Scheduling activities Flashcards
1
Q
critcal part Determines :
The earliest possible time – project completion
A
true
2
Q
critical path Determines :
The earliest possible time – project completion
Amount of scheduling flexibility (total float)
Each of various network path
Overall project duration
Activities critical to overall project
Delay in completion of entire project
A
true
3
Q
Early Start: the latest date the activity can begin
A
false
Early Start: the earliest date the activity can begin