Resource Management Flashcards

1
Q

What types of constraints could exist in resource allocation?

A
  1. Cash Flow
  2. Rsource volume
  3. Staff availability
  4. Contractor availability
  5. Shared facilities
  6. Policy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Resource Management Techniques

A
  1. Resource estimating
  2. Resource allocation
  3. Resource smoothing
  4. Resource Levelling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the process of resource allocation?

A
  1. Draw network
  2. Create bar chart
  3. Add resource load
  4. Calculate totals and prepare initial resource load histogram
  5. Check against capacity
  6. Optimise allocation of resource
    1. Perform resource smoothing or levelling
    2. Draw final resource histogram
  7. Cumulate data and draw “S-curve”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Optimise Resource Allocation

A
  • Need to adjust schedule to meet resource constraints
  • May wish to eliminate peaks and troughs
  • Is tasks are moved, then this is reflected in the resource loading
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Resource Optimisation methods

A

2 methods depending on whether the priority is time or resource:

  1. fixed time limit: resource smoothing. Time limited scheduling
  2. fixed resources: resources levelling. Resource limited scheduling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Adjust to meet Constraints

A
  • Any task with float may be delayed: protects the critical path
    • Free float: best to adjust these, as all other tasks unaffected
    • Total float: other tasks may have to move as well
How well did you know this?
1
Not at all
2
3
4
5
Perfectly