Scheduling Flashcards
Definitions for Network Calculations
ES?
Early start = Latest Early finish of all Immediately preceding activities (IPA)
Definitions for Network Calculations
EF?
Early Finish = Early Start + Duration
Definitions for Network Calculations
LF
Late Finish = Earliest Late start of succeeding activities
Definitions for Network Calculations
LS
Late start = Late finish - duration
Definitions for Network Calculations
TF
Total Float = The maximum that the ES of an activity can be delayed without changing the overall project duration for a given activity= Late start - Early start
Definitions for Network Calculations
FF
Free float = The maximum that the ES of an activity can be delayed without changing the ES of ANY immediately following activity.
Definitions for Network Calculations
CP
Critical path = the longest interconnected path through the network. the length of which equals the project duration activities
Things that are accounted for in the construction planning phase
- The identification of specific activities of work required and the interrelationships between those items (precedence relationships)
- the proper sequencing of the specific activities of work in order to complete the project in an optimum amount of time
- the time for delivery of materials and installed equipment
- the types, quantities, and duration of use of construction equipment
- the classification and number of workers required and the periods of time they will be required
- the amount and timing of financial assistance required
What is Work Breakdown Structure(WBS)?
the progressive hierarchical breakdown of the project into smaller pieces to the lowest practical level to which costs can be applied
Types of Construction Schedules
Bar Gantt Charts
Network Schedules (Critical Path Method diagrams)
-Activity on arrow diagram
-Activity on node diagram
What is a Critical Path Schedule?
-Relationships between activities are shown (precedence relationships)
-Critical activities determine project duration and indicate critical path
Activity on arrow diagrams (Critical path Method)
-arrows represent activities
-Nodes represent points in time
Activity on node diagrams (Critical Path Method)
-node boxes represent the activities
-arrows indicate relationships between nodes
Activity on Node diagrams
-boxes at nodes represent the activity
-lines show the interrelationship of activities
-uses a “finish-start” relationship between dependent activities
-easier to draw than arrow diagrams
Negative Total Float on Critical Path
-The contract may call for a completion time of 180 workdays
-Forward pass gives total time of 190 workdays
-start backward pass at 180 –all critical activities have TF = -10
-Must save 10 days throughout project