CHOP Flashcards
What is RAIC Document 5?
Canadian Rules for the Conduct of Architectural Competitions
What is RAIC Document 6?
Canadian Standard Form of Agreement Between Client and Architect
What is RAIC Document 7?
Canadian Standard Form of Agreement Between Client and Architect — Abbreviated Version
What is RAIC Document 9?
Canadian Standard Form of Agreement Between Architect and Consultant
What is CCDC 2?
CCDC 2 – Stipulated Price Contract is the industry standard prime contract between Owner and prime Contractor. This contract establishes a single, pre-determined fixed price, or lump sum, for the project.
The contract outlines the high-level administrative requirements and procedures needed for construction projects, including the role and authority of the consultant, procedures for changes in the work, work by other contractors, insurance requirements, prerequisites for Ready-for-Takeover, dispute resolution procedures, early occupancy by the Owner, and more.
Operating on the basis of a stipulated price, the CCDC 2 assumes monthly progress payments and makes reference to provincial payment legislations where applicable.
What is CCDC 3?
CCDC 3 – 2016 is a standard prime contract between Owner and prime Contractor to perform the required work on an actual-cost basis, plus a percentage or fixed fee which is applied to actual costs.
What are Statutory Declaration Forms — CCDC 9A, and 9B?
CCDC 9A – 2018 Statutory Declaration of Progress Payment Distribution by Contractor is a sworn statement for use by the Contractor as a condition of receiving payment for either the second and subsequent applications for progress payment or the release of holdback funds.
CCDC 9B – 2018 Statutory Declaration of Progress Payment Distribution by Subcontractor is a sworn statement for use by the Subcontractor as a condition of receiving payment for either the second and subsequent applications for progress payment or the release of holdback funds.
What is CCDC 10?
CCDC 10 identifies the issues that should be considered when selecting a project delivery method. It examines the characteristics and critical conditions for the following common project delivery methods:
Design – bid – build
Design – build
Construction management for services
Construction management for services and construction
Integrated project delivery
CCDC 10 also includes a chart showing how different project delivery methods can affect the following common project issues if all critical conditions are met:
Scope definition; Performance requirements; Schedule requirements; Costs; Allocation of human resources and construction expertise; Collaboration and communications
What is CCDC 11?
CCDC 11 – Contractor’s Qualification Statement offers a standard format for contractors to provide information about their company, capacity, skill, and experience. It includes:
Company information – legal structure, financial reference, contract security reference, insurance reference, health and safety, valuation of construction work projected for current year and the actual value for the past four years.
Qualification and experience of personnel – key office and site personnel proposed for the qualification statement.
Project experience – A list of five relevant projects for each of the following:
Key construction projects completed in the past five years;
Comparable construction projects completed;
Key construction projects underway. For recommended practices on the pre-qualification process refer to CCDC 29 – A Guide to Pre-qualification.
What is CCDC 12?
CCDC 12 – 1994 Is a model form to assist the Owner in showing that financial arrangements have been made to fulfill the Owner’s obligations under the contract (e.g. CCDC 2).
What is Design-Build Stipulated Price Contract — CCA — CSC — RAIC Document 14?
This document is based on CCDC 2 – 1994 ‘Stipulated Price Contract’ and CCAC 6 – 1994
‘Canadian Standard Form of Agreement Between Client and Architect’.
What is CCDC 20?
CCDC 20 – 2008 Guide to the Use of CCDC 2 – 2008 Stipulated Price Contract is a guide document designed to assist users of CCDC 2 – 2008.
What is CCDC 22?
The purpose of this guide is to help the construction and business communities in Canada better understand surety bonds and the suretyship process. This guide was prepared by the Surety Sub-Committee of the Canadian Construction Documents Committee (CCDC) and is endorsed by the constituent organizations of the CCDC and the Surety Association of Canada.
CCDC 22 describes the suretyship process and clears up some commonly held misconceptions. The guide is divided into three parts. Part 1 reviews suretyship, what a bond is and how it differs from other risk management tools. Part 2 discusses how suretyship works in practice, how bonds are obtained, the requirements of a surety company, and how the company proceeds through the prequalification process. Part 3 examines the various forms of bonds with a view to understanding the purpose of each bond and the claims process.
What is CCDC 23?
CCDC 23 addresses all aspects of the bid calling and contract award process:
Summary of fundamental principles under the law of competitive bidding such as the legal obligation of owners and bidders under Contract A and Contract B.
Overview of the bid documents: Division 00 to Division 49.
- Calling for bids: bid solicitation, bidding period and scheduling, pre-bid meetings and site-visits, bidder inquiries and issuances of addenda.
- Receiving bids: bid closing dates and times, bid modifications, bid opening, two-stage bid closing, electronic receipt of bids.
- Awarding the contract: evaluation for compliance, selection of successful bidder, contract award, post-bid negotiations and re-bidding, owner’s responsibilities, notification of contract award.Users of the CCDC 23 are encouraged to familiarize themselves with CCDC Master Specification for Division 00 as a companion document. Division 00 provides standard text that reflects the best practices in CCDC 2.23
What is CCDC 24?
CCDC 24 – 2016 is a guide document to assist users of CCDC 2 – 2008 in meeting the administrative requirements outlined in that standard contract form.
For each model form the guide contains a brief explanation of each of the administrative processes involved, a short narrative description to guide users of the form, a list of items which should be included in the form, and an example of a model form.
What is CCDC 40?
CCDC 40 – Rules for Mediation and Arbitration of Construction Disputes sets out specific methods for settling disputes incorporating the concepts of negotiation, mediation and arbitration to encourage speedy, inexpensive and voluntary resolutions of construction disputes.
CCDC 40 has been incorporated by reference in CCDC contract forms, including CCDC 2. It is also a standalone document and can be used with other construction contract forms.
What are the differences between a corporation, a joint venture, a partnership and a sole proprietorship?
Corporation: A legal collective entity which acts as an individual business unit requiring a legal
instrument to create the entity as a commercial corporation.
Joint Venture: A defined business relationship between two or more architectural practices for a limited
purpose or objective, without some of the inherent duties and responsibilities of a partnership.
Partnership: An unincorporated relationship between architects (or other professionals as may be
permitted by provincial requirements) for carrying on business in common.
Sole Proprietorship: An architectural practice owned and controlled exclusively by one person.
What is goodwill in the context of succession planning?
Goodwill: The intangible element of the value of a business (including the worth of the architect’s legacy,
image, and client base) calculated as the amount by which the value for sale or investment exceeds the sum
of net identifiable assets.
This is sometimes measured as the current value of expected future earnings in excess of the return required for sale or investment, or calculated as a multiple of earnings performance averaged over a period of five or more previous years.
What is a Project Cost Control Chart?
A project cost control chart is a financial record of each project, which includes professional fees, consultants’ fees, staff time expended, budgeted time, expended payroll, and profit and loss for each phase of the work.
What is a payroll burden?
Payroll Burden: Includes required contributions by the employer (statutory benefits), including
Employment Insurance (EI), Canada Pension Plan/Québec Pension Plan (CPP/QPP), health taxes, and
workers compensation in addition to discretionary benefits such as insurance and pension plans, and
bonuses