Section 3.3 Instrumentation Flashcards

1
Q
  • LCO 3.3.1 Rx Trip Instrumentation*
    • *

If the plant is in MODES 3-5 and we lose 1 or both extended range NIs, what are our actions?

A
  • LCO 3.3.1 Rx Trip Instrumentation*
  • Action 5*
    • *

Loss of 1 Extended Range:

  • Restore to OPERABLE [72 hrs]

OR

  • Suspend all positive reactivity changes [Immediately]

Loss of Both Extended Ranges:

  • Suspend all positive reactivity changes [Immediately]

AND

  • Isolate unborated water sources [15 min]

AND

  • Restore to OPERABLE [1 hr]

OR

  • Secure unborated water sources [2 hrs]

AND

  • Verify SDM [4 hrs] and every 12 hrs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • LCO 3.3.2 ESF Instrumentation*
    • *

If the charging header pressure indicator (PT-0204) fails while in MODES 1-4, what are your actions?

A
  • LCO 3.3.2 ESF Instrumentation*
  • Action 16*
    • *
  • Place in trip [1 hr]

AND

  • Restore to OPERABLE [7 days]

OR

  • Be in MODE 3 [6 hrs]

AND

  • Be in MODE 5 [Following 30 hrs]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • LCO 3.3.5 Remote Shutdown Room*
    • *

When is LCO 3.3.5 Remote Shutdown Room Applicable?

A

MODES 1-3

Bases:
Allows operators to maintain plant in safe shutdown (MODE 3) from a location other than the control room.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • LCO 3.3.1 Rx Trip Instrumentation*
    • *

If the plant is in MODES 1-2 and we lose 1 Intermediate range NI, what are our actions?

A
  • LCO 3.3.1 Rx Trip Instrumentation*
  • Action 3*
    • *

Below P-6:

  • Restore to OPERABLE before exceeding P-6

Above P-6 but below P-10:

  • Restore to OPERABLE before exceeding P-10
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • LCO 3.3.1 RTS Instrumentation*
    • *

Can the CRMP be applied to anything in LCO 3.3.1 RTS Instrumentation?

A

No

Most actions involve placing channel in bypass and then placing in trip within 72 hrs.

Note:
LCO 3.3.2 ESFAS Instrumentation: The CRMP can be applied to most things and if it cannot be applied then Be in MODE 3 [6 hrs] and MODE 5 [Following 30 hrs]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • LCO 3.3.6 Post Accident Monitoring*
    • *

When is LCO 3.3.6 Post Accident Monitoring Applicable?

A

MODES 1-3

Most actions are fix within 30 days and submit a report in 14 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • LCO 3.3.6 Post Accident Monitoring Instrumentation*
    • *

How many sensors can fail in a RVWL probe and RVWL still be OPERABLE?

A
  • *Probe consists of 8 sensors
  • 2 in the top / 6 in the bottom***

Need ≥ 1 in the top OPERABLE
AND
Need ≥ 3 in the bottom OPERABLE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • LCO 3.3.1 Rx Trip Instrumentation*
    • *

If the plant is in MODE 2 and we lose 1 source range NI, what are our actions?

A
  • LCO 3.3.1 Rx Trip Instrumentation*
  • Action 4*
    • *
  • Suspend Positive Reactivity Additions [Immediately]
    • *

Limited Cooldown and dilution is allowed if accounted for in SDM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly