Estimating Flashcards

1
Q

3 steps of estimating from owners side

A
  1. conceptual
  2. Alternative design estimate
  3. owner’s engineers estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3 steps of estimating from contractor’s side

A
  1. Contractor’s estimates
  2. Alternative construction method
  3. Changes/Claims
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Steps of estimating: Conceptual

A

-Feasibility study
-Owner hires A/E to provide an order of magnitude estimate of the cost
-Rough cost estimate
-owner has a general idea of what the owner can get with their money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Steps of estimating: Alternative design estimate

A

-evaluating options
-A/E comes up with cost estimates based on previous experience and relies on bid abstracts for cost information
-Quantity Takeoff
-Design to a level where the owners can make a choice
-At the end of the process, the owner decides on which option he wants to go with
-drawings and specs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Steps of estimating: Owner’s Engineers estimate

A

-Provides a baseline cost to evaluate other bids
-Quantity takeoff from engineers
-Engineers rely on past experience of bid abstracts
( Owners’ bid estimate (so that owners know what to expect) )

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Steps of estimating: Contractor’s Estimates

A

-(MOST DETAILED) b/c if it’s inaccurate, the contractor will lose money
-Contractor’s bid estimate
This includes a detailed quantity takeoff
-Based on the in-house cost database
-Considers construction methods (may not necessarily be the most efficient equipment for the job, but is it worth buying new equipment?) Contractors decide

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Steps of estimating: Alternative Construction Method

A

-Has been awarded the job
-Now detailed review of how the job is priced
-Is there a better way to do the work —> a better construction method?
-to maximize profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Steps of estimating: Changes/Claims

A

-Change order: outside the scope of the original contract. The contractor and owner sign off on it.
-Change directives: the contractor has to perform the work the owner has requested.
-Needs to be priced
-Claims: when the contractor thinks that they are not getting paid for something that they think should be paid for

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Contractor’s Bid Estimate Horizontal Breakdown (highest to lowest risk)

A
  1. Labour
  2. Repair and service labour
  3. Operated and maintained cost
  4. Expendable materials
  5. Rental
  6. Equipment Operating expenses
  7. Subcontractors
  8. Permanent Materials
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Contractor’s Bid Estimate vertical Breakdown

A
  1. Direct costs (Physical construction)
  2. Indirect cost (management)
  3. Escalation (inflation)
  4. Interests
  5. Markup (general risk, profit, home office, general administration)
  6. Contingency (identified vs unidentified)
  7. Bond costs (bid bond)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is expendable material? (EM)

A

Any material falling outside of the neat lines on drawings
+temporary structures (don’t forget that this is included in the definition)
(e.g. silt fences, formwork)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is equipment operating expenses? (EoE)

A
  1. Fuel, oil, and grease (FOG): lubricants needed for machinery (NOT GAS, don’t forget)
  2. Tires (can contribute a substantial expense)
  3. Small repair parts
  4. 3rd party overhaul
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Repair + Service Labour (RL)?

A

A high-risk cost type
1. Direct cost
2. Why break them out? To know how much money goes towards keeping equipment operating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the two types of contingencies?

A

Identified and unidentified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are Identified contingencies?

A
  1. Soft Subs
    a contractor with no performance bond
    Good reputation with the lowest bid but no performance bond. The owner takes on the risk. And contingency is to prepare for the risk
  2. Productivity Hedge
    Productivity-related, in case work, doesn’t get done on time
  3. Event
    Prep in case there is a workers’ strike. Or a specific event.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are unidentified contingencies?

A

Markups
1. Home office
General and administrative
2. Profit
3. General Risk
“Sleep at night”
For unexpected events

17
Q

What are escalations?

A

predictions on how much prices are likely to go up due to inflation (critical to lumpsum)

18
Q

what are the types of indirect costs?

A
  1. Salaried Payroll (superintendent, project manager, foremen)
  2. Time-related expenses (rental for the equipment) monthly expenses
  3. Non-time related overhead expense (purchasing computers) one time
  4. Insurance and taxes
  5. Construction planning
19
Q

Shift Differential Pay

A

additional or modified compensation based on the time or job tasks associated with an hourly employee’s shift

20
Q

What is “rental”?

A
  1. Rental, Depreciation, Write-off (how you procure your equipment to the job site)
  2. In-house equipment division (larger contractors)
    -Rent equipment for their own projects
    -Operated as a profit center (increase price or replace equipment if not earning money off of it)
  3. Rent/Lease
  4. Operated + Maintained (highest risk): the third company provides the equipment and operator
    Other than O+M, low risk
21
Q

Highest to lowest Risk Projects

A
  1. Hand-mined drainage tunnels
  2. Bridge river crossing substructure
  3. Rapid transit tunnels in rock by TBM
  4. Large earth-filled dam for BUREC
  5. Sewage Treatment Plant
  6. High-Rise Building