Construction Project Life Cycle

1
Q

What are the key Construction Project Phases?

A
8 of them
Definition
Planning
Designing
Tendering
Construction
Commissioning
Operation
Evaluation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is EPC

A

Engineering Procurement Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are some characteristics of Project Phases?

A

Phases can overlap
End of each phase has go or no-go
Change in past phase moves project back into that phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does PDS stand for?

A

Project Delivery System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why use a Project Delivery System?

A

Ensures a quality end product, delivered on time, and within budget to satisfy client.
Ensure best practices are implemented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key phases in the project delivery system?

A
There are 6:
Planning
Defining
Implementing
Commissioning
Operation
Evaluation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens in the Planning phase?

A

Identify and Define in detail the client investment opportunity or need.
Assess all feasible alternatives.
Establish Budget and Completion Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happens in the Definition phase?

A
Translate the Investment Analysis Report into technical criteria.
Prepare project Scope definition.
Define Implementation Strategies.
Transfer Responsibility to PM.
Choose a Consultant
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What happens in the Implementation phase?

A

Design
Tendering and Award
Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is created during the Design portion?

A
Produces...
Conceptual Design
Detailed Drawings
Final cost estimates
Time schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens during Tendering?

A

Selection of a Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are some keys to winning a RFP?

A

Know your competition
Establish a relationship when possible
Identify Owner’s ‘hot points’
Presentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the 3 main ingredients of the Treasury Board Policy?

A

Honesty
Fairness
Best Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What happens during Construction?

A

The physical building of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What happens in the Commissioning phase?

A

The static completed project is transitioned into full working order.
Ensures the design intent is met.
Ensures all contractual responsibilities are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What happens in the Operation phase?

A

Establish and ensure reliability.
Test and record operating performance.
conduct O and M.

17
Q

What happens in the Evaluation phase?

A

Assess the project in terms of planned and actual.
Determine any variances from planned performance.
Record the project performance for review and lessons learned database.