Scheduling Flashcards

1
Q

Define the parts of a node in a “on Node (AON) network”

A

1-2-3 5 7-8-9 1: Earliest star time 2: Duration 3: Earliest finish time 5 task identifier 7: Latest start time 8: Total float 9: Latest finish time Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is total floats?

A

Total float is the amount of time an activity can be delayed without affecting the project completion date. It is the difference between LST- EST or LFT-EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Free floats?

A

Free floats is amount fo time an activity can be delayed without affecting the start date of any of its successors. Free Float= EST of earliest successor - EFT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the advantages of a Gantt Chart?

A
  1. Easy to read overview
  2. Easy to construct
  3. Interdependencies can be shown
  4. Helps develop resource bar charts
  5. Aids progress tracking
  6. Easy to print
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the limitations of a Gantt Chart?

A
  1. interdependencies not as apparent as in a network diagram