Schedule Management Flashcards

1
Q

Plan Schedule Management PROCESS

A

Main output is schedule management plan

Documents how you will do the other 5 processes

States how to measure the schedule and how to fix it if there are any variances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Activities PROCESS

A

Main output is activity list, activity attributes, and Milestone list

Taking the work packages and breaking them down into activities

Activities are more detailed then work packages. Each work package usually contains many activities
^Once this is done you store them in the activities list.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Sequence Activities PROCESS

A

Main output is project schedule network diagram

Take the list of activities and put them in the order you will perform them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimate Activity Durations PROCESS

A

Main output is activity duration estimates

Analyze each activity to determine how long each will take

This will be used to create the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop Schedule PROCESS

A

Main output is schedule baseline, project schedule, schedule data, project calendars.

Process of creating project schedule and the schedule baseline.
You review everything you did in the previous processes to develop the schedule

This is an iterative process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Control Schedule PROCESS

A

Main Output is work performance info and change request

Controlling project work to ensure it will finish on the schedule basline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activities List

A

Used to estimate the duration and cost of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Rolling wave Planning

A

A form of progressive elaboration
Work packages happening soon can be decomposed now
Work packages happening later will be decomposed at a later date when more details are known

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity Attributes

A

More detailed info about each activity
This includes:
Resources needed to complete the activity
-Location of the activity
-Cost
-Assumptions
-Constraints
-Leads and lags
Relationship to other activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Milestone

A

Consist of all project or phase milestones
activity that has no duration and is used to represent a major accomplishment
Example: Permit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project schedule network diagram

A

A diagram that shows the order in which you will do each individual activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Precedence Diagramming Method (PDM)

A

PDM maps out project development by creating a visual representation of critical paths and dependencies. The primary output of PDM is a project schedule network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Finish to Start (FS)

A

Finish activity A then you can start activity B
Activity A is the predecessor and activity B is the the successor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Finish to Finish FF

A

Need to finish at the same time, but not necessarily start at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Start to Finish SS

A

Activity A must start before activity B can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Start to Finish SF

A

Activity B cannot finish until activity A has started

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Mandatory Dependencies

A

Also known has hard logic
You have to finish one activity to start the next activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Discretionary Dependencies

A

Known as soft logic
Activities do not need to get done in a specific order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

External Dependencies

A

Activities are dependent on activities outside the control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Internal Dependencies

A

Activities are dependent on activities outside control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Lead

A

Overlap between activities
EX you can start taping up fixtures after half of the furniture has been removed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Lags

A

Delays between activities
Ex: Once you finish painting a room you give a lag of 1 day to let is dry before you put furniture back

23
Q

Analogous Estimating

A

Relies on historical information to assign the current duration to the activities

24
Q

Parametric Estimating

A

Uses mathematical algorithm to calculate cost or duration

Example: If it takes 1 hour to write one line of code, it would take 1000 hours to write 1000 lines of code

25
Three Point Estimation (PERT)
Program evaluation and review technique Uses 3 different values to calculate the duration or cost of an activity -Optimistic -Most Likely (Realistic) -Pessimistic
26
Optimistic
best case for the activity or the least amount of time to complete the activity Smallest of the 3 values
27
Most Likely
Most realistic Usually has a value between Optimistic and pessimistic
28
Pessimistic
Worst case for the activity Biggest of the 3 numbers
29
Beta Distribution
PERT FORMULA Places more weight on the realistic estimate Optimistic +4 * Realistic +Pessimistic /6
30
Standard Deviation
Pessimistic-Optimistic /6
31
Bottom Up Estimating
Known to be accurate Done by breaking down work to its lowest levels and then aggregating the work back up to find an overall duration
32
Reserve Analysis
Adding extra time to an activity because of risk
33
Basis of Estimates
How the estimates were developed and their ranges. Can include consumptions and constraints
34
Triangle Distribution
This is the average of 3 numbers
35
Schedule Network Analysis
Helps create project schedule Will use critical path method or resource optimization
36
Critical Path Method
The longest path through a network diagram Activities on the critical path have the highest risk Activities on this path have no float.
37
Float
The amount of time you can delay activities without delaying the project end date
38
Resource Leveling
resources are limited or over-allocated. Over-allocated means it is working on two or more activities at the same time. Resource leveling increases length of the critical path
39
Resource Smoothing
Used to ensure the critical path does not change Allows activities to change if their is float Does not effect critical path
40
Crashing
Increases cost and adds risk You add more resources to activities to complete them faster
41
Fast Tracking
Gets project done quicker but increases risk Method where you do thing in parallel instead of sequentially EX: instead of installing server and then the workstation, you would install them at the same time.
42
Release Plan
Set of iterations that will help to create a product that is given to the customers for feedback
43
Iteration Plan
Plan that will be used to create a single iteration for part of the product
44
Milestone Chart
Point in time and have no duration Only shows major deliverables Summary of Entire Project
45
Gantt Chart
Shows activity start dates, end dates, and durations. Longer the bars, the bigger the activity
46
Project Schedule Network Diagrams
Shows duration and sequencing of every activity on the project
47
Project Schedule
Contains network diagram and the gantt chart
48
Project calendar
Displays what is happening day to day on a project
49
Earned Value Analysis
Series of formulas that are used to numerically analyze the performance of a project related cost and time
50
Burndown chart
Generally used on agile project Y axis shows work needs to get complete d
51
52
1 or above means your ahead of schedule
53
54