Schedules and Resources Flashcards
Scheduling Steps
Create WBS
Arrange WBS elements into precedence diagram (from lowest level of WBS only) Undertake Critical Path analysis
Convert precendence diagram into Gantt chart (add durations)
Add resource histogram
Create cumulative cost chart
Critical Path
Shortest route through precedence diagram (longest duration) with no float
Process:
Forward pass: ES Duration = EF - carry on through from left to right. If there are two choices of ES use the higher number
Then take the LS of the final node and move it down into the LF
Backward pass: LF-duration = LS
If there is a choice use the lower number
Total Float: EF - LF
Free Float = EFn - ESn+1
Total vs Free Float
Tasks with (total) float if delayed will affect the next task but not the end date.
Tasks with free and total float can be delayed without any impact on other tasks or the end date.
Benefits of Critical Path Analysis
Illustrates which tasks are more time critical
Visualises detail of inter-dependencies, relationships between tasks, impact of delays.
Benefits of Gantt
Helps illustrate schedule for communicating progress
Converts relative to absolute timings
Can be colour coded to add information e.g. critical path
Shows milestones
Software systems +/-
\+ Quick \+ Facilitates scenario testing \+ Flexible if changes needed \+ Customisable \+ Supports multiple users \+ Facilitates reporting/dashboards etc. \+ Can interface with other platforms e.g. finance
- Can be a crutch/repalcement for thinking
- Can provide spurious accuracy
- Can be time consuming and overly elaborate
- Can limit flexibility
Resource Management themes
Availability of resources - time, place
Awareness of scarce components
Limits and constraints
Costs - profiling and cash flow
Types of resource
Reusable e.g. people
Consumable e.g. fuel
Equipment/Technology e.g. boring machine, server space
Materials - converted into the deliverables
Resource Histograms
Time along X axis Resource value/quantity along Y axis
Shows at a glance when resources are needed. Facilitates cost planning
Resource management techniques (strategic)
Smoothing - using total float to assign resources more slowly without affecting project end date
Levelling - assigning resources as available, will affect end date
Task Splitting - split tasks to make resources available. Can incur de/remobilisation costs.
Resource management techniques (tactical)
Reduce scope
Seek efficiency
Remove bottlenecks/delays (with suppliers perhaps)
Spend more - e.g. weekend working
Budget baselining - benefits
Baselined budget:
- Records progress against a baseline
- Illustrates funding requirements
- Supports change control
- Links with cost breakdowns to understand spend
- Supports review cycles
- Supports Cost management
Finance terminology
Commitment - a future cost which can not be avoided. E.G. rent.
Accrual: Cost incurred but not yet invoiced. Helps to provide a better picture of spend.
Forecast: Prediction of future spend. Useful for review purposes and for org planning.
Cash Flow: Having money available when it is needed.Borrowing can be expensive.
Earned Value Definition
“Earned value management (EVM) is a project control process…
It facilitates the integration of project scope, time and cost objectives and the establishment of a baseline plan for performance measurement.”
Helpful to understand project progress against plan, particularly budget.
Earned Value Analysis Terminology
ATE actual time expended EV earned value PC planned cost AC actual cost BAC budget at completion EAC estimate at completion Planned completion Actual Completion CV cost variance SV schedule variance CPI cost performance index SPI schedule performance index