Schedule Management Flashcards
Plan Schedule Management PROCESS
Main output is schedule management plan
Documents how you will do the other 5 processes
States how to measure the schedule and how to fix it if there are any variances
Define Activities PROCESS
Main output is activity list, activity attributes, and Milestone list
Taking the work packages and breaking them down into activities
Activities are more detailed then work packages. Each work package usually contains many activities
^Once this is done you store them in the activities list.
Sequence Activities PROCESS
Main output is project schedule network diagram
Take the list of activities and put them in the order you will perform them
Estimate Activity Durations PROCESS
Main output is activity duration estimates
Analyze each activity to determine how long each will take
This will be used to create the project schedule
Develop Schedule PROCESS
Main output is schedule baseline, project schedule, schedule data, project calendars.
Process of creating project schedule and the schedule baseline.
You review everything you did in the previous processes to develop the schedule
This is an iterative process
Control Schedule PROCESS
Main Output is work performance info and change request
Controlling project work to ensure it will finish on the schedule basline
Activities List
Used to estimate the duration and cost of the project
Rolling wave Planning
A form of progressive elaboration
Work packages happening soon can be decomposed now
Work packages happening later will be decomposed at a later date when more details are known
Activity Attributes
More detailed info about each activity
This includes:
Resources needed to complete the activity
-Location of the activity
-Cost
-Assumptions
-Constraints
-Leads and lags
Relationship to other activities
Milestone
Consist of all project or phase milestones
activity that has no duration and is used to represent a major accomplishment
Example: Permit
Project schedule network diagram
A diagram that shows the order in which you will do each individual activity
Precedence Diagramming Method (PDM)
PDM maps out project development by creating a visual representation of critical paths and dependencies. The primary output of PDM is a project schedule network diagram.
Finish to Start (FS)
Finish activity A then you can start activity B
Activity A is the predecessor and activity B is the the successor
Finish to Finish FF
Need to finish at the same time, but not necessarily start at the same time
Start to Finish SS
Activity A must start before activity B can start
Start to Finish SF
Activity B cannot finish until activity A has started
Mandatory Dependencies
Also known has hard logic
You have to finish one activity to start the next activity
Discretionary Dependencies
Known as soft logic
Activities do not need to get done in a specific order
External Dependencies
Activities are dependent on activities outside the control of the project team
Internal Dependencies
Activities are dependent on activities outside control of the project team
Lead
Overlap between activities
EX you can start taping up fixtures after half of the furniture has been removed