to the work;
  • shop drawings;
  • coordination of consultants.
86
Q

When is the architect required to provide a field review for both Building Code & non-Code matter?

A

When contracted to certify payments to the contractor?

87
Q

The project manager is a leader responsible for:

A
  • Ensuring that the project proceeds through successive stages from program approval to project implementation;
  • Keeping the project on time and within budget;
  • Managing the progress of the project by: directing an internal team; coordinating engineers and other consultants; and achieving the firm’s financial objectives;
  • Providing proper project closeout.
88
Q

What are some definitions of quality as it relates to architectural services?

A
  • Providing value to clients;
  • Providing a service that is delivered in a consistent & professional manner
  • Offering solutions that fit the purpose);
  • Providing service which consistently meets or exceeds performance levels required by the client.
89
Q

What is Quality Assurance?

A

All the planned and systematic activities implemented within the quality system and demonstrated as needed to provide adequate confidence that an architectural practice will fulfil requirements for quality.

90
Q

What is Total Quality Management?

A

A management approach of an organization centered on quality, based on the participation of all of its members and aiming at long-term success through client satisfaction and benefits to all members of the organization and to society.